The Docklands Light Railway (DLR) is an automated light metro system primarily serving the redeveloped Docklands area of London and providing a direct connection between London's two major financial districts, Canary Wharf and the City of London. First opened on 31 August 1987, the DLR has been extended multiple times, giving a total route length of 38 km (24 miles). Lines now reach north to Stratford, south to Lewisham, west to Tower Gateway and Bank in the City of London financial district, and east to Beckton, London City Airport and Woolwich Arsenal. An extension to Thamesmead is currently being proposed.
Docklands Light Railway | |
---|---|
Overview | |
Owner | Docklands Light Railway Ltd, part of Transport for London |
Area served | London |
Locale | Greater London |
Transit type | Light metro |
Number of lines | 3[1] |
Number of stations | 45 |
Daily ridership | 340,000 (daily average, DfT 2017) |
Annual ridership | 92.3 million (2022/23)[2] 19.6% |
Headquarters | Endeavour Square, E20[3] |
Website | tfl |
Operation | |
Began operation | 31 August 1987[4] |
Operator(s) | KeolisAmey Docklands Limited (Keolis 70%, Amey 30%) (2014–2033) |
Number of vehicles | 149 |
Train length | 2 or 3 vehicles per trainset |
Headway | 3–5 minutes |
Technical | |
System length | 38 km (24 mi)[5] |
No. of tracks | 2 |
Track gauge | 4 ft 8+1⁄2 in (1,435 mm) standard gauge |
Minimum radius of curvature | 125 ft (38 m) |
Electrification | Third rail, 750 V DC |
Top speed |
|
Docklands Light Railway | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Normal operations are automated, so there is minimal staffing on the 149 trains (which have no driving cabs) and at major interchange stations; the four below-ground stations are staffed, to comply with health and safety regulations for underground stations. The DLR was the first major railway infrastructure project in Britain where access for disabled people was considered, with level access into the train from platforms and lifts at all stations.
The DLR is operated and maintained by franchisee KeolisAmey Docklands (a joint venture of transport company Keolis and infrastructure support provider Amey) for Transport for London (TfL). Passenger numbers have increased as the network has expanded since its launch. In the financial year 2022/23, there were 92.3 million passenger journeys.
History
editBackground
editIn the 18th and 19th century, new docks were built east of the City of London to cater for the rapidly growing city. The last of these docks opened in 1921 in the Royal Docks. From the early 1960s, the docks began to decline as cargo was containerised and mechanised. The older docks did not have space to expand, and could not handle larger vessels.[7] The docks had been connected to the national railway network via the London and Blackwall Railway (L&BR), which was closed in 1966 for lack of traffic.[8] From the mid 1960s, the docks gradually closed down - leading to major job losses and economic deprivation.[7] In the 1970s, the opening of new deep water Tilbury container docks located further east in Essex exacerbated the issue, with the Royal Docks closing in 1981.[7]
Origins and development
editThroughout the 1970s, the government and the Greater London Council (GLC) put forward various plans to redevelop the Docklands area. The area was thought to have great potential for redevelopment, located close to the City of London with historic warehouses and large areas of water.[9]
In 1972, the London Docklands Study team commissioned Travis Morgan & Partners to propose redevelopment of the area. In 1973, they proposed, among other recommendations, that a "minitram" people-mover system capable of carrying up to 20 people in each unit should be constructed to connect the Docklands with the planned Fleet line tube railway terminus at Fenchurch Street railway station.[10] The Greater London Council formed a Docklands Joint Committee with the Boroughs of Greenwich, Lewisham, Newham, Southwark and Tower Hamlets in 1974 to undertake the redevelopment of the area. A light railway system was envisaged, terminating either at Tower Hill tube station or at nearby Fenchurch Street, but both options were seen as too expensive.
Nonetheless, in 1976 another report proposed a conventional tube railway for the area and London Transport obtained Parliamentary powers to build a line from Charing Cross station to Fenchurch Street, Surrey Docks (now Surrey Quays railway station), the Isle of Dogs, North Greenwich and Custom House to Woolwich Arsenal. This was intended to be the second stage of the Fleet line – which had been renamed the Jubilee line, the first stage of which opened in 1979 from Stanmore to Charing Cross. This would have cost around £325 million.[11] However, when the Thatcher Government came to power, the plans to extend the Jubilee line were halted and the new government insisted that a lower-cost option should be pursued.[10]
In July 1981, the government established the London Docklands Development Corporation (LDDC) to coordinate the redevelopment of the Docklands. The need to provide a cheap public transport solution led to it commissioning London Transport to evaluate a number of exclusively light rail options, using trams or tram like vehicles.[12] The cost of extending the Jubilee line to the area was now estimated to be around £450 million.[13]
The core of the route ran alongside the Great Eastern line out of London and south along the former London & Blackwall Railway line through the Isle of Dogs. Three terminus options were proposed at the west end, at Tower Hill, Minories and Aldgate East. The Tower Hill option would have required a low-level interchange to be constructed alongside the existing Underground station, but this would have been a very costly venture. The Minories option, a high-level station virtually on the site of the old Minories railway station, was selected and became the current Tower Gateway DLR terminus.[10] Aldgate East would have been perhaps the most ambitious of all of the options, as it originally envisaged a low-level connection with the District line that would have allowed DLR trains to run on London Underground tracks to a variety of central London destinations. However, it quickly became apparent that there was no capacity on the existing network for integrating the DLR into the Underground.[14]
Two southern terminus options were put forward, at Cubitt Town (today's Island Gardens station) and Tiller Road, on the west side of Millwall Dock, with two possible routes to reach them. A "western" route would have run from the Westferry station alongside West Ferry Road via Cuba Street, then either terminating at Tiller Road or continuing over Millwall Docks Cut to a terminus at Cubitt Town. The "central" option required the West India Docks to be infilled or bridged and would run down the middle of the peninsula, through what was at the time an area of derelict warehouses.[15] Ultimately this latter option was chosen, though the 1981 London Transport report warned that without extensive development around Canary Wharf the area would be "very isolated with poor traffic prospects" – as indeed it was, for a number of years.[16]
The northern terminus was proposed at Mile End, with options including street running down Burdett Road towards Limehouse or along the Mile End Road to turn south before using an old railway alignment to reach Poplar.[17]
A final report – prepared by the GLC, LDDC, government departments and London Transport – was published in June 1982, proposing a north–south route from Mile End to the Isle of Dogs, and an east–west route linking the Isle of Dogs to the City of London.[13][18] Even during the development of the line, proposals for future extensions were being envisaged and investigated.[13][19]
Parliamentary process and construction
editFollowing the publishing of the report, the Departments of the Environment and Transport agreed to provide £77 million towards construction of the extension, with a deadline of 1987.[20] The funding agreement also included conditions to maximise the use of modern technology, and that no ongoing subsidy would be available from government.[21]
Initially, the system was planned to be manually operated and having some stretches of street running.[22] During the Parliamentary process, the northern terminus of the line was changed to Stratford, as part of efforts to segregate the line from road and other railway traffic, as the LDDC were pushing for the line to use a "high tech automated system".[21] In 1984, the contract for the initial system was awarded to a GEC / John Mowlem joint venture, which proposed fully automated operation using light rail vehicles.[23]
The two Acts of Parliament that authorised the line to be built were passed in 1984 and 1985.[24] Construction of the system began shortly after in 1985, with the joint venture careful to minimise costs in light of the £77 million budget.[21] Two thirds of the route was built on underused or disused railway infrastructure, and station architecture used a kit-of-parts approach to save money.[25][26]
Initial system (1987–1990)
editThe railway was formally opened by Queen Elizabeth II on 30 July 1987,[27] and passenger services began on 31 August.[28][4] The initial system comprised two routes, from Tower Gateway and Stratford to Island Gardens, with a total length of 12.1 km (7.5 miles).[25] It was mainly elevated on disused railway viaducts or new concrete viaducts, and adopted disused surface railway formations between Poplar and Stratford. The trains were fully automated, controlled by computer, and had no driver; a Passenger Service Agent (PSA) on each train, originally referred to as a "Train Captain", was responsible for patrolling the train, checking tickets, making announcements and controlling the doors. PSAs could take control of the train in circumstances including equipment failure and emergencies.[29][30] A total of eleven units supplied by Linke-Hofmann-Busch comprised the first generation of the Docklands Light Railway rolling stock.[31]
The system was lightweight, with stations designed for trains of only a single articulated vehicle. The three branches totalled 13 km (8.1 miles), had 15 stations, and were connected by a flat triangular junction near Poplar. Services ran from Tower Gateway to Island Gardens and from Stratford to Island Gardens; the north side of the junction was used only for access to the Poplar depot.[32][28][33] The stations were mostly of a common design and constructed from standard components. A common feature was a short half-cylindrical glazed blue canopy. All stations were above ground and were generally unstaffed.[26] All stations featured lifts and level access into the train from platforms, catering for disabled people, people with small children and elderly people.[34][35]
Extensions to the City and the Royal Docks (1991–1994)
editThe initial system had a relatively low capacity, but the Docklands area very quickly developed into a major financial centre and employment zone, increasing traffic. In particular Tower Gateway, at the edge of the City of London, attracted criticism for its poor connections, as it did not connect directly with the nearby Tower Hill tube station or Fenchurch Street railway station. The criticism arose partly because the system usage was higher than expected.[36] Plans were developed, before the system opened, to extend it to Bank in the west and Beckton in the east.[37] Stations and trains were extended to two-unit length, and the system was expanded into the heart of the City of London to Bank through a tunnel, which opened in 1991 at a cost of £295 million.[38][39] This extension left Tower Gateway on a stub.
The original trains were not suitable for underground usage due to not meeting the fire safety laws for underground trains.[31] They were operated for a time on the above-ground sections only, and were later sold.
As the Canary Wharf office complex grew, Canary Wharf DLR station was redeveloped from a small wayside station to a large one with six platforms serving three tracks and a large overall roof, fully integrated into the malls below the office towers.[40]
The east of Docklands needed better transport connections to encourage development, and a fourth branch, towards Beckton, was planned, with several route options available.[41] A route from Poplar via Canning Town and the north side of the Royal Docks complex was chosen, and opened in March 1994 at a cost of £280 million.[28] Initially it was thought the line was likely to be underutilised, due to the sparse development in the area[42] and for this reason two additional stations at Thames Wharf (not to be confused with the later Thames Wharf proposal on the Woolwich branch) and Connaught were omitted.[43] As part of this extension, one side of the original flat triangular junction was replaced by a grade-separated junction west of Poplar. Poplar was rebuilt to give cross-platform interchange between the Stratford and Beckton lines, with a new grade-separated junction built east of the station at the divergence of the Stratford and Beckton lines. As part of the extension, a new, larger, depot was built at Beckton.
Extension to Greenwich & Lewisham (1996–1999)
editEarly on, Lewisham London Borough Council commissioned a feasibility study into extending the system under the River Thames. This led the council to advocate an extension via Greenwich and Deptford, terminating at Lewisham railway station.[44] The ambitions of the operators were supported by politicians in Parliament, including the future Labour Deputy Prime Minister John Prescott, and Lord Whitty; and by 1996 construction work had begun.[40][45][46]
The Lewisham extension opened on 20 November 1999, at a cost of £200 million funded mostly by the private sector as a Private finance initiative.[47][39] It left the Island Gardens route south of the Crossharbour turn-back sidings, and dropped gently to Mudchute, where a street-level station replaced the high-level one on the former London & Blackwall Railway viaduct. The line then entered a tunnel, following the route of the viaduct to a shallow subsurface station at Island Gardens, accessible by stairs or a lift. It crossed under the Thames to Cutty Sark in the centre of Greenwich, and surfaced at Greenwich railway station, with cross-platform interchange between the northbound track and the London-bound main line. The line snaked on a concrete viaduct to Deptford Bridge, before descending to Elverson Road at street level, close to Lewisham town centre, terminating in two platforms between and below the main-line platforms at Lewisham railway station, with buses stopping outside the station. The extension quickly proved profitable.[48]
Extensions to London City Airport & Woolwich (2004–2009)
editAn extension to London City Airport from the existing Beckton branch was explored in the mid-90s, at first via travelator from Royal Albert, and then in 1998 via a proposed lift-bridge over the dock with an intermediate station at West Silvertown.[49][50] The government initially supported this proposal, and in 1999 was developed to the route known today with a further extension to King George V. At this time, the further route to Woolwich Arsenal was developed with an intermediate station at Woolwich Reach, but was viewed as a longer term aspiration. The Woolwich Reach station (on the south bank of the Thames, at the site of the Marlborough Road ventilation and escape shaft), was descoped in 2000.
The extension was aided by a five-year programme of investment for public transport across London that was unveiled by Mayor of London Ken Livingstone on 12 October 2004.[51] On 2 December 2005, an eastward branch along the approximate route of the former Eastern Counties and Thames Junction Railway on the southern side of the Royal Docks complex opened from Canning Town to King George V via London City Airport.[52]
A further extension from King George V to Woolwich Arsenal opened on 10 January 2009, providing interchange with the North Kent main line, close to the stop on the Elizabeth line to Abbey Wood via West India and Royal Docks,[32] met by Private Finance Initiative funding.[53] Construction began in June 2005, the same month that the contracts were finalised,[54] and the tunnels were completed on 23 July 2007,[55] and formally opened by Boris Johnson, Mayor of London on 12 January 2009.[56] Following completion, the project was shortlisted for the 2009 Prime Minister's Better Public Building Award.[57]
The original Tower Gateway station was closed in mid-2008 for complete reconstruction. The two terminal tracks either side of a narrow island platform were replaced by a single track between two platforms, one for arriving passengers and the other for departing (Spanish solution). It reopened on 2 March 2009.[58][59]
As part of an upgrade to allow three-car trains, strengthening work was necessary at the Delta Junction north of West India Quay.[60] It was decided to include this in a plan for further grade separation to eliminate the conflict between services to Stratford and from Bank. A new timetable was introduced, with improved frequencies at peak hours. The new grade-separated route from Bank to Canary Wharf is used throughout the day, bypassing West India Quay station until mid-evening.[61] Work on this project proceeded concurrently with the three-car upgrade work and the 'diveunder' (sometimes referred to as a flyunder but DLR have coined the term in this instance 'diveunder'), and the improved timetable came into use on 24 August 2009.[62]
Upgrade to three-car trains (2007–2011)
editWith the development of the eastern Docklands as part of the Thames Gateway initiative and London's staging of the 2012 Summer Olympics, several extensions and enhancements were undertaken.[63]
Capacity was increased by upgrading for trains with three cars, each with four doors per side. The alternative of more frequent trains was rejected as the signalling changes needed would have cost no less than upgrading to longer trains and with fewer benefits.[64] The railway had been built for single-car operation, and the upgrade required both strengthening viaducts to take heavier trains and lengthening many platforms.[65] The extra capacity was useful for the 2012 Summer Olympics, which increased the use of London's transport network.[66] The main contractor for the expansion and alteration works was Taylor Woodrow.[67]
Elverson Road, Royal Albert, Gallions Reach and Cutty Sark have not been extended for three-car trains; such extension may be impossible in some cases. Selective door operation is used, with emergency walkways in case a door fails to remain shut. Cutty Sark station is underground, and both costs and the risk to nearby historic buildings prevent platform extension. The tunnel has an emergency walkway. Additional work beyond that needed to take the three-car trains was also carried out at some stations. This included replacing canopies with more substantial ones along the full platform length. A new South Quay station has been built 200 m (660 ft) east of the former location as nearby curves precluded lengthening. Mudchute now has a third platform.[68]
For this upgrade DLR purchased an additional 31 cars compatible with existing rolling stock.[69] The works were originally planned as three phases: Bank-Lewisham, Poplar-Stratford, and the Beckton branch. The original £200 million contract was awarded on 3 May 2007.[70] Work started in 2007 and Bank-Lewisham was originally due to be completed in 2009. However, the work programme for the first two phases was merged and the infrastructure work was completed by the end of January 2010. The Lewisham-Bank route now runs three-car trains exclusively. They started running on the Beckton branch on 9 May 2011.[71] Stratford to Lewisham and Bank to Woolwich Arsenal services sometimes operate as three-car trains; other routes run the longer trains when required.
Extension to Stratford International (2011)
editIn addition to the three-car station extensions, partly funded from the 2012 Olympics budget, a line was opened from Canning Town to Stratford and Stratford International railway station along the former North London Line of the national railway system, with additional stations. It parallels the London Underground Jubilee line for much of its length.
The extension to Stratford International, taking over the North London Line from Canning Town to Stratford, links the Docklands area with domestic high-speed services on High Speed 1. It was an important part of transport improvements for the 2012 Olympic Games, much of which were held on a site adjoining Stratford International.[72]
The first contract for construction work was awarded on 10 January 2007[73] and construction started in mid-2007. Originally scheduled to open in mid-2010,[74] the line opened on 31 August 2011.[75] On 11 November 2015 the Mayor of London announced that all stations on this line would be rezoned from zone 3 to zone 2/3.[76]
New stations were Canning Town, Star Lane, West Ham, Abbey Road, Stratford High Street and Stratford International. Of these, Canning Town, West Ham and Stratford are former North London Line stations, and Stratford High Street was built on the site of Stratford Market railway station.
From Canning Town to Stratford the extension runs parallel to the Jubilee line of the London Underground. As well as providing interchange with the adjacent Jubilee line stations, there are additional DLR stations at Star Lane, Abbey Road and Stratford High Street.
At Stratford new platforms were built for the North London Line at the northern end of the station. The old platforms (formerly 1 and 2) adjacent to the Jubilee line were rebuilt for the DLR, renumbered 16 (towards Stratford International) and 17 (towards Beckton/Woolwich Arsenal). Interchange between the Stratford International branch and DLR trains via Poplar is possible although the platforms are widely separated and at different levels. There is no physical connection between the two branches.
Relocation of Pudding Mill Lane station (2014)
editOne of the tunnel portals for Elizabeth line is on the original site of Pudding Mill Lane station. As a consequence, work was carried out to divert the DLR between City Mill River and the River Lea onto a new viaduct further south. This included a replacement station, which opened on 28 April 2014.[77][78] The former station stood on the only significant section of single track on the system, between Bow Church and Stratford.[79] The opportunity was taken to double the track in three stages, to improve capacity. There was originally no provision for works beyond the realigned section in the Crossrail Act.
Current system
editNetwork
editThe DLR has 38 km (24 miles) of tracks,[80] with 45 stations.[81] The three lines shown on the TfL DLR map have six branches: to Lewisham in the south, Stratford and Stratford International in the north, Beckton and Woolwich Arsenal in the east, and Central London in the west, splitting to Bank and Tower Gateway.[82]
The northern, southern and south-eastern branches terminate at the National Rail stations at Stratford, Stratford International, Lewisham and Woolwich Arsenal. Other interchanges with National Rail are at Limehouse, Greenwich and West Ham, while out-of-station interchanges for Oyster card holders are available between Shadwell DLR station and London Overground's station of the same name, and between Fenchurch Street and the DLR's western termini of Tower Gateway and Bank.[83]
Between Limehouse and Tower Gateway, the DLR runs parallel to the London, Tilbury and Southend line.
Services
editThe following services are operated in normal off-peak service from 26 September 2022:[84]
Off-peak service | |||
---|---|---|---|
Route | Trains per hour | Calling at | |
Bank – Lewisham | 12 | Shadwell, Limehouse, Westferry, West India Quay (Bank-bound only), Canary Wharf, Heron Quays, South Quay, Crossharbour, Mudchute, Island Gardens, Cutty Sark for Maritime Greenwich, Greenwich, Deptford Bridge, Elverson Road | |
Bank – Woolwich Arsenal | 6 | Shadwell, Limehouse, Westferry, Poplar, Blackwall, East India, Canning Town, West Silvertown, Pontoon Dock, London City Airport, King George V | |
Tower Gateway – Beckton | 6 | Shadwell, Limehouse, Westferry, Poplar, Blackwall, East India, Canning Town, Royal Victoria, Custom House for ExCeL, Prince Regent, Royal Albert, Beckton Park, Cyprus, Gallions Reach | |
Canning Town – Beckton | 6 | Royal Victoria, Custom House, Prince Regent, Royal Albert, Beckton Park, Cyprus, Gallions Reach | |
Stratford – Canary Wharf | 12 | Pudding Mill Lane, Bow Church, Devons Road, Langdon Park, All Saints, Poplar, West India Quay | |
Stratford International – Woolwich Arsenal | 6 | Stratford, Stratford High Street, Abbey Road, West Ham, Star Lane, Canning Town, West Silvertown, Pontoon Dock, London City Airport, King George V |
At peak times, these same services run, but with the frequency increased by 25 per cent. Additionally, in the morning peak, alternate Stratford – Canary Wharf services extend to Lewisham.
At terminal stations, trains reverse direction in the platforms, except at Bank where there is a reversing headshunt in the tunnel beyond the station. During service disruption or planned engineering work, trains can also turn back at Crossharbour and Mudchute. There is also capability for an additional shuttle from Canning Town to Prince Regent when exhibitions are in progress at the ExCeL exhibition centre, although this is not supported by any additional turnback infrastructure. Trains serve every station on the route, but trains from Bank to Lewisham do not call at West India Quay because they are routed along the diveunder track to avoid junction conflicts. When required, such as during engineering works or for special events, other routes may be operated, such as Beckton to Lewisham if the Bank and Tower Gateway branch is closed.
Future services
editThe new rolling stock to be introduced from 2024 onwards will support service improvements.[85]
Stations
editMost stations are elevated, with others at street level, in cutting or underground. Access to the platforms is mostly by staircase and lift, with escalators at some stations. From the outset the system has been fully accessible to wheelchairs; much attention was paid to quick and effective accessibility for all passengers.[86] The station platforms match the floor height of the cars, giving level access for passengers with wheelchairs or pushchairs.[34]
Most stations are of a modular design dating back to the initial system, extended and improved with two side platforms, each with separate access from the street, and platform canopies, although few examples remain of the original, distinctive rounded roof design. Stations are unstaffed, except the underground stations at Bank, Stratford International and Woolwich Arsenal for safety reasons, a few of the busier interchange stations, Canning Town, West Ham, and City Airport, which has a ticket office for passengers unfamiliar with the system. Canning Town, Custom House and Prince Regent are normally staffed on the platform whenever there is a significant exhibition at the ExCeL exhibition centre.
On 3 July 2007, DLR officially launched[87] an art programme called DLR Art,[88] similar to that on the London Underground, Art on the Underground. Alan Williams was appointed to produce the first temporary commission, called "Sidetrack", which portrays the ordinary and extraordinary sights, often unfamiliar to passengers, on the system and was displayed throughout the network.[89]
Fares and ticketing
editThe system is part of the London fare zone system, and Travelcards that cover the appropriate zones are valid. There are one-day and season DLR-only "Rover" tickets, plus a one-day DLR "Rail and River Rover" ticket for the DLR and City Cruises river boats. Tickets can be purchased from ticket machines at the entrances to platforms, and are required before accessing the platform. Passengers using Oyster pay-as-you-go[90] and contactless bank-cards need to touch both in and out of the system using card readers on automatic gates and platforms. There are no ticket barriers at DLR-only stations:[91] correct ticketing is enforced by random on-train inspections by PSAs. There are barriers at Bank, Canning Town, Woolwich Arsenal, West Ham and Stratford, where the DLR platforms are within a London Underground or National Rail barrier line. Users of payment cards who have failed to touch in at the start of the journey, and other passengers without a correct ticket, may be liable to a £80 penalty fare or prosecution for fare evasion.
Rolling stock
editThe DLR is equipped with 149 high-floor bi-directional single-articulated electric multiple units (EMUs). Each car has four double doors on each side, and two or three cars make up a train.[32][failed verification] There are no cabs because normal operations are automated; a small driver's console is concealed behind a locked panel at each end, from which the PSA can drive the car.[92] Consoles at each door opening allow the PSA to control door closure and make announcements whilst patrolling the train. With the absence of a driver's position, the fully glazed car ends provide a forward and rear view for passengers. The operational top speed is 64 km/h (40 mph).
Despite having high floors and being automated, the cars are derived from a German light-rail design intended for street running. All cars look similar but there have been several different types, some still in service, others sold to other operators. Units were purchased from Bombardier in 2005 and delivered between 2007 and 2010.[93]
Future rolling stock
editIn 2017, TfL opened bidding for new full-length, walk-through trains, subsequently awarded to CAF in 2019[94] and expected in service between 2024 and 2026,[85][95] following delivery and testing on the network of the initial units from January 2023.[85][95] Fifty-four 5-car trains were ordered, 33 to replace the existing stock and the rest to increase service capacity.[85] The design of the train increases internal capacity by 10%, which combined with service improvements will bring about a 65% increase in capacity from Stratford to Lewisham, and a doubling of capacity between Canning Town and Beckton/Woolwich Arsenal. The trains will feature charging points and air-conditioning.[96]
Depots
editThe network has two depots, at Poplar and Beckton. Poplar was opened with the initial line in 1987. Due to the constrained site, a new, larger, depot at Beckton was opened in 1994 – and is now the main maintenance depot and primary control centre for the network.[97] Track maintenance, off-peak train stabling, as well as the Operating and Maintenance Centre (OMC for TfL Staff) and the Hilton, Ritz and Dorchester Buildings houses the KeolisAmey Docklands franchise staff and the secondary back-up control centre are based at Poplar.[97]
Buckingham Group was awarded a £35m contract in 2021 to upgrade the Beckton DLR depot to accommodate the new B23 rolling stock. Works include construction of a new carriage wash, extension and modification to existing track, and new sidings for the new trains. This was scheduled for completion in September 2023, but Buckingham went into administration the previous month (August 2023). TfL appointed Morgan Sindall to complete the work, alongside a £90m deal to build a new train shed and deliver further sidings.[98]
Electrification
editTraction power is provided at 750 V DC via an unusual bottom contact third rail system.
Signalling technology
editOriginally, the DLR used signalling based on a fixed-block technology developed by GEC-General Signal and General Railway Signal. This was replaced in 1994 with a moving-block TBTC (Transmission Based Train Control) system developed by Alcatel, called SelTrac.[99] The SelTrac system was bought by Thales in 2007 and updates are provided by Thales Rail Signalling Solutions. The same technology is used by rapid transit systems including Vancouver's SkyTrain, Toronto's SRT, the San Francisco Municipal Railway and Hong Kong's MTR. The SelTrac S40 system has also been adopted by the London Underground Jubilee line and Northern line. Transmissions occur via an inductive loop cable between each train's Vehicle On-Board Controller (VOBC) and the control centre (VCC, SMC) at Beckton. If this link is broken and communication is lost between the VOBC and VCC, SMC, the train stops until it is authorised to move again. If the whole system fails the train can run in restricted manual at 19 km/h (12 mph) for safety until the system is restored and communication is re-established. Emergency brakes can be applied if the train breaks the speed limit during manual control or overshoots a fixed stopping point, or if it leaves the station when the route has not been set.[32] A secondary control centre is based at Poplar, the location of the original control centre, which can operate immediately should there be any issues with the primary at Beckton.[100]
Corporate affairs
editInfrastructure and ownership
editInitially, DLR was a wholly owned subsidiary of London Regional Transport. In 1992, ownership was transferred to the London Docklands Development Corporation (LDDC).[101] With the winding up of the LDDC in 1998, ownership passed to Department of the Environment, Transport and the Regions – before passing to Transport for London (TfL) in 2000.[39]
The infrastructure is owned by Docklands Light Railway Ltd,[102] part of the London Rail division of TfL, which also manages London Overground, London Trams, the IFS Cloud Cable Car and the Elizabeth line.[clarification needed] The infrastructure is maintained by the private company awarded the DLR franchise by TfL – currently KeolisAmey Docklands.[39][103] The Lewisham, City Airport and Woolwich Arsenal extensions were designed, financed, built and maintained by private companies (concessionnaires): City Greenwich Lewisham (CGL) Rail, City Airport Rail Enterprises (CARE), and Woolwich Arsenal Rail Enterprises (WARE).[104] In 2011, Transport Trading Limited (a subsidiary of TfL)[105] bought out the companies responsible for the City Airport and Woolwich Arsenal extensions, leaving only the Lewisham extension under private ownership until 31 March 2021.[106]
Operations
editInitially operated by London Regional Transport, the DLR was transferred to the LDDC in 1992. The LDDC appointed Brown and Root to run the system in 1993.[39] In 1994, it was announced that the DLR would be privatised, with operations and maintenance operated under franchise by the private sector.[39][107]
In 1997, the first franchise was awarded to Serco Docklands Limited for seven years;[108][109] operations began in April 1997.[110] A management buyout backed by Serco management later sold its shares to Serco. A two-year extension was granted in 2002. In February 2005 TfL announced that Balfour Beatty/Keolis, First Carillion, RATP/Transdev and Serco had been shortlisted to operate the franchise,[111] and in November 2005 TfL announced that Serco had retained the franchise for seven years from May 2006.[112][113]
In July 2012, TfL called for expressions of interest in bidding for the next DLR franchise,[114] and in January 2013 Serco's contract was extended until September 2014.[115] In April 2013, TfL announced that Go-Ahead/Colas Rail, Keolis/Amey, Serco and Stagecoach had been shortlisted to bid for the next franchise.[116] However, on 30 August, just before the bid submission date of 9 September 2013, Go-Ahead/Colas Rail pulled out.[117] The franchise was awarded to KeolisAmey Docklands Limited, with a handover date of 7 December 2014, expiring in April 2021 with an option for extension without going to tender.[103]
In August 2023, TfL went out for tender for the next DLR franchise, with KeolisAmey Docklands contract being extended to 2025 while bidding took place.[118] In February 2024, TfL announced that KeolisAmey, ComfortDelGro and Connecting Docklands (a joint venture of AtkinsRéalis and Go-Ahead Group) had been shortlisted to bid for the next franchise.[119] In October 2024, TfL announced that KeolisAmey retained the franchise, being awarded an 8 year contract to operate and maintain the DLR.[120]
Performance
editWithin a year of launch, annual passenger numbers reached 17 million,[121] increasing to 64 million in 2009,[121][122] and more than 80 million in 2011.[123] The most recent figures show 116.8 million annual passengers in the financial year to 31 March 2020.[124] The first five years had unreliability and operational problems,[125] but the system has since become highly reliable.[125] Research in 2008 showed 87% of the population of North Woolwich were in favour of the DLR.[126]
The Parliamentary Transport Select Committee favourably reviewed light rail in 2005,[127] and due to the success of the DLR, proposals for similar systems elsewhere emerged. The North and West London Light Railway was a plan for an orbital railway serving the other side of London.[128] The DLR has been successful, as have other recent light rail systems,[129] although it was earlier criticised for having been designed with insufficient capacity to meet the demand that quickly arose.[44][36][40]
Until 1 July 2013, the only bicycles that were allowed were folding ones.[130] DLR stated that this is because if evacuation is required, they would slow down the process. DLR cars, especially older rolling stock, were not designed with bicycles in mind – if they were allowed, they might obstruct doors and emergency exits.[131] Since January 2014, full-size bicycles have been allowed on DLR trains at off-peak hours and weekends (except Bank Station, where bicycles are not permitted for safety reasons).[132]
Business trends
editThe key available trends in recent years for the Docklands Light Railway are (years ending 31 March):
2010 | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Passenger revenue[a] (£m) | 74.9 | 88.8 | 102.8 | 122.1 | 130.0 | 146.2 | 158.4 | 166.5 | 168.3 | 171.6 | 168.8 | 54.3 | 104.9 |
Profit/Financial assistance[b] (£m) | −208.3 | −126.7 | −480.0 | −94.0 | −53.5 | −43.2 | −57.2 | −46.5 | −38.0 | −43.1 | −42.9 | −71.8 | −199.8 |
Number of passengers (m) | 69.4 | 78.3 | 86.1 | 100.0 | 101.6 | 110.2 | 116.9 | 122.3 | 119.6 | 121.8 | 116.8 | 39.9 | 70.0 |
Number of trains (at year end) | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 | 149 |
Notes/sources | [124] [133] |
[124] [134] |
[124] [134] |
[124] [135] |
[124] [135] |
[124] [136] |
[124] [136] |
[124] [137] |
[124] [137] |
[124] [138] |
[124] [139] |
[124] [140] |
[124] [141] |
Activities in financial years 2020/21 and 2021/22 were severely reduced by the impact of the coronavirus pandemic.
Future developments
editThamesmead extension
editMooted throughout the 2010s,[142][143] an extension across the River Thames to Thamesmead was first proposed in November 2019 as part of the Thamesmead and Abbey Wood OAPF (Opportunity Area Planning Framework).[144][145] Technical and feasibility work began in late 2020.[146] Stations would be located at Beckton Riverside and Thamesmead.[147][148] Public consultation into the extension began in 2024.[149] Estimated to cost around £1bn, the extension could open in the "early 2030s".[150]
Thames Wharf station
editAs part of the construction of the London City Airport extension, a gap in the viaduct due west of the western end of Royal Victoria Dock, between Canning Town and West Silvertown stations, was passively safeguarded for a future station when development came forward on the brownfield and industrial sites.[151] A station was also initially proposed at Oriental Road; however this was discounted at an early stage and the site is now flanked by several developments.[152] The potential of development on the land at Thames Wharf was on hold for until the late 2010s, as the area was being safeguarded for the route of the Silvertown Tunnel, a new Thames river crossing currently under construction on the site.[153]
As part of the 2018 budget, the Chancellor announced funding for the DLR to support development in the Royal Docks.[154] Following completion of the Silvertown Tunnel in the mid 2020s,[153] around 5,000 homes will be built on the site, and a new DLR station constructed.[151][155]
Tower Gateway station to Tower Hill interchange
editIn July 2014, a Transport Supporting Paper from the London Infrastructure Plan 2050 by the Mayor of London considered the closure of Tower Gateway DLR station and the branch serving it, with a replacement interchange being provided via new platforms at Tower Hill Underground station. This would increase train frequencies to Bank by approximately 30 per cent, thereby unlocking more capacity on the Bank branch.[156][note 1]
Extensions cancelled or not progressed
editGallions Reach to Dagenham Dock
editThe extension to Dagenham Dock in East London, via the Barking Riverside development was first proposed in 2003,[157] and was anticipated that the project could be completed and open for use by 2017,[158] at a cost of around £750 million.[159] In November 2008, the Mayor of London Boris Johnson announced that due to financial constraints the extension, along with a number of other transport projects, had been cancelled.[160] The Barking Riverside development is instead served by an extension of the London Overground to the new Barking Riverside station, which opened in July 2022.[161]
Bank to Charing Cross
editIn February 2006 a proposal to extend the DLR to Charing Cross station from Bank DLR branch was revealed.[79] The idea originates from a DLR "Horizon Study".[162]
While not confirmed, it is probable that the Charing Cross scheme would use the overrun tunnels between Charing Cross Jubilee platforms and slightly west of Aldwych. These tunnels were intended to be incorporated into the abandoned Phase 2 of the Fleet Line (Phase 1 became the original Jubilee line, prior to the Jubilee line Extension).[163] However they would need enlargement because the DLR loading gauge is larger than tube gauge and current safety regulations require an emergency walkway in the tunnel.[164]
Two reasons driving the proposal are capacity problems at Bank, having just one interchange between the DLR and the central portion of Underground, and the difficult journeys faced by passengers from Kent and South Coast between their rail termini and the DLR. Intermediate stations would be at City Thameslink/Ludgate Circus and Aldwych, which was intended for future connection with the proposed but now abandoned Cross River Tram.
City Thameslink to Euston and St Pancras
editIn 2011, strategy documents proposed a DLR extension to Euston and St Pancras.[165] Transport for London have considered driving a line from City Thameslink via Holborn north to the rail termini.[166][167][168] The main benefit of such an extension would be to broaden the available direct transport links to the Canary Wharf site. It would create a new artery in central London and help relieve the Northern and Circle lines and provide another metro line to serve the High Speed line into Euston.
Lewisham to Catford and Beckenham Junction
editThis possible extension was considered during the latest Horizon Study. The route would follow the Southeastern line and terminate between Catford and Catford Bridge stations. It has been seen as attractive to the district, as has the current terminus at Lewisham, built in an earlier extension.[169][170] A map published in 2010 by Transport for London suggests that a further extension from Catford to Forest Hill has also been considered.[166]
However, early plans showed problems due to Lewisham station being only marginally lower than the busy A20 road, which impedes any extension. The plan is however being revised.[171] When the Lewisham extension was first completed there were proposals to continue further to Beckenham to link it up with the Tramlink system. However, the way in which Lewisham station was built impedes this possible extension and it would prove costly to redevelop.[172]
Lewisham to Bromley North
editAnother proposal is to Bromley North by taking over the Bromley North Line, a short National Rail branch line which has no direct services into Central London. The scheme being considered by Transport for London[173] and the London Borough of Bromley[174] would convert the branch line to DLR operation. Although Lewisham Council planned to re-route the A20 road and redevelop the area south of Lewisham DLR station, the plans published in 2012 have no safeguarded route for an extension, making one unlikely.[175][176]
Accidents and incidents
edit- On 10 March 1987, before the system opened, a test train crashed through buffer stops at the original high-level Island Gardens terminus and was left hanging from the end of the elevated track. The accident has largely been attributed to unauthorised tests being run before the correct installation of the wayside safety system had been verified; an omission in the wayside system allowed the train to travel too fast on the approach to the terminus. The train was being driven manually at the time.[177][178][page needed][179][page needed] However, inside sources have stated these tests were being done to test the ATP if the train was entering the station too quickly, and after six successful tests, a software issue involving asynchronous computer systems caused the train to not receive the instructions to activate the ATP, cut off power from the motors, and apply the brakes soon enough to prevent the train from slowing down, causing the train to go through the buffers. Following this, the software was reworked and the braking distance was changed to ensure such incidents wouldn't happen in practice, and as a result may have possibly prevented a far more tragic incident from occurring.[180]
- On 22 April 1991, two trains collided at a junction on the West India Quay bridge during morning rush hour, requiring a shutdown of the system and evacuation of passengers by ladder.[181][182] One train was travelling automatically; the other was under manual control.[183]
- On 9 February 1996, the Provisional IRA blew up a lorry under a bridge near South Quay,[184] killing two people and injuring many others.[185] This caused £85 million of damage and marked an end to an IRA ceasefire in force at the time. Significant disruption was caused and a train was stranded at Island Gardens, unable to move until the track was rebuilt.
See also
editNotes
editReferences
edit- ^ "DLR Route Map" (PDF). tfl.gov.uk. Transport for London. May 2022. Retrieved 23 August 2024.
- ^ "Light rail and tram statistics, England: year ending March 2023". GOV.UK. Department for Transport. 5 September 2023. Retrieved 5 September 2023.
- ^ "DOCKLANDS LIGHT RAILWAY LIMITED overview - Find and update company information - GOV.UK".
- ^ a b Cross, David (1 September 1987). "Enthusiasts flock to busy opening day: Docklands Light Railway". The Times. London.
- ^ "Route kilometres open for passenger traffic on light rail and trams and undergrounds by system: Great Britain - annual from 1995/96". UK Government Department for Transport. Archived from the original on 20 September 2021. Retrieved 20 September 2021.
- ^ "TfL transparency". Department for Transport. Retrieved 30 November 2018.
- ^ a b c Jolly, Stephen (1986). Docklands Light Railway : official handbook 1987. Bob Bayman. Harrow Weald: Capital Transport. pp. 6–7. ISBN 0-904711-80-3. OCLC 18746528.
- ^ Christopher, John (30 September 2013). The London & Blackwall Railway. Amberley Publishing. p. 63. ISBN 978-1-4456-2187-6.
- ^ Jolly, Stephen (1986). Docklands Light Railway : official handbook 1987. Bob Bayman. Harrow Weald: Capital Transport. p. 7. ISBN 0-904711-80-3. OCLC 18746528.
- ^ a b c Pearce, Alan; Hardy, Brian; Stannard, Colin (November 2000). Docklands Light Railway Official Handbook. Harrow Weald: Capital Transport Publishing. pp. 4–5. ISBN 978-185414-223-8.
- ^ Jolly, Stephen (1986). Docklands Light Railway : official handbook 1987. Bob Bayman. Harrow Weald: Capital Transport. p. 5. ISBN 0-904711-80-3. OCLC 18746528.
- ^ Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. p. 5. ISBN 1-85414-223-2. OCLC 456423124.
- ^ a b c Greater London Council; London Docklands Development Corporation (Spring 1982). "A Light Railway for Docklands?" (PDF). Retrieved 22 April 2023.
- ^ Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. p. 6. ISBN 1-85414-223-2. OCLC 456423124.
- ^ Pearce, Hardy & Stannard 2000, p. 6
- ^ Pearce, Hardy & Stannard 2000, p. 7
- ^ Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. pp. 5–7. ISBN 1-85414-223-2. OCLC 456423124.
- ^ Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. p. 7. ISBN 1-85414-223-2. OCLC 456423124.
- ^ Greater London Council; London Docklands Development Corporation (July 1984). "Docklands Light Railway Beckton Extension" (PDF). Retrieved 22 April 2023.
- ^ Jolly, Stephen (1986). Docklands Light Railway : official handbook 1987. Bob Bayman. Harrow Weald: Capital Transport. p. 5. ISBN 0-904711-80-3. OCLC 18746528.
The cash outturn price was not to exceed £77m, to be funded equally by the Departments of Transport and of the Environment to the GLC and the LDDC.
- ^ a b c Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. p. 8. ISBN 1-85414-223-2. OCLC 456423124.
- ^ Bayliss, David. "What's New in European and Other International Light Rail Transit Projects?". TRB Special Report. 221 (Light Rail Transit: New System Successes at Affordable Prices): 48. Retrieved 24 July 2024.
- ^ "World Report". Railway Age. October 1984. p. 31.
- ^ "Docklands Light Railway (DLR)". Transport for London. Retrieved 22 April 2023.
Two bills passed in 1984 and 1985 authorised the DLR - construction began soon afterwards.
- ^ a b Pearce, Alan (2000). Docklands Light Rail : official handbook. Brian Hardy, Colin Stannard (4th ed.). Harrow: Capital Transport. p. 10. ISBN 1-85414-223-2. OCLC 456423124.
- ^ a b Jolly, Stephen (1986). Docklands Light Railway : official handbook 1987. Bob Bayman. Harrow Weald: Capital Transport. p. 10. ISBN 0-904711-80-3. OCLC 18746528.
- ^ Ford, Roger (September 1987). "Opening of the Docklands Light Railway". Modern Railways. London.
- ^ a b c "Docklands Light Railway (D.L.R.)". Exploring 20th Century London. Archived from the original on 15 March 2013. Retrieved 3 September 2009.
- ^ "Technology: Signalling & Control". Transport for London. Archived from the original on 30 September 2007. Retrieved 29 August 2007.
- ^ "The Docklands Light Railway, London, UK". BBC – h2g2. Archived from the original on 5 November 2012. Retrieved 29 August 2007.
- ^ a b McCarthy, Colin; McCarthy, David (2009). Railways of Britain – London North of the Thames. Hersham, Surrey: Ian Allan Publishing. p. 12. ISBN 978-0-7110-3346-7.
- ^ a b c d "Docklands Light Railway Capacity Upgrading, United Kingdom". Railway-Technology.com. Archived from the original on 15 June 2018. Retrieved 13 June 2014.
- ^ "Mayor of London – Transport Strategy – DLR". Greater London Authority. c. 2006. Archived from the original on 12 March 2008. Retrieved 19 March 2012.
- ^ a b "Monograph - "Starting from Scratch" - the development of transport in London Docklands (1997) - The Detailed Story (1)". London Docklands Development Corporation. 1997. Archived from the original on 5 January 2023. Retrieved 25 August 2021.
Another important principle established at this stage was that all stations and trains should allow for disabled access. This meant that lifts and ramps were available at all stations, and trains were designed with platform height floors.
- ^ Lloyd, David (3 October 1986). "Captains sought for Dockland Trains". LRT News. p. 4.
Stations on the line will have lifts as well as stairs to platform level ... "the lifts will be slow running to discourage people from using them all the time. They are primarily for disabled people, people with shopping and children and the elderly."
- ^ a b "New Games transport link marks 20 years of progress". London 2012 Official Blog. 13 January 2009. Archived from the original on 28 May 2009. Retrieved 24 June 2009.
- ^ "Hansard Written Answers". Parliamentary Debates (Hansard). 6 May 1987. Archived from the original on 6 October 2012.
- ^ "Ben Roskrow reports on Nuttal's extension of the Docklands Light Railway". Construction News. 16 February 1990. Archived from the original on 28 September 2010. Retrieved 25 June 2009.
- ^ a b c d e f Butcher, Louise (4 May 2010). "Railways: Docklands Light Railway (DLR)" (PDF). House of Commons Library. Archived (PDF) from the original on 9 June 2015. Retrieved 19 March 2022.
- ^ a b c "DLR history timeline". Transport for London. Archived from the original on 30 September 2007. Retrieved 3 September 2007.
- ^ "Options for the DLR Beckton Extension route". London Docklands Development Corporation. Archived from the original on 7 February 2012. Retrieved 23 February 2008.
- ^ Widdicombe, Gillian (30 March 1994). "Architecture: A driverless train, a blighted destination". The Independent. London. Archived from the original on 18 January 2012. Retrieved 24 June 2009.
- ^ "Map showing the Docklands Light Rail proposed extensions to Beckton and Lewisham, issued 1992". London Transport Museum. Retrieved 28 March 2022.
- ^ a b Wolmar, Christian (25 January 1995). "Crucial links hold key to the future: Docklands, a special report". The Independent. London. Archived from the original on 26 January 2012. Retrieved 24 June 2009.
- ^ "Prescott backs DLR airport extension". New Civil Engineer. Archived from the original on 2 October 2011. Retrieved 25 June 2009.
- ^ "DLR: Take off for airport link" (Press release). M2 Presswire. 18 February 1999. Retrieved 25 June 2009.[dead link]
- ^ De Haan, Judy (29 August 2000). "Getting Back on the Right Track (letter to the editor)". The Bolton News. Archived from the original on 3 May 2012. Retrieved 25 June 2009.
- ^ Withers, Malcolm (8 March 2001). "DLR helps Mowlem ride high at £25 million". London Evening Standard. Archived from the original on 25 October 2012. Retrieved 25 June 2009.
- ^ "Transport Plans for the London Area - East". 14 August 2020. Archived from the original on 14 August 2020. Retrieved 18 April 2022.
- ^ "LCY Extension Project: The Routes". Docklands Light Railway (Archived). Archived from the original on 29 June 2001. Retrieved 18 April 2022.
- ^ Muir, Hugh (12 October 2004). "Mayor unveils £10bn scheme for capital's transport". The Guardian. London. Archived from the original on 28 August 2013. Retrieved 28 June 2009.
- ^ Hamilton, Fiona; Coates, Sam; Savage, Michael (6 December 2005). "Docklands Light Railway reaches City airport". The Times. London. Retrieved 25 June 2009.[dead link]
- ^ "New DLR extension wins approval". BBC News. 26 February 2004. Archived from the original on 16 February 2006. Retrieved 24 June 2009.
- ^ "AMEC, RBoS jv finalise contract for DLR extension to Woolwich Arsenal". Forbes. New York. 6 January 2005. Retrieved 24 June 2009.[dead link]
- ^ "Tunnel extending Docklands Light Railway to Woolwich completed" (Press release). Transport for London. 23 July 2007. Archived from the original on 28 September 2007. Retrieved 29 June 2008.
- ^ "Mayor unveils DLR Woolwich Arsenal station" (Press release). Transport for London. 12 January 2009. Archived from the original on 25 April 2012. Retrieved 19 March 2012.
- ^ "DLR extension award". Construction News. 10 June 2009. Retrieved 24 June 2009.
- ^ "Tower Gateway Station – Now Open". Transport for London. Archived from the original on 2 July 2009. Retrieved 21 June 2009.
- ^ "DLR Terminal suddenly reopens: Taking passengers by surprise". East London Advertiser. Ilford. Archived from the original on 5 March 2009. Retrieved 21 June 2009.
- ^ Christopher 2013, p. 68
- ^ "Docklands Light Railway (DLR) Delta Junction Grade Separation" (PDF). Transport for London. Archived from the original (PDF) on 3 October 2007. Retrieved 21 June 2009.
- ^ "Docklands Light Railway – West India Quay/Poplar Junction Improvements". Transport for London. Archived from the original on 27 June 2009. Retrieved 1 August 2009.
- ^ "Docklands Light Railway – Development Projects". Transport for London. Archived from the original on 5 July 2008. Retrieved 9 July 2008.
- ^ "Docklands Light Railway – Three-carriage Capacity Enhancement Project". Transport for London. Archived from the original on 3 August 2008. Retrieved 9 July 2008.
- ^ "Longer trains for Docklands Line". BBC News. 31 July 2007. Retrieved 24 June 2009.
- ^ "Docklands Light Railway (DLR) 3 Car Enhancements Project". Arup. Archived from the original on 21 April 2019. Retrieved 24 June 2009.
- ^ "Taylor Woodrow wins £200m Docklands Light Railway project". Contract Journal. 3 May 2007. Archived from the original on 17 January 2016. Retrieved 24 June 2009.
- ^ "Mudchute third platform". London Connections. 11 April 2008. Archived from the original on 8 July 2011. Retrieved 29 June 2008.
- ^ Barrow, Keith (July 2006). "Olympic rail gets a head start". International Railway Journal. Archived from the original on 12 July 2012. Retrieved 12 March 2012.
- ^ "Extra carriage on every DLR train" (Press release). Transport for London. 3 May 2007. Archived from the original on 27 September 2011. Retrieved 10 June 2011.
- ^ "Docklands Light Railway ready for 2012 Games with three-car upgrade completed" (Press release). Transport for London. 10 May 2011. Archived from the original on 13 May 2011.
- ^ "£20m bullet trains to serve Olympic Park" (Press release). London2012.org. 28 September 2004. Archived from the original on 3 April 2013. Retrieved 6 July 2005.
- ^ "Major contract award signals start of work on DLR Stratford International Extension". Transport for London. 10 January 2007. Archived from the original on 22 March 2012. Retrieved 19 March 2012.
- ^ "Government gives green light to key 2012 rail link" (Press release). Transport for London. 25 October 2006. Archived from the original on 14 September 2011. Retrieved 8 August 2011.
- ^ "New £211m DLR extension connecting Olympic venues opens". BBC News. 31 August 2011. Archived from the original on 1 September 2011.
- ^ "Mayor announces real terms fares freeze | London City Hall". London.gov.uk (Press release). 11 November 2015. Retrieved 17 November 2016.
- ^ "New DLR station opens at Pudding Mill Lane". Transport for London. 28 April 2014. Archived from the original on 27 April 2015. Retrieved 20 April 2015.
- ^ "Pudding Mill Lane Station To Be Rebuilt". Londonist. 28 July 2011. Archived from the original on 12 August 2011. Retrieved 13 August 2011.
- ^ a b Abbott, James (March 2006). "DLR aims for Charing Cross". Modern Railways. London. p. 54.
- ^ "Increased services for Docklands Light Railway routes" (Press release). Transport for London. 24 August 2015. Archived from the original on 29 June 2016.
- ^ "London's transport - a history: Docklands Light Railway (DLR)". Transport for London. Archived from the original on 15 June 2014. Retrieved 13 June 2014.
- ^ "Docklands Light Railway". visitlondon.com. Official London Guide. Archived from the original on 23 February 2012. Retrieved 19 March 2012.
- ^ "OSI List". oyster-rail.org.uk. October 2014. Archived from the original on 20 March 2015. Retrieved 14 April 2015.
- ^ "New DLR timetable promises quicker, easier and more comfortable journeys". Transport for London. 2 September 2022. Retrieved 26 September 2022.
- ^ a b c d "Improving the DLR". Transport for London. Retrieved 12 February 2023.
- ^ "DLR was the first fully accessible railway in the UK, making access much easier for everyone". Transport for London. Archived from the original on 30 May 2012. Retrieved 4 March 2012.
- ^ "Docklands Light Railway draws up public arts strategy" (Press release). Transport for London. 3 July 2007. Archived from the original on 25 April 2012. Retrieved 4 March 2012.
- ^ "The DLR Public Arts Programme". DLR Art. Archived from the original on 9 May 2012. Retrieved 5 August 2010.
- ^ "Alan Williams – Sidetrack". Docklands Light Railway. Archived from the original on 29 August 2009. Retrieved 25 June 2009.
- ^ "London jetpack: London Oyster travelcard". studentjetpacks.com. Archived from the original on 30 May 2012. Retrieved 21 June 2009.
- ^ Webster, Ben; Clennell, Andrew (5 January 2004). "Tube errors may cost you dear". The Times. London.
- ^ "Unmanned Train: DLR Respond". The Londonist (blog). 2 November 2007. Archived from the original on 22 February 2012. Retrieved 19 March 2012.
- ^ "Bombardier receives a $94 million US order from Docklands Light Railway for automatic Light Rail cars to be used in London, UK" (Press release). Montreal: Bombardier. 4 May 2005. Archived from the original on 21 August 2009. Retrieved 14 July 2009.
- ^ "CAF wins driverless trains contract in London" (Press release). Guipúzcoa: CAF. 12 June 2019.
- ^ a b Smith, Roger (9 February 2023). "Mayor of London views first new Docklands Light Railway train". Rail Advent. Retrieved 12 February 2023.
- ^ "TfL opens bidding for 43 new DLR trains". Rail Technology Magazine. 20 November 2017. Archived from the original on 1 December 2017.
- ^ a b Pearce, Alan (2006). Docklands Light Railway : official handbook. Brian Hardy, Colin Stannard, Capital Transport (5th ed.). Harrow: Capital Transport. ISBN 1-85414-298-4. OCLC 137312784.
- ^ Rogers, Dave (4 April 2024). "Buckingham collapse delays DLR job by months, TfL confirms". Building. Retrieved 4 April 2024.
- ^ Pearce, Hardy & Stannard 2000, p. 66
- ^ "Franchise Agreement: Docklands Light Railway Limited and Keolis Amey Docklands Limited relating to the Docklands Light Railway" (PDF). Transport for London. 17 July 2014. p. 14. Archived (PDF) from the original on 20 November 2015.
- ^ "About TfL - Culture & heritage - London's transport a history - Docklands Light Railway (DLR)". Transport for London. Retrieved 19 March 2022.
- ^ "URI". Data.companieshouse.gov.uk. 13 October 2011. Archived from the original on 31 March 2017. Retrieved 17 November 2016.
- ^ a b "French firm wins 7-year Docklands Light Rail franchise". BBC News. 4 July 2014. Archived from the original on 24 September 2015.
- ^ "DLR management". Transport for London. Archived from the original on 30 September 2012. Retrieved 10 June 2011.
- ^ "TfL Subsidiary Company Structure" (PDF). Transport for London. Archived from the original (PDF) on 13 October 2012.
- ^ "TfL expects £250m saving from buying Docklands Light Railway PFI concessionaires". Railway Gazette. London. 6 December 2011. Archived from the original on 24 September 2015.
- ^ Stevenson, Tom (27 October 1994). "Docklands railway will be privatised". The Independent. Retrieved 3 October 2024.
- ^ "URI". Data.companieshouse.gov.uk. 13 October 2011. Archived from the original on 13 August 2016. Retrieved 17 November 2016.
- ^ "DLR management | Transport for London". Archived from the original on 30 September 2012. Retrieved 1 October 2012.
- ^ "Acquisition of DRML Shares" (Press release). Serco. 1997. Archived from the original on 13 March 2013.
- ^ "Four Pre-Qualify for DLR Franchise" (Press release). Transport for London. 15 February 2005. Archived from the original on 13 November 2013.
- ^ "Serco appointed preferred bidder for £400m Docklands Light Rail service" (Press release). Serco. 22 November 2005. Archived from the original on 13 March 2013.
- ^ "DLR awards new franchise to Serco" (Press release). Transport for London. 8 March 2006. Archived from the original on 13 November 2013.
- ^ "Docklands Light Rail franchise contract". OJEU tender. 13 July 2012.[permanent dead link]
- ^ "DLR operating contract extended until September 2014" (Press release). Transport for London. 7 January 2013. Archived from the original on 17 January 2013. Retrieved 7 January 2013.
- ^ "DLR announces short list of bidders for new franchise" (Press release). Transport for London. 17 April 2013.
- ^ Thomas, Natalie (31 August 2013). "Go-Ahead forced to pull out of DLR contest". The Daily Telegraph. London. Archived from the original on 25 September 2015.
- ^ Preston, Robert (25 August 2023). "TfL tenders next Docklands Light Railway operating contract". Modern Railways.
- ^ "Three shortlisted for Docklands Light railway operating contract". Railway Gazette International. 19 February 2024. Retrieved 3 October 2024.
- ^ "KeolisAmey retains the franchise to operate the DLR". Transport for London. 3 October 2024. Retrieved 3 October 2024.
- ^ a b "Docklands Light Railway performance". Transport for London. Archived from the original on 23 January 2012. Retrieved 19 March 2012.
- ^ "Docklands Light Railway carries 60 million passengers" (Press release). Transport for London. 4 April 2007. Archived from the original on 25 April 2012. Retrieved 4 March 2012.
- ^ "Client News - DLR now carries more than 10 times the population of London per year". Flagship Consulting. 21 June 2012. Archived from the original on 7 April 2014. Retrieved 28 June 2014.
- ^ a b c d e f g h i j k l m n o "Light rail and tram statistics (LRT)". Department for Transport. 25 June 2020. Retrieved 11 July 2020.
- ^ a b "DLR: resolving the problems". London Docklands Development Corporation. Archived from the original on 26 April 2012. Retrieved 11 July 2008.
- ^ "North Woolwich Research: Changes, 2006–2008 – The influence of Docklands Light Railway" (PDF). Social Research Associates. July 2008. Archived from the original (PDF) on 16 July 2011. Retrieved 26 June 2009.
- ^ "Horses for Courses: The Advantages of Light Rail". Commons Transport Select Committee. UK Parliament. 3 April 2005. Archived from the original on 28 July 2012.
- ^ Flintoff, John-Paul (17 September 2009). "Orbital rail the solution to city congestion?". The Times (Environment blog). London. Archived from the original on 25 September 2009. Retrieved 16 December 2009.
- ^ "Light Rail – the Solution to Inner-City Chaos?". Railway-Technology.com. 22 May 2008. Archived from the original on 29 February 2012. Retrieved 19 March 2012.
- ^ "Bikes on public transport". Transport for London. Archived from the original on 27 May 2013. Retrieved 27 January 2013.
- ^ Low, Valerie (6 August 2007). "Last one in the water is toast". London Evening Standard. Archived from the original on 6 June 2011. Retrieved 27 January 2013.
- ^ ibikelondon (18 January 2014). "i b i k e l o n d o n: Good news! From today you can take your bike on the Docklands Light Railway". Ibikelondon.blogspot.co.uk. Archived from the original on 18 October 2016. Retrieved 17 November 2016.
- ^ "Transport for London Financial Statements for the year ended 31 March 2010" (PDF). TfL. 23 June 2010. Archived (PDF) from the original on 7 November 2017. Retrieved 12 November 2021.
- ^ a b "Transport for London Financial Statements for the year ended 31 March 2012" (PDF). TfL. 27 June 2012. Archived (PDF) from the original on 16 October 2015. Retrieved 12 November 2021.
- ^ a b "Transport for London Financial Statements for the year ended 31 March 2014" (PDF). TfL. 3 July 2014. Archived (PDF) from the original on 11 January 2016. Retrieved 12 November 2021.
- ^ a b "Transport for London Financial Statements for the year ended 31 March 2016" (PDF). TfL. 19 July 2016. Archived (PDF) from the original on 11 September 2016. Retrieved 12 November 2021.
- ^ a b "Transport for London Financial Statements for the year ended 31 March 2018" (PDF). TfL. 25 July 2018. Archived (PDF) from the original on 27 August 2018. Retrieved 12 November 2021.
- ^ "Transport for London Financial Statements for the year ended 31 March 2020 (Draft)" (PDF). TfL. 31 May 2020. Archived from the original (PDF) on 12 July 2020. Retrieved 11 July 2020.
- ^ "Transport for London Financial Statements for the year ended 31 March 2020" (PDF). TfL. 29 July 2020. Archived (PDF) from the original on 29 August 2020. Retrieved 20 March 2021.
- ^ "Transport for London Annual Report and Statement of Accounts 2020/21" (PDF). TfL. 28 July 2021. Archived from the original (PDF) on 3 November 2021. Retrieved 13 November 2021.
- ^ "Transport for London Annual Report and Statement of Accounts 2021/22" (PDF). TfL. 27 September 2022. Retrieved 6 June 2023.
- ^ Mayor of London (10 October 2016). "East London Crossings (8)". Mayor's Question Time. Retrieved 17 April 2020.
- ^ "DLR extension to provide 11,500-home Thamesmead boost". Inside Housing. 4 October 2016. Retrieved 17 April 2020.
- ^ Leeming, Lachlan (30 January 2020). "See DLR extension plans for Thamesmead and Abbey Wood". Bexley Times. Archived from the original on 29 September 2020. Retrieved 17 April 2020.
- ^ "Workshops about the future of Thamesmead and Abbey Wood opened to public". News Shopper. Petts Wood. 31 January 2020. Retrieved 17 April 2020.
- ^ "TfL and partners commence feasibility work on extending DLR into Thamesmead" (Press release). Transport for London. 21 December 2020. Retrieved 21 December 2020.
- ^ "Thamesmead and Abbey Wood Opportunity Area". Greater London Authority. 21 December 2020. Archived from the original on 21 December 2020. Retrieved 21 December 2020.
- ^ "Thamesmead and Abbey Wood OAPF - OAPF Transport Strategy" (PDF). Greater London Authority. December 2020. pp. 25–26. Archived (PDF) from the original on 27 January 2021. Retrieved 17 April 2020.
- ^ Vickers, Noah (5 February 2024). "Londoners to have their say on plans for cross-river DLR extension". Evening Standard. Retrieved 5 February 2024.
- ^ "FAQs | Extending the Docklands Light Railway to Beckton Riverside and Thamesmead | Have Your Say Transport for London". haveyoursay.tfl.gov.uk. Retrieved 5 February 2024.
the extension could be open in the early 2030s ... We think it could cost around £1bn (2022 prices)
- ^ a b "Coming soon: a new stop on the DLR". The Royal Docks. Retrieved 17 April 2020.
- ^ "DLR Horizon 2020 Study Business Case Appraisal" (PDF). What Do They Know. ARUP. July 2005. p. 10. Archived (PDF) from the original on 8 November 2011. Retrieved 24 January 2022.
- ^ a b "Improvements and Projects - Silvertown Tunnel". Transport for London. Retrieved 17 April 2020.
- ^ Long, Rhiannon (2 November 2018). "Chancellor pledges £291million to build homes around the Isle of Dogs and Royal Docks". Newham Recorder. Archived from the original on 3 November 2018. Retrieved 17 April 2020.
- ^ "Thameside West". Keystone. Archived from the original on 6 February 2020. Retrieved 17 April 2020.
- ^ a b "London Infrastructure Plan 2050: Transport Supporting Paper" (PDF). London City Hall. p. 143. Archived (PDF) from the original on 6 February 2018. Retrieved 6 February 2018.
- ^ "DLR extension planned". New Civil Engineer. 1 March 2003. Retrieved 15 April 2020.[permanent dead link]
- ^ "Docklands Light Railway - Dagenham Dock: Key Project Milestones". Transport for London. Archived from the original on 15 June 2009.
- ^ Johnson, Marc (12 September 2017). "In focus: London Overground's Barking Riverside Extension". RailStaff. Retrieved 15 April 2020.
- ^ "TfL scraps projects and cuts jobs". BBC News. 6 November 2008. Retrieved 15 April 2020.
- ^ Emmett, Conrad (26 July 2022). "Barking Riverside station opening celebrated". RailBusinessDaily. Business Daily Group. Retrieved 2 April 2023.
- ^ Ove Arup & Partners Ltd. (July 2005). "Bank-Aldwych-Charing Cross (E2)" (PDF). DLR Horizon 2020 Study: Business Case Appraisal. Docklands Light Railway Ltd. p. 34. Archived (PDF) from the original on 8 November 2011. Retrieved 19 October 2012.
- ^ Feather, Clive. "Jubilee Line, A Modern Tube". Clive's UndergrounD Line Guides (CLUG). Archived from the original on 24 April 2012. Retrieved 26 June 2008.
- ^ "The long and confusing history that explains why Charing Cross and Embankment are so weird | CityMetric". citymetric.com. Archived from the original on 7 April 2020. Retrieved 7 April 2020.
- ^ "TfL Moots New DLR Routes, Including Victoria And St Pancras". Londonist. 3 May 2011. Archived from the original on 7 July 2014. Retrieved 17 November 2016.
- ^ a b "Potential DLR extensions" (PDF). Transport for London. 21 September 2010. Archived from the original (PDF) on 22 March 2012. Retrieved 28 January 2013.
- ^ "Archived copy". Archived from the original on 12 December 2017. Retrieved 11 December 2017.
{{cite web}}
: CS1 maint: archived copy as title (link) - ^ "Archived copy" (PDF). Archived (PDF) from the original on 11 December 2017. Retrieved 11 December 2017.
{{cite web}}
: CS1 maint: archived copy as title (link) - ^ Wilkes, Roger (19 June 2002). "One long picnic, it certainly ain't". The Daily Telegraph. London. Archived from the original on 11 November 2012. Retrieved 24 June 2009.
- ^ "DLR takes off". Contract Journal. 6 May 2004. Archived from the original on 9 July 2012. Retrieved 24 June 2009.
- ^ "DLR to Catford". Always Touch Out. 27 October 2007. Archived from the original on 13 May 2008. Retrieved 9 July 2008.
- ^ "Bakerloo line extension. Background to Consultation Summary Report. October 2019" (PDF). Transport for London. Archived (PDF) from the original on 24 March 2020. Retrieved 24 March 2020.
- ^ "Could the DLR or Bakerloo line be coming to Bromley?". This is Local London. 23 January 2012. Archived from the original on 4 March 2016. Retrieved 26 January 2013.
- ^ "Future Rail and Tram Links to Bromley" (PDF). Report No. ES12004. London Borough of Bromley. 18 January 2012. Archived (PDF) from the original on 4 June 2013. Retrieved 26 January 2013.
- ^ "Masterplan". Lewisham Gateway: Phase A Consultation. Lewisham Council. December 2012. Archived from the original on 21 May 2013. Retrieved 27 January 2013.
- ^ "The Past and Future of the Bromley North Branch". London Reconnections. 25 January 2013. Archived from the original on 28 January 2013. Retrieved 26 January 2013.
- ^ "London Docklands Light Railway; Northern Line's Dot-Matrix Indicators". RISKS Digest. Vol. 5, no. 29. 13 August 1987. Article 3. Archived from the original on 24 August 2007.
- ^ "Report on the Docklands Light Railway Accident Which Occurred at Island Gardens Station on 10 March 1987". Modern Railways. London. May 1987.
- ^ "'Unauthorised Tests' Caused DLR Crash". Modern Railways. London. June 1987.
- ^ The Island Gardens Accident: What Really Happened, 14 March 2021, retrieved 12 July 2023
- ^ Kamens, Jonathan I. (23 April 1991). "Another commuter train wreck in London". RISKS Digest. Vol. 11, no. 52. Archived from the original on 26 July 2007.
- ^ "Computer-controlled commuter trains collide in east London". United Press International. 22 April 1991.
- ^ Batten, Ian G. (25 April 1991). "Trains collide in east London". RISKS Digest. Vol. 11, no. 54. Archived from the original on 22 September 2007.
- ^ Tumposky, Ellen; Gentile, Don (10 February 1996). "Blast shatters London, Adams Presumes IRA's Responsible". New York Daily News. Archived from the original on 12 September 2009. Retrieved 12 November 2008.
- ^ "Docklands bomb ends IRA ceasefire". BBC News. 10 February 1996. Archived from the original on 21 March 2012. Retrieved 2 January 2010.
Further reading
edit- Jolly, Stephen; Bayman, Bob (November 1986). Docklands Light Railway Official Handbook. Harrow Weald: Capital Transport Publishing. ISBN 978-0-904711-80-6.
- Gonsalves, B.F.; Deacon, R.W.; Pilgrim, D; Pritchard, B.P. (October 1991). "Docklands Light Railway and Subsequent Upgrading". 90. Proceedings of the Institution of Civil Engineers. OCLC 24833359.
{{cite journal}}
: Cite journal requires|journal=
(help)
External links
editWest: | Crossings of the River Thames | East: |
---|---|---|
Jubilee line between Canada Water and Canary Wharf |
Lewisham branch, between Island Gardens and Cutty Sark |
Greenwich Foot Tunnel |
Woolwich foot tunnel | Woolwich branch, between King George V and Woolwich Arsenal |
Dartford Cable Tunnel |