Tsumeb Biomass Power Station

Tsumeb Biomass Power Station, also Otjikoto Biomass Power Station, is a 40 MW (54,000 hp) biomass-fired thermal power plant under development in Namibia. The power station is owned and under development by NamPower, the national electricity utility company. As raw material, the power station is designed to use wood chips.[1]

Tsumeb Biomass Power Station
Map
Tsumeb Biomass Power Station
Official nameOtjikoto Biomass Power Station
CountryNamibia
LocationTsumeb, Oshikoto Region
Coordinates19°13′26″S 17°42′30″E / 19.22389°S 17.70833°E / -19.22389; 17.70833
StatusUnder construction
Construction began2024
Commission date2027 Expected
Construction costUS$152 million
Owner(s)NamPower
Thermal power station
Primary fuelBiomass
Power generation
Nameplate capacity40 MW (54,000 hp)
Capacity factor300 GWh

Location

edit

The power plant is under construction approximately 12 kilometres (7 mi), north of the town of Tsumeb, in the Oshikoto Region of Namibia.[1] Tsumeb is located approximately 433 kilometres (269 mi) northeast of Windhoek, the largest city and national capital of the country.[2]

Overview

edit

The 40 MW power-generating plant is designed to use as raw material, wood chips derived from "brush wood", that grows abundantly in the locality where the power station is located. NamPower, the owner/developer of the power station intends to integrate the power generated here into the Namibian grid. The power station will burn wood chips to heat water and produce steam. The steam will then be used to turn turbines and generate electricity.[1][3][4][5]

Construction costs and funding

edit

Financing was sourced from various sources as outlined in the table below. The construction budget is calculated as US$151.83 million.[1][3]

Sources of Funding For Tsumeb Biomass Power Station
Rank Funding Partner Millions of US$ Percentage Notes
1 French Development Agency
100.00
65.86
Loan[1][3]
2 Mitigation Action Facility
26.96
17.76
Grant[1][3]
3 Government of Namibia
21.64
14.25
Equity[1][3]
4 French Facility for Global Environment
3.23
2.13
Grant[1][3]
Total
151.83
100.00

Contractor and timeline

edit

The selected engineering, procurement and construction contractor is Dong Fang Electric International Corporation (DFEIC) of China. Construction is expected to start in H1 2024 and commercial commissioning is expected in Q1 2027.[1][3][4]

Other considerations

edit

Several benefits are expected to accrue from this project including:[4]

  1. It has been estimated that around N$21 billion (US$1.14 million) in economic benefits could be harvested, "including increased groundwater recharge and improved agricultural productivity in harvested areas".[4]
  2. The project increases the country's generation capacity as it strives to become a net energy exporter by 2030.[4]
  3. This power station is part of Namibia's efforts to reduce dependency on imported electricity.[4]

See also

edit

References

edit
  1. ^ a b c d e f g h i Matthew Dlamini (5 June 2024). "Tsumeb To Get Biomass Power Station". The Namibian. Windhoek, Namibia. Retrieved 13 June 2024.
  2. ^ Google (13 June 2024). "Road Distance Between Tsumeb, Namibia And Windhoek, Namibia" (Map). Google Maps. Google. Retrieved 13 June 2024.
  3. ^ a b c d e f g "Namibia: Construction Begins On 40 MW Biomass Power Plant". Energy Capital & Power. Cape Town, South Africa. 29 May 2024. Retrieved 13 June 2024.
  4. ^ a b c d e f Niël Terblanché (30 May 2024). "NamPower Set To Launch N$2 Billion Biomass Power Plant". Windhoek Observer. Windhoek, Namibia. Retrieved 13 June 2024.
  5. ^ O+GR (26 October 2023). "Namibia Launches Tender For EPC Contract For 40 MW Biomass Power Station". Africa Oil & Gas Report (O+GR). Lagos, Nigeria. Retrieved 13 June 2024.
edit