Nachtigal Hydroelectric Power Station

The Nachtigal Hydroelectric Power Station is a 420 megawatt run-of-the-river hydroelectric power station under development in Cameroon across the Sanaga River, which harnesses the energy of the Nachtigal Falls. The development rights were granted to Nachtigal Hydro Power Company (NHPC), a company owned by a consortium comprising (a) Électricité de France (b) International Finance Corporation and (c) the Government of Cameroon. A 35-year power purchase agreement is in place, between Eneo Cameroon S.A. and NHPC.[1]

Natchigal Dam
Nachtigal Hydroelectric Power Station is located in Cameroon
Nachtigal Hydroelectric Power Station
Location of Natchtigal Power Station
Placement on map is aptedproximate
Nachtigal Hydroelectric Power Station is located in Africa
Nachtigal Hydroelectric Power Station
Nachtigal Hydroelectric Power Station (Africa)
Nachtigal Hydroelectric Power Station is located in Earth
Nachtigal Hydroelectric Power Station
Nachtigal Hydroelectric Power Station (Earth)
LocationNatchtigal, Cameroon
Coordinates04°21′03″N 11°38′00″E / 4.35083°N 11.63333°E / 4.35083; 11.63333
Construction began2018
Opening dateJuly 2024 Expected
Construction cost€1.2 billion
Owner(s)Nachtigal Hydro Power Company
Dam and spillways
Type of damRCC Gravity dam
ImpoundsSanaga River
Height14 m
Length2000 m
Reservoir
Total capacity27.9E6 m³
Surface area4.21 km²
Power Station
Operator(s)Nachtigal Hydro Power Company
Commission dateJuly 2024 Expected
Turbines7 x GE Francis 60 MW
Installed capacity420 MW

Location edit

The dam lies across the Sanaga River, about 65 kilometres (40 mi) north-east of Yaoundé, the capital city of Cameroon.[2]

Overview edit

The design calls for a gravity dam with a power potential of 420 megawatts, powered by seven turbines, each with a capacity of 60 megawatts. The roller-compacted concrete (RCC) dam will create a reservoir with a surface area of 4.21 square kilometres (1,040 acres), capable of storing 2.78 million m³ of water.[1]

As part of this project, NHPC the concessionaire, will construct a double circuit 225 kilovolt high voltage transmission line measuring 50.3 kilometres (31 mi) in length, that will transmit the generated power to a substation where it will be integrated into the national electricity grid. Once the high voltage transmission line is constructed and operational, ownership, operation and maintenance will transfer to National Electricity Transmission Company (Sonatrel).[1]

Ownership edit

The power station is owned by the special purpose company named Nachtigal Hydro Power Company (NHPC). The table below illustrates the shareholding in NHPC.

Shareholding In Nachtigal Hydro Power Company
Rank Shareholder Domicile Percentage Notes
1 Électricité de France France
40.00
[1][3]
2 International Finance Corporation United States
20.00
[1][3]
3 Government of Cameroon Cameroon
15.00
[1][3]
4 Africa50 Ivory Coast
15.00
[1][3]
5 Stoa Infra & Energy France
10.00
[1][3]
Total
100.0

Construction costs edit

The estimated costs for the dam and power plant was €1.2 billion in 2018. Approximately €300 million (25 percent) was raised internally by the NHPC consortium as equity investment. The remaining amount, about €900 million, was borrowed from the eleven international financiers and four Cameroonian banks. Some of the lenders to this project include the following:[1][4]

Timeline and commissioning edit

In December 2021, Afrik21 reported that the first 60 megawatt turbine was expected to be commissioned in July 2023. The final and seventh of equally rated turbines is expected to come online in July 2024.[5]

See also edit

References edit

  1. ^ a b c d e f g h i NS Energy (2018). "Nachtigal Hydro Power Plant". United Kingdom: NS Energy Business. Retrieved 5 June 2021.
  2. ^ "Nachtigal Hydropower Project".
  3. ^ a b c d e Boris Ngounou (6 December 2018). "Cameroon: Nachtigal Hydropower Company's capital passes from 3 to 5 shareholders". Paris, France: Afrik21.africa. Retrieved 5 June 2021.
  4. ^ Boris Ngounou (9 November 2018). "Cameroon: Funding for Nachtigal hydroelectric power plant (420 MW) complete". Paris, France: Afrik21.africa. Retrieved 5 June 2021.
  5. ^ Benoit-Ivan Wansi (22 December 2021). "Cameroon: Nachtigal hydroelectric dam to come on stream mid-2024". Afrik21.africa. Paris, France. Retrieved 28 December 2021.

External links edit