Busia Water Supply and Sanitation Project

Busia Water Supply and Sanitation Project (BWSSP), also Busia Water Supply and Sewerage System is a water intake, purification, distribution and waste water collection and disposal system in Busia District, Uganda.[1]

Busia Water Supply and Sanitation Project
Busia Water Supply and Sanitation Project is located in Uganda
Busia Water Supply and Sanitation Project
Location of Busia Water Supply and Sanitation Project
Map
Desalination plant
LocationMajanji, Busia District
Coordinates00°14′37″N 33°59′17″E / 0.24361°N 33.98806°E / 0.24361; 33.98806
Estimated output12,988 cubic meters (12,988,000 L) of water daily
CostUS$14.2 million
TechnologySedimentation, Chlorination
Percent of water supply100% of Busia (Uganda) Metropolitan Area & 30% of Busia District
Operation date1 July 2027 Expected

Location edit

The water treatment and waste water disposal facility is under construction in the lakeside town of Majanji, Majanji Parish, Majanji Sub-County, in Busia District, approximately 28 kilometres (17 mi), by road, south of the town of Busia, where the district headquarters are located.[2] Majanji is located approximately 187 kilometres (116 mi), by road, east of Kampala, the capital city of Uganda.[3] The geographical coordinates of the water treatment plant are: 00°14'37.0"N, 33°59'17.0"E (Latitude:0.243611; Longitude:33.988056).[4][5]

Overview edit

In the late 2020 the Government of Uganda borrowed funds from the World Bank to establish the Busia District Water Supply and Sanitation Project, in Eastern Uganda. The main objective is to improve water supply and sanitation services in the town of Busia, Uganda and to about one third of the surrounding rural district.[6]

The water intake point will be in Lake Victoria, about 300 metres (984 ft) off the coast, in the town of Majanji. The water treatment plant, capable of processing 12,988 cubic meters (12,988,000 L) of water very 24 hours will be constructed in Majanji as well. An elevated storage tank capable of storing 1,720 cubic meters (1,720,000 L) of potable water will be erected at Dabani, between Majanji and downtown Busia.[6]

The central collection point of the waste water will be established in the neighborhood called Osapir, within Busia Municipality, on land that is already owned by the town council. The waste water will first be passed through artificial wetland filters to separate the liquids from the solids. The liquids will then be directed into natural wetlands. The biosolids will be dried and either sold or donated to farmers to use as fertilizer.[5][6]

Other planned infrastructure developments include the construction of eight flushing public toilets in downtown Busia, Uganda to cut down on open defecation and reduce water borne diseases, including Cholera, typhoid and dysentery, which are now prevalent.[1][6][7]

Construction and funding edit

In April 2021, the Uganda Ministry of Water and Environment, which is the implementing agency, awarded the engineering, procurement and construction (EPC) contract to Zhonghao Overseas Construction Engineering Company. The contract price is quoted as USh50 billion (approx. US$14 million). Construction is expected to last 6 years.[8]

Other considerations edit

Part of the water extracted from Lake Victoria under this project is intended to supply irrigation water to several agro-processing businesses in Busia District.[8]

See also edit

References edit

  1. ^ a b Daily Monitor (7 August 2020). "Busia banks on Shs50b water project to end disease burden". Daily Monitor. Kampala. Retrieved 10 July 2021.
  2. ^ Google (10 July 2021). "Road Distance Between Busia, Uganda And Majanji, Uganda" (Map). Google Maps. Google. Retrieved 10 July 2021.
  3. ^ Google (10 July 2021). "Road Distance Between Kampala, Uganda And Majanji, Uganda With Interactive Map" (Map). Google Maps. Google. Retrieved 10 July 2021.
  4. ^ Google (10 July 2021). "Location of Busia Water Supply and Treatment Plant" (Map). Google Maps. Google. Retrieved 10 July 2021.
  5. ^ a b ESIA Team (April 2018). "Water Supply And Sanitation Project In Majanji, Lumino, Buhehe, Masafu, Masaba, Dabani, Buteba, Masinya, And Siduka Sub-Counties; Busia Municipality, Busia District: Environmental and Social Impact Assessment for Busia Water Supply and Sanitation Project: Updated And Final Environmental And Social Impact Report" (PDF). World Bank Group. Retrieved 10 July 2021.
  6. ^ a b c d Inès Magoum (14 August 2020). "Uganda: $13.6 million from WB for drinking water in Busia district". Afrik21.africa. Paris, France. Retrieved 10 July 2021.
  7. ^ Dennis Ayemba (5 May 2021). "Chinese company to implement Busia Water Supply and Sanitation Project in Uganda". Construction Review Online. Nairobi, Kenya. Retrieved 30 August 2021.
  8. ^ a b Inès Magoum (4 May 2021). "Uganda: China's Zhonghao wins contract for Busia water and sanitation project". Afrik21.africa. Paris, France. Retrieved 10 July 2021.

External links edit