The Bielsko-Biała Power Plant is a complex of coal-fired combined heat and power plants at Czechowice-Dziedzice near Bielsko-Biała, Poland. It has two principal flue gas stacks, 100 metres (330 ft) and 225 metres (738 ft) high, the latter of which is one of the tallest free standing structures in Poland. The complex is operated by Południowy Koncern Energetyczny, a subsidiary of the Tauron Group.

Bielsko Biala Power Plant
Map
Official nameZespół Elektrociepłowni Bielsko-Biała
CountryPoland
LocationCzechowice-Dziedzice
Coordinates49°48′43″N 19°03′07″E / 49.812°N 19.052°E / 49.812; 19.052
StatusOperational
Construction began1960
Owner(s)PKE
Thermal power station
Primary fuelCoal
Secondary fuelFuel oil
Tertiary fuelNatural gas
Cogeneration?Yes
Power generation
Units operational1 × 77 MW
1 × 55 MW
Units planned1 × 50 MW & 150 MWt
Nameplate capacity132 MW

History edit

The first plant (EC1) at Bielsko Biala was built in 1960–1973. The necessity of building this power station was caused when Bielsko and Czechowice formed a big industrial center which required more energy. The second power plant (EC2) was built in 1975–1997 to supply energy for the Fabryka Samochodów Małolitrażowych car factory and residential housing estates. In 2009, it was announced that Tauron Groupis planning to build a new generation unit with power capacity of 50 MW and thermal capacity of 150 MWt.[1]

Specifications edit

The first plant has four boilers and consists of three turbine sets. It has installed power capacity of 77 MW and installed thermal capacity of 275 MJ/s. The second plant has a heating unit with the circulating fluidized bed boiler and two heating steam-oil boilers. It has installed power capacity of 55 MW and installed thermal capacity of 172 MJ/s.

   
Czechowice-Dziedzice Plant Smaller stack, 100 meters