2024 East–West MRT line disruption

On 25 September 2024, train services on the Singapore Mass Rapid Transit (MRT) East–West line (EWL) were disrupted when an axle box of a Kawasaki C151 train dislodged, damaging the track and equipment along the stretch between the Clementi and Dover stations. This resulted in the suspension of regular services between the Boon Lay and Queenstown stations, affecting more than 2.6 million commuters.[2]

September 2024 East–West MRT line disruption
The stalled C151 train on the tracks towards Ulu Pandan Depot
Details
Date25 September 2024; 48 days ago (2024-09-25)
approximately 9.25 a.m. (SST)
LocationClementi MRT station to Ulu Pandan Depot reception track
1.6 km (0.99 mi)
Coordinates1°19′26.85″N 103°45′36.88″E / 1.3241250°N 103.7602444°E / 1.3241250; 103.7602444
CountrySingapore
LineEast-West Line
OperatorSMRT Trains Ltd (SMRT Corporation)
OwnerLand Transport Authority
Incident typeTrain car derailment, mechanical failures leading to extensive track damage[1]
CauseDislodged axle box of train
Statistics
TrainsKawasaki Heavy Industries C151
Deaths0
Injured0
Damage46 rail breaks, 3 turning point machines, power cables, third rails, and rail fasteners
Area of disruption

Described by experts as a "rare" incident,[3] the damage was reported to be extensive, and services was expected to be restored only some days after.[4][5] During restoration works by engineers from the Land Transport Authority and SMRT Corporation, shuttle train services were restored for the stretches between the Queenstown and Buona Vista stations, and between the Jurong East and Boon Lay stations. Bus bridging services were provided for the closed segment between the Buona Vista and Jurong East stations.[6]

Services resumed on 1 October. This was one of the longest train disruptions on the MRT network in Singapore's history,[7] as well as the longest since 2017.[8] Investigations into the incident are ongoing.

Incident

edit

At about 9 am local time on 25 September 2024, a faulty eastbound Kawasaki C151 train was pulled out of service at Clementi station.[9] Eyewitnesses said there was smoke emitting from the train as it arrived into Clementi station. The 850 passengers on the train disembarked and SMRT staff guided the passengers to Clementi station.[10] To return to Ulu Pandan Depot, it had to switchover at Queenstown station.[9][11] Near Dover station, a defective axle box dropped on the tracks, causing the bogie frame to be dislodged from the third car of the six car train. The bogie damaged the third rail (exposing its cables), power cables, point machines (which enabled trains to change tracks), and rail fasteners[12] as well as causing rail breaks across 2.55 km (1.58 mi)[a] of track, triggering a power trip at 9:25am, which stalled the train.[2][11][1]

This also stalled four other trains between Clementi and Buona Vista, including a train 40 metres (130 ft) near Clementi station,[2][10][14] and the affected passengers from that stalled train also disembarked and walked to Clementi station with SMRT staff guidance.[11] The train operator SMRT Trains first reported the incident at 9:52 am and suspended train services between the Queenstown and Boon Lay stations.[10][14] The Land Transport Authority (LTA) later announced at 2:45 pm that there would not be train services between Boon Lay and Queenstown for the rest of that day because of the extensive damage.[14]

Repair and mitigation works

edit
 
Police officers and other staff managing the crowd for bus bridging services at a bus stop near Buona Vista station
 
Engineers on the EWL tracks between Clementi and Ulu Pandan Depot

The disruption caused "extensive damage" to the affected track stretch. The damages include 46 rail cracks, exposure of the third rail's cables, three point machines, power cables, and rail fasteners.[15] A point machine between Jurong East and Clementi station was so badly damaged that it could not be salvaged and needed to be replaced. All of the equipment aforementioned needed replacement, with the point machines requiring realignment and careful recalibration.[12] Emergency repair works have been underway since 25 September, with over 300 engineers involved in rectification and replacement works.[5] There are also investigations currently ongoing.[3]

Free regular bus services were offered between Queenstown and Boon Lay stations, while bridging buses started running between Buona Vista and Jurong East in 9:58 am by SMRT Buses, SBS Transit, Tower Transit and Go-Ahead Singapore.[16][17] Police officers, LTA ground staff, and personnel from the bridging bus operators were deployed to manage the crowds at the affected stations.[18] Shuttle train services between Queenstown and Buona Vista stations, as well as between Jurong East and Boon Lay stations, were activated at 3:56 pm and later 4:11 pm, respectively.[2] By 26 September, the shuttle train services were running at 10-minute intervals.[16] While the authorities initially hoped to restore partial services between Jurong East and Buona Vista by 27 September, this was ruled out in favour of minimizing delays in restoring full services with the new deadline set for 30 September.[4] Transport Minister Chee Hong Tat issued an apology for the disruptions in a Facebook post.[19]

The engineers managed to move the train back to Ulu Pandan Depot by attaching a temporary axle box to the train before using a hydraulic system to move the wheel back on the rail and pulled the train back to the depot.[12] The power cables and two of the three point machines were replaced on 27 September, with repairs on the third rail expected to be completed on the same day. During maintenance, the engineers had to use mechanical jigs instead of rail vehicles due to the broken rails.[20] The next day, SMRT and LTA reported that their engineers made "significant progress" with the maintenance as well as completion of heavy rail delivery work. The track point machines and associated trackside equipment were replaced and tested, while the power rail was restored.[21] Once repairs were finished, systematic and functional tests were planned for 29 September 2024, including checks on tracks, power supply, and train signalling as well as running trains in different speeds to ensure smooth operations.[22]

In a joint statement by SMRT and LTA on 29 September, it was announced that engineers had found 12 more cracks through stress and loading tests which were previously not visible during the replacement of other damaged parts of the track. As such, the expected reopening of the segment was further delayed to 1 October after more tests were being carried out on 30 September.[23][24] On the next day, the LTA announced the restoration of the third rail and the completion of locomotive stress tests and other tests for electric meggering and track circuiting and they were still performing loaded train endurance tests.[25] They also carried out ultrasound tests on the welds of the tracks.[26]

The LTA and SMRT announced that train services would resume on 1 October, though with temporary speed restrictions on westbound tracks for safety. Train speeds would be reduced train's speed from 60 to 80 kilometres per hour (50 mph) to 40 kilometres per hour (25 mph) for safety.[26][27][28]

Impact

edit

The disruption caused significant increases in travel times, with The Straits Times reporting that a typical journey from Jurong East to Redhill took approximately 90 minutes instead of the usual 21 minutes. Queues at bus stops serving the affected stations were as long as 100 metres (330 ft).[18][8] Many commuters were also confused with the transport arrangements, such as the location of free bridging bus stops for closed stations.[18] Some voiced their frustration regarding the disruption and its spillover effects, including the longer travel time and the long walking distance between Jurong East station and its free bridging bus stop.[8][18]

It is estimated that the disruption affected more than 2.1 million commuters as of 30 September,[29][30] with 358,000 passengers on the first day, 516,000 passengers on the second day, and 500,000 passengers on the third day of the disruption. Some commuters avoided the part of MRT system from Queenstown to Jurong East due to lack of safe distancing involved in all public bus services, with some elderly struggled with route changes at all days.[21]

The incident occurred during the Primary School Leaving Examination (PSLE). In response to the disruption, the Ministry of Education (MOE) announced that students taking the PSLE on 26 September were granted the full allocated time to sit their paper as long as they turned up before the end of the exam.[31] Free taxi services were offered to ferry students to their examination venues from affected stations,[32][33] though according to The Straits Times, the taxis were not used by the students.[34] According to MOE, five students were late to the English and foundation English examination (four of which were N-level candidates and one was a PSLE candidate)[35] on 26 September due to the disruption, of which one student took the examination in another examination centre. All of them were given the full duration of the paper.[31] Additionally, according to the Singapore Examinations and Assessment Board (SEAB), no candidates were affected by the disruption for the Mathematics exam on 27 September.[35]

Response

edit

It is the second longest MRT disruption in Singapore's history, as well as the longest one since 2017.[8] The incident has been described by experts as "rare", with Dubai Road and Transport Authority's chief specialist of rail operations Jumadi Husani stating that "Under normal circumstances, the axle box, bogie... and train wheels do not come off from the train", adding that if it does, it was "mainly due to improper installation of parts after maintenance or testing activities or if defective components... are not replaced". Similarly, electrical engineer Teo Chok Kok said "it's very rare for [axle boxes] to drop... it's a very rare case".[3]

Aftermath

edit

Investigation

edit

On 2 October, the LTA established an Expert Advisory Panel (EAP) to investigate the cause of the incident.[36] Malcolm Dobell, who was the former Head of Train Systems for London Underground, has been appointed as the EAP Chairman. He would also be assisted by five other local and overseas experts. The investigation would involve finding the root cause of the axle box failure and the fault detection and incident handling procedures. The investigation would be held over a few months with the findings released to the public.[37] In addition, the LTA and representatives from public bus operators met on 2 October to discuss their management of the bridging bus services during the breakdown to examine improvements needed for such incident management plans.[17] On 1 November, SMRT announced the establishment of a tripartite workgroup – comprising representatives from LTA, SMRT and the National Transport Workers’ Union (NTWU) – that would oversee the reliability and safety of the rail network.[38][39]

Parliament

edit

A total of thirty one Parliamentary Questions have been filed against Minister of Transport Chee Hong Tat,[40] with nineteen questions answered on 14 October.[41][42]

Notes and references

edit

Notes

edit
  1. ^ initially reported as 1.6 km (0.99 mi)[13]

References

edit
  1. ^ a b Ang, Hwee Min (26 September 2024). "Faulty train caused 'extensive damage' to track between Clementi and Dover, leading to power trip and disruption". CNA. Retrieved 27 September 2024.
  2. ^ a b c d Loi, Esther (15 October 2024). "East-West Line disruption: Parliament hears timeline of events". The Straits Times. Retrieved 16 October 2024.
  3. ^ a b c Ong, Justin Guang-Xi; Ang, Hwee Min; Mohan, Matthew (27 September 2024). "Incident that caused MRT service disruption was a rare case, say experts". CNA. Retrieved 27 September 2024.
  4. ^ a b Cheng, Kenneth (26 September 2024). "Train disruption on EWL to last several more days; SMRT aims to restore services on Sept 30". The Straits Times. Archived from the original on 27 September 2024. Retrieved 27 September 2024.
  5. ^ a b Ng, Hong Siang (27 September 2024). "More than 300 engineers, technicians working to repair 'extensive' damage on East-West Line, says Chee Hong Tat". CNA. Archived from the original on 27 September 2024. Retrieved 27 September 2024.
  6. ^ "Joint News Release by the Land Transport Authority (LTA) & SMRT". LTA. 26 September 2024. Archived from the original on 26 September 2024. Retrieved 27 September 2024.
  7. ^ Iau, Jean (26 September 2024). "Singapore's MRT train disruption to continue over weekend". South China Morning Post. Archived from the original on 26 September 2024. Retrieved 27 September 2024.
  8. ^ a b c d Lim, Vanessa; Ganesan, Natasha (26 September 2024). "Commuters cope with rain, longer journeys on day 2 of East-West Line MRT disruption". CNA. Archived from the original on 27 September 2024. Retrieved 27 September 2024.
  9. ^ a b "East-West Line MRT disruption: How a faulty train left a trail of destruction". The Straits Times. Archived from the original on 28 September 2024. Retrieved 27 September 2024.
  10. ^ a b c "Frustration and confusion as MRT services halted between Boon Lay and Queenstown stations for hours". CNA. 25 September 2024. Retrieved 27 September 2024.
  11. ^ a b c "Parliamentary Ministerial Statement by Minister for Transport Mr Chee Hong Tat". Ministry of Transport. 15 October 2024. Retrieved 2 November 2024.
  12. ^ a b c Chelvan, Vanessa Paige (26 September 2024). "Defective train left cracked rail, damaged power cables in its wake on EWL stretch". The Straits Times. Archived from the original on 26 September 2024. Retrieved 27 September 2024.
  13. ^ Teo, Brian; Chua, Charlene; Tan, Charlotte; Loi, Esther; Lee, Hannah Summer; Lee, Jiaying; Lee, Pei Jie; Pereira, Nikita; Lim, Yao Hui; Teoh, Shannon; GV, Xaoquín (27 September 2024). "East-West Line MRT disruption: How a faulty train left a trail of destruction". Straits Times (Interactive graphic). Archived from the original on 27 September 2024. Retrieved 28 September 2024.
  14. ^ a b c Lee, Chong Ming (26 September 2024). "East-West Line disruption: A timeline of what happened". CNA. Retrieved 27 September 2024.
  15. ^ "East-West Line disruption: No train services from Jurong East to Buona Vista on Sep 30, new cracks found along tracks". CNA. Archived from the original on 29 September 2024. Retrieved 29 September 2024.
  16. ^ a b Koh, Sarah (26 September 2024). "Free bus services, shuttle trains: Alternative travel options amid MRT disruption on EWL". The Straits Times. ISSN 0585-3923. Archived from the original on 27 September 2024. Retrieved 27 September 2024.
  17. ^ a b Chelvan, Vanessa Paige (3 October 2024). "LTA, bus operators to review management of free bus services during EWL disruption". The Straits Times. ISSN 0585-3923. Retrieved 3 October 2024.
  18. ^ a b c d Mujibah, Fatimah; Chelvan, Vanessa Paige; Khan, Fatmah (26 September 2024). "Longer travel time, snaking bus queues: EWL passengers cope with 2nd day of train disruption". The Straits Times. Retrieved 27 September 2024.
  19. ^ Aravindan, Aradhana; Sofia, Nurin (26 September 2024). "Singapore Minister Apologizes for Rare Lengthy Train Disruption". Bloomberg. Archived from the original on 26 September 2024. Retrieved 29 September 2024.
  20. ^ Chelvan, Vanessa Paige (27 September 2024). "Major EWL train disruption: Power rail to be fixed by Sept 27 as repairs continue along affected stretch". The Straits Times. Retrieved 27 September 2024.
  21. ^ a b Choi, Esther (28 September 2024). "Significant progress made in repair of damaged MRT rail tracks: LTA". The Straits Times. Archived from the original on 28 September 2024. Retrieved 28 September 2024.
  22. ^ "MRT disruption: Restoration of power rails 'fully completed', safety tests set for Sunday". CNA. 28 September 2024. Archived from the original on 29 September 2024. Retrieved 29 September 2024.
  23. ^ "East-West Line disruption: No train services from Jurong East to Buona Vista on Sep 30, new cracks found along tracks". CNA. Archived from the original on 29 September 2024. Retrieved 29 September 2024.
  24. ^ Sun, David (29 September 2024). "Train service between Jurong East, Buona Vista won't resume on Sept 30, expected to restart on Oct 1". The Straits Times. Retrieved 29 September 2024.
  25. ^ "East-West Line disruption: Affected rail segments replaced, train endurance test ongoing". CNA. 30 September 2024. Retrieved 30 September 2024.
  26. ^ a b Loi, Esther (30 September 2024). "East-West Line MRT services to fully resume on Oct 1; westbound trains will run at slower speeds". The Straits Times. Retrieved 30 September 2024.
  27. ^ Loi, Esther; Khan, Fatmah (1 October 2024). "East-West Line MRT services back to normal after 6-day disruption". The Straits Times. Retrieved 1 October 2024.
  28. ^ Ang, Hwee Min (1 October 2024). "East-West Line MRT services fully resume after six-day disruption". CNA. Retrieved 1 October 2024.
  29. ^ Iau, Jean (30 September 2024). "A look at Singapore's MRT disruption and other train delays in Asia". South China Morning Post. Retrieved 30 September 2024.
  30. ^ "MRT disruptions: Full train services on East-West Line to resume on Oct 1 , Singapore News". AsiaOne. 30 September 2024. Retrieved 30 September 2024.
  31. ^ a b Fatimah, Mujibah (27 September 2024). "5 pupils late for PSLE paper due to EWL train disruption, given full duration of exam". The Straits Times. Archived from the original on 27 September 2024. Retrieved 27 September 2024.
  32. ^ Lim, Kewei (26 September 2024). "Train disruptions: Taxis offering free rides to PSLE students near Jurong East MRT station". AsiaOne. Retrieved 27 September 2024.
  33. ^ Salim, Shazalina (26 September 2024). "Free cab rides for PSLE pupils affected by train disruptions". The New Paper. Archived from the original on 27 September 2024. Retrieved 28 September 2024.
  34. ^ Ang, Shermaine; Khan, Fatmah. "Commuters rethink weekend plans due to EWL train disruption". The Straits Times. Archived from the original on 28 September 2024. Retrieved 29 September 2024.
  35. ^ a b Mujibah, Fatimah (30 September 2024). "5 late for PSLE, N-Level papers on Sept 30 due to East-West Line train disruption". The Straits Times. Retrieved 30 September 2024.
  36. ^ "East-West Line disruption: Investigations underway, LTA to appoint expert advisory panel to review findings". CNA. 2 October 2024. Retrieved 2 October 2024.
  37. ^ "LTA to Conduct Thorough Investigations Into the Root Cause of the Disruption of Services on East-West Line". LTA. 2 October 2024. Retrieved 2 October 2024.
  38. ^ Ng, Hong Siang (1 November 2024). "SMRT establishes tripartite workgroup to review rail reliability, safety". CNA. Retrieved 2 November 2024.
  39. ^ Yufeng, Kok (1 November 2024). "Disruption-hit rail operator SMRT forms group to look into reliability, safety issues". The Straits Times. Retrieved 2 November 2024.
  40. ^ "Parliamentary Ministerial Statement by Minister for Transport, Mr Chee Hong Tat".
  41. ^ "Fourteenth Parliament of Singapore (Second Session) Order Paper. Monday, 14 October 2024" (PDF). Parliament of Singapore. Retrieved 12 October 2024.
  42. ^ Yow, Daphne (11 October 2024). "Parliament to discuss East-West Line disruption, school bullying and Dyson layoffs". CNA. Retrieved 12 October 2024.
edit