Trianel Windpark Borkum

Trianel Windpark Borkum (formerly Borkum West II) is an offshore wind farm near Borkum. Its first phase of 40 turbines rated at a total capacity of 200 MW is operational, with a planned, additional 200 MW in a second phase.[4][unreliable source?] The project was approved for construction in 2008[5] and will cost over €1 billion to construct once fully operational (€900m for phase I alone). Originally known as Borkum West II the name was changed to Trianel Windpark Borkum in early 2013.

Borkum West II
Map
CountryGermany
Location45 km North of Borkum island
Coordinates54°02′30″N 6°28′00″E / 54.0417°N 6.4667°E / 54.0417; 6.4667
StatusOperational
Construction beganSeptember 2011
Commission dateJuly 2015 (2015-July)[1]
Construction costEUR900m (Phase 1) ? (Phase 2)
Owner(s)Trianel + 33 municipal utilities
Operator(s)Trianel
Wind farm
Typeoffshore
Max. water depth33 m
Distance from shore45 km (65.6 km for center)
Rotor diameter116 m
Power generation
Units operational40 x 5 MW
Make and modelAreva Wind M5000-116[2]
Units planned32 x 6.34 MW[3]
Nameplate capacity200 MW
External links
Websitewww.trianel-borkum.de/en/start.html
Map
Wind farm layout
Borkum West II's location in the wind farms of the German Bight

Phase 1 of the installation was completed in the 4th quarter of 2014 and consist of 40 Areva M5000-116 turbines (5 MW turbines) on Tripod foundations.[2] It was connected to the grid in August 2015.[6] In the six months before March 2016 the wind farm produced 452.33 GWh,[7] i.e. a capacity factor of 51.6%.

In September 2016 Senvion was awarded a conditional contract for the second phase, for 32 upgraded 6.2M152 turbines rated at a total capacity of 203 MW. A final investment decision was expected in the first half of 2017 after which construction could start in early 2018 for a planned completion in the fall of 2019.[3] Cost is €184/MWh.[8]

References edit

  1. ^ "Borkum West II Commissioned". Enerdata. 20 July 2015. Retrieved 20 July 2015.
  2. ^ a b "Facts and figures". trianel-borkum.de. Retrieved 17 August 2013.
  3. ^ a b "Trianel Windpark Borkum II counts on Senvion offshore turbines". trianel.com. 2016-09-28. Retrieved 2017-03-05.
  4. ^ "Borkum West II Offshore Wind Farm, Germany". power-technology.com. Retrieved 24 January 2013.
  5. ^ Berkenhagen, J. R.; Döring, R.; Fock, H. O.; Kloppmann, M. H. F.; Pedersen, S. R. A.; Schulze, T. (2010). "Decision bias in marine spatial planning of offshore wind farms: Problems of singular versus cumulative assessments of economic impacts on fisheries". Marine Policy. 34 (3): 733. doi:10.1016/j.marpol.2009.12.004.
  6. ^ "Germany adds lots of offshore wind".
  7. ^ "Trianel Windpark Borkum halbes Jahr in Betrieb Erster rein kommunaler Offshore-Windpark erfüllt positive Erwartungen" [Trianel Windpark Borkum half year in operation First purely municipal offshore wind farm fulfills positive expectations]. presseportal.de (in German). 2016-03-18. Retrieved 2017-03-05.
  8. ^ "Trianel Windpark Borkum II Offshore Wind Farm - Fully Commissioned - Germany | 4C Offshore". www.4coffshore.com. Archived from the original on 9 January 2022.