Gemasolar Thermosolar Plant

Gemasolar is a concentrated solar power plant with a molten salt heat storage system. It is located within the city limits of Fuentes de Andalucía in the province of Seville, Spain.[2]

Gemasolar
The Gemasolar power plant in 2021
Map
CountrySpain
LocationFuentes de Andalucía, Sevilla
Coordinates37°33′29″N 5°19′45″W / 37.558086°N 5.329056°W / 37.558086; -5.329056
StatusOperational
Construction beganMarch 2009
Commission dateMay 2011
OwnerTorresol Energy
Solar farm
TypeCSP
CSP technologySolar power tower
Collectors2,650
Site resource2,172 kWh/m2/yr
Site area520 acres (210 ha)
Power generation
Units operational1
Nameplate capacity19.9 MW
Capacity factor45.9%
Annual net output80 GW·h
Storage capacity299 :) MW·he (670 MW·ht)[1]
External links
CommonsRelated media on Commons

Design and specifications

edit

The plant is of the solar power tower type CSP and uses concepts pioneered in the Solar One and Solar Two demonstration projects, using molten salt as its heat transfer fluid and energy storage medium. Originally called Solar Tres, it was renamed Gemasolar.[3]

The project, which has received a subsidy of five million euros from the European Commission and a loan of 80 million euros from the European Investment Bank, makes use of the Solar Two technology tested in Barstow, California, but is approximately three times the size. It makes use of several advances in technology after Solar Two was designed and built.

Gemasolar is the first commercial solar plant with central tower receiver and molten salt heat storage technology. It consists of a 30.5-hectare (75-acre) solar heliostat aperture area with a power island and 2,650 heliostats, each with a 120-square-metre (1,300 sq ft) aperture area and distributed in concentric rings around the 140-metre-high (460 ft) tower receiver. The total land use of the Heliostats is 195 hectares (480 acres).[4]

The most innovative aspects of the plant, which belongs to the company Torresol Energy, are its molten salt receiver, its heliostats aiming system and its control system. In addition, its storage system allows it to produce electricity for 15 hours without sunlight (at night or on cloudy days). This storage capacity makes its solar power manageable so that it can be supplied based on demand. The plant has already been able to supply a full day[5] of uninterrupted power supply to the grid, using thermal transfer technology developed by SENER.

Gemasolar, with its 19.9 MW of power, can supply 80 GWh per year — enough to supply power to 27,500 homes.[1] The plant has been operational since May 2011. Its official launch was held in October 2011.[6]

Performance

edit
 
Gemasolar in 2012

After the second year of operation the plant has exceeded projected expectations. In 2013, the plant achieved continuous production, operating 24 hours per day for 36 consecutive days, a result which no other solar plant has attained so far. Total operation is 6,450 hours at full capacity per year, preventing about 30,000 tons of CO2 emissions per year.[7]

See also

edit

References

edit
  1. ^ a b "Gemasolar solar thermal power plant". Archived from the original on 2020-02-07. Retrieved 2019-12-10.
  2. ^ NREL CSP Technology Workshop: Solar Tres Archived 2007-09-30 at the Wayback Machine, SENER Ingeniería y Sistemas, S.A., 2007-03-07, accessed 2007-05-31
  3. ^ "CSP: Concentrated Solar Power" (PDF). Archived from the original (PDF) on 2022-01-20. Retrieved 2019-12-10.
  4. ^ "Gemasolar Thermosolar Plant". Concentrating Solar Power Projects. National Renewable Energy Laboratory (NREL), U.S. Dept. of Energy (DOE). 20 March 2017. Archived from the original on 16 May 2021. Retrieved 10 December 2019.
  5. ^ Gemasolar, energía non stop Archived 2021-10-17 at the Wayback Machine Spanish 26 October 2011
  6. ^ "Gemasolar: how it works" (PDF). Archived from the original (PDF) on 2017-06-15. Retrieved 2012-03-19.
  7. ^ "Gemasolare celebrates its second anniversary with an excellent operational record" (PDF). Torresol Energy. 3 October 2013. Archived from the original (PDF) on 14 July 2014. Retrieved 13 July 2014.
edit