Berlin–Dresden railway
Overview
Line number
  • 6135 (Bln. Südkreuz–Elsterwerda)
  • 6248 (Elsterwerda–Dr.-Friedrichst.)
LocaleBerlin, Brandenburg and Saxony
Termini
Service
Route number
  • 200.2 (Yorckstraße–Blankenfelde)
  • 203 0 (Glasower Damm–Elsterwerda)
  • 225 0 (Elsterwerda–Dresden Hbf)
  • 240 0 (all traffic)
Technical
Line length174.2 km (108.2 mi)
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification15 kV/16.7 Hz AC overhead catenary
Operating speed160 km/h (99.4 mph) (maximum)
Route map

Berlin Dresdner Bahnhof
1.600
Yorckstraße
3.500
Berlin Südkreuz (Papestraße until 2006)
RingbahnS41S42S46S47
Berlin-Tempelhof freight yard
5.100
Berlin Priesterweg
6.700
Attilastraße
(formerly Mariendorf)
6.800
Berlin-Mariendorf junction
freight line from Ring line
Kamenzer Damm
(planned)
9.400
Berlin-Marienfelde
11.000
Buckower Chaussee
to GAR
from GAR
12.300
Schichauweg
13.800
Lichtenrade
BerlinBrandenburg state border
16.800
Mahlow
19.100
Glasower Damm Süd junction
from BAR
19.400
Blankenfelde (Teltow-Fläming district),
terminus of S2
20.800
Dahlewitz
24.300
Rangsdorf
30.700
Dabendorf
31.200
Zossen Zoa junction
32.700
Zossen
37 m
Notte Canal
36.000
Zossen Lager
39.100
Wünsdorf-Waldstadt
50 m
42.100
Neuhof (b Zossen)
51.500
Baruth/Mark
55 m
56.100
Klasdorf
61.800
Golßen (Niederl)
62 m
68.600
Drahnsdorf
65 m
76.000
Luckau-Uckro
84 m
81.100
Gehren (Kr Luckau)
85.500
Walddrehna
115 m
93.700
Brenitz-Sonnewalde
99 m
100.000
Doberlug-Kirchhain Nord junction
to Cottbus
102.900
Doberlug-Kirchhain
Halle–Cottbus line
108.900
Rückersdorf (Niederl)
116.500
Hohenleipisch
121.700
Biehla
122.800
Elsterwerda
93 m
124.600
50.400
Route no. change 6135 / 6248
48.120
Prösen Ost
93 m
BrandenburgSaxony state border
43.450
Frauenhain
110 m
39.530
Zabeltitz
113 m
33.520
Großenhain Berlin station
(passenger station to 2002) 118 m
27.900
Röder new cut
0
Kottewitz junction
Böhla
(passenger station until 2002)
144 m
17.480
Weinböhla
(passenger station until 2002)
143 m
13.310
Neucoswig
(until 2002)
123 m
11.800
Az junction (Bk)
11.946
10.950
Radebeul-Naundorf junction (Bk)
10.800
Radebeul-Naundorf
111 m
Elbe bridge, Niederwartha (354 m)
8.970
Niederwartha
112 m
Niederwartha pumped-storage plant siding
6.784
Cossebaude
110 m
5.350
Dresden-Stetzsch
110 m
3.890
Dresden-Kemnitz
108 m
2.220
Dresden-Cotta
116 m
from Dresden port (freight line)
0.230
Dresden-Friedrichstadt
marshalling yard
114 m
0.000
(start of line)
Source: German railway atlas[1]

The Berlin–Dresden railway is a double track, electrified main line railway in the German states of Berlin, Brandenburg and Saxony, which was originally built and operated by the Berlin-Dresden Railway Company (Berlin-Dresdener Eisenbahn-Gesellschaft). It runs from Berlin through the southern Teltow countryside and then between Lower Lusatia and Fläming Heath through Elsterwerda and the Großenhainer Pflege countryside to Dresden.

Upgrades completed in December 2017 enabled maximum speeds of 160 km/h (99 mph). By 2020 new signalling should allow speeds of 200 km/h (120 mph).

History edit

Up to 1945 edit

In 1848 the Berlin-Anhalt Railway Company opened the Jüterbog–Röderau line, connecting with the Leipzig–Dresden line and creating the first direct rail link between Berlin and Dresden. In 1872 the Berlin-Dresden Railway Company was founded to build a competing a line via Elsterwerda that was 12 km (7.5 mi) shorter. This route was opened on 17 June 1875. Long-distance traffic between Berlin and Dresden was divided between the two routes until the end of World War II.

1 October 1877 management of the line was taken over by Prussian state railways. On 24 January 1887 Saxony and Prussia contracted a treaty, under which ownership of the company passed to Prussia from 1 April 1887. This treaty also provided that the Elsterwerda–Dresden section was resold to the Saxon government on 1 April 1888, when it became part of the Royal Saxon State Railways.

 
Original Berlin station in Dresden
 
Former Berlin station in Dresden, now part of a goods yard
 
Elsterwerda station
 
Elbe bridge in Niederwartha

At both ends of the line new stations were built, the Dresdner Bahnhof (Dresden station) in Berlin and Berliner Bahnhof (Berlin station) in Dresden. Both stations were used only briefly. In 1882 the Dresden station in Berlin (located on the site of the present-day Gleisdreieck U-Bahn station and the former postal station in Luckenwalder Strasse) was closed for passenger traffic. The line’s Berlin terminus was moved a little further north to the Anhalter Bahnhof (Anhalt station). A little later, the Berlin station in Dresden was abandoned as part of the redevelopment of the Dresden railway node. In its place the Dresden-Friedrichstadt station was built, which has been used since 1894 for freight and regional services. Since that time, long distance services have turned off towards Radebeul-Zitzschewig on the Leipzig–Dresden line and Dresden-Neustadt to Dresden Hauptbahnhof. In contrast, freight trains to and from Leipzig use the Berlin–Dresden railway from Radebeul-Naundorf station to Friedrichstadt.

The Prussian and Saxon railway administrations initially did not cooperate with the use of locomotives. Although carriages were hauled between Berlin and Dresden early on, the locomotives were changed in Elsterwerda. This caused financial losses and prevented a reduction in travel time. It was not until 1 May 1905 that the railway administration introduced locomotive operations with both Prussian and Saxon locomotives.[2]

From 1875 until World War I the Prussian military railway ran parallel with the line from Berlin to Zossen. Between 1901 and 1903, the line between Marienfelde and Zossen was reinforced so that the Studiengesellschaft für Elektrische Schnellbahnen (Study Society for Electric Rapid Railways) could carry out tests with three-phase rapid transit sets and locomotives. On 28 October 1903, the record speed of 210.8 km/h (131.0 mph) was achieved on this line. In 1904, high-speed tests with steam locomotives followed on the upgraded military railway line. After the First World War, the military railway was disbanded as a military unit and operations on the military railway track between Berlin and Zossen were stopped. In the 1920s, the track in this section was dismantled and the military railway station facilities continued to be used by the Reichsbahn.

With the construction of the Teltow Canal, which opened in 1906, three new bridges for the Dresden Railway and the Military Railway became necessary south of the Mariendorf S-Bahn station (now Attilastraße).

At the southern end of the Tempelhof marshalling yard (near Priesterweg S-Bahn station, the long-distance tracks and the suburban tracks of the Dresden Railway were separated from the tracks of the Berlin–Halle railway. There was a separate pair of tracks for suburban traffic as far as Mariendorf station (later called Attilastraße). South of this station, long-distance traffic and suburban traffic shared a two-track line.

In 1936 a high-speed express service commenced between Berlin and Dresden using the Henschel-Wegmann Train, taking 100 minutes. The Berlin suburb train operations were electrified in 1939 and 1940. Berlin S-Bahn services commenced on 15 May 1939 between Priesterweg and Mahlow and on 6 October 1940 the S-Bahn was extended to Rangsdorf. The S-Bahn shared tracks in southern Berlin with long-distance passenger and freight trains. At the end of the 1930s work began on the new track to separate the S-Bahn and long-distance tracks, but by the beginning of the Second World War this work was not completed.

In April 1945, S-Bahn services ceased as a result of the war.[3]

Reopening in 1945 edit

After the end of the war in 1945 the railway line was seriously damaged by the allies. In addition the bridges over the Teltow Canal in Berlin were blown up in the last days of the war by the German army. Later the line’s second track was dismantled to provide reparations to the Soviet Union. Only two tracks have been restored on these bridges. Services resumed between August and October 1945. Between Mariendorf and Marienfelde stations S-Bahn services and the remaining passenger and freight services ran on a common two-track section. Between Rangsdorf and Wünsdorf steam suburban trains operated to connect with the S-Bahn.

The division of Germany and Berlin also affected the traffic on the Berlin-Dresden line. In 1951, a connecting curve was built in an easterly direction from the line linking with the newly established Berlin outer ring. Long-distance trains from Dresden used it to avoid West Berlin. The terminal stations on West Berlin territory were closed, including the Anhalt station on 18 May 1952. Afterwards regional services used the outer ring to reach the East Berlin stations of Schöneweide, Lichtenberg or Ostbahnhof. Only the S-Bahn service from Rangsdorf ran over the border into West Berlin. Freight services continued to operate in West Berlin from the north to Marienfelde station (including to the gas works at Mariendorf and the Daimler factory at Marienfelde). The remaining long-distance tracks south of Marienfelde station was partially dismantled or became overgrown in the following decades.

After the building of the Berlin Wall on 13 August 1961, S-Bahn-operations between Lichtenrade and Mahlow were abandoned. S-Bahn services initially operated a shuttle service between Mahlow and Rangsdorf, but this was discontinued on 9 October 1961 due to the lack of repair and storage facilities. Commuter trains from Wünsdorf ran to Schönefeld Airport station. From 1962 there was an S-Bahn service to Berlin. As of 26 May 1963 a shuttle train consisting of a class VT 2.09 railbus (known as the "piglet taxi") ran between Mahlow and Blankenfelde, connecting to services on the outer ring.[4]

Upgrading of the line since the 1960s edit

The low capacity of the single-track line and the poor condition of the track had long caused operational problems. The high density of freight on the line left only a small number of paths for fast passenger trains. An improvement occurred in 1972, after the second track was fully restored.[5] In the 1960s, work began on the raising of maximum speeds on the line to 160 km/h (99 mph). The stations from Baruth/Mark to Brenitz-Sonnewalde were converted for high speed with the relocation of platforms onto sidings. For various reasons, trains could still only operate at 120 km/h (75 mph).

The section from Dresden-Friedrichstadt to Radebeul-Naundorf was electrified on 28 September 1969. The adjoining section to the Berlin outer ring, including the two connections to the ring, followed in several sections from 1979 to 1983. A few years after the West Berlin S-Bahn network was taken over by the Berliner Verkehrsbetriebe, the reconstruction began on the missing second track between Marienfelde and Lichtenrade in 1988.

The route had heavy express train traffic towards Czechoslovakia, Hungary, Romania, Bulgaria and Austria as well as inland traffic in the GDR. The notable trains included the Vindobona Express from Berlin to Vienna from 1957 and the Hungaria Express between Berlin and Budapest since 1960. Other important long-distance trains were the Balt-Orient Express to Bucharest, the Pannonia Express to Sofia and the Meridian to Belgrade, which at times ran as far as Bar on the Adriatic. From 1976 onwards, the Städteexpress ("city express") Elbflorenz connected Berlin with Dresden and "Fichtelberg" connected Berlin with Karl-Marx-Stadt (now Chemnitz) on this line. They ran to Berlin in the morning and in the opposite direction in the afternoon. Later, the Berlin Express train pair was added, which ran to Dresden in the morning and to Berlin in the afternoon.

In local transport, trains ran approximately every hour between Schönefeld (bei Berlin) station and Wünsdorf, and some continued to Baruth. On the other sections, the importance of local transport was low. For many years only four passenger trains a day ran between Baruth and Elsterwerda. South of Elsterwerda in the Dresden catchment area, there were somewhat more services.

 
Train route sign: Pannonia-Express Budapest – Bad Schandau – Berlin-Lichtenberg

The route was also heavily used for freight transport. The Dresden-Friedrichstadt marshalling yard was an important hub for north-south traffic. There was extensive traffic between Scandinavia as well as the Baltic Sea ports and the inland countries towards southern Europe. In addition, heavy block trains carrying raw lignite and in double traction were transported between Elsterwerda and Dresden. In the 1980s, up to 140 train journeys were made in the Weinböhla area each day.

Development in the 1990s edit

After the fall of the Wall, the gap between Lichtenrade and Mahlow was closed for the S-Bahn and traffic to Blankenfelde was resumed on a single track on 31 August 1992.[6] Occasionally, freight trains with compacted waste containers even ran on the S-Bahn track from the Gradestrasse transfer station to landfills south of Berlin.

On 17 May 1991, Deutsche Reichsbahn commissioned the Berlin and Dresden Reichsbahn rail divisions to quickly upgrade the line for a maximum speed of 160 km/h (99 mph). On 15 July 1991, the board of the Deutsche Reichsbahn adopted appropriate measures. Less than a year was available for implementation. The planned costs were DM 145 million. In some cases, preparations should also be made for a top speed of 200 km/h.[7] In November 1991, WSSB Verkehrstechnik GmbH, which belongs to Siemens, was awarded the contract to retrofit the control and safety technology. From January to May 1992, extensive retrofitting and renewal work was carried out on the line. The PZB train protection system was also installed, electrical supply lines were changed and the overhead line system was slightly adjusted. The rail track was not changed. When the timetable changed in May 1992, the maximum speed was increased in sections to 160 km/h.[8] At the same time, switches with larger radii were installed, signal distances were increased and 100 new switch drives were installed. The signalling block system was automated throughout. This reduced travel times on long-distance transport by 35 minutes to under two hours.[8] For the first time in several decades, speeds of more than 120 km/h (75 mph) were operated on the line. The scheduled travel time for long-distance traffic between Berlin Ostbahnhof and Dresden Hauptbahnhof was one hour and 59 minutes.[7] Like the historic Henschel-Wegmann Train, it ran via Radebeul and Dresden-Neustadt on the Leipzig–Dresden railway to Dresden Hauptbahnhof. Deutsche Reichsbahn had purchased class 112 locomotives for express traffic.

In 1992, IC line 7 (Dresden–Prague) was introduced with a service at two-hour intervals with a connection to Hamburg.[9] From 25 September 1994, a pair of ICE trains ran along the line every day. The ICE ran from Berlin Zoologischer Garten station to Dresden Hauptbahnhof in the evening and in the opposite direction in the morning.[10] From 1998, the ICE ran via Berlin Ostbahnhof before the ICE connection was discontinued on 27 May 2000.

The D-Zugs running on the line were converted in 1992 by Deutsche Reichsbahn into Interregios from Rostock to Chemnitz on the Berlin to Elsterwerda section. All through rail services with stops along the way to Dresden were discontinued and replaced by regional trains with the opportunity of changing in Elsterwerda. The connections without intermediate stops on the route, for instance those of the Vindobona, were reclassified as InterCity services from Hamburg to Dresden and EuroCity services from Hamburg, Berlin to Budapest, Prague, Vienna and used with carriages from ČD, DB, MÁV and ÖBB.

The Elsterwerda train disaster occurred on 20 November 1997 at Elsterwerda station. A brake failure caused a tank car block train loaded with petrol to derail due to excessive speed. Two wagons exploded and 15 others burned out.

Situation from 2000 to 2020 edit

At the beginning of the new millennium, the condition of the route had noticeably deteriorated due to inadequate maintenance in the 1990s. Since 2002, regional traffic has been relocated between Großenhain and Radebeul-Naundorf to the Großenhain–Priestewitz and Leipzig–Dresden lines. From Coswig, regional traffic was relocated from the Leipzig line via Dresden-Neustadt to the longer, original Berlin line via Cossebaude. This was part of the segregation of traffic so that on the Großenhain–Dresden and Medessen–Dresden section, regional trains would operate on the Großenhain–Priestewitz and Leipzig–Dresden lines (western route) and express trains would operate on the Medessen–Böhla and Berlin–Dresden lines (eastern route).

On 28 May 2006, with the last Interregio in Germany from Berlin via Elsterwerda and Riesa to Chemnitz (IR line 34), this type of train was abolished and replaced by Regional Express and Regionalbahn, e.g. RE 5, RE 3 from 2006, now RE 8 (StralsundElsterwerda) and by the RB 45 (Elsterwerda – Riesa – Chemnitz). At that time, three pairs of trains had recently run from Berlin to Chemnitz every day.[11]

In 2007, the line had a capacity of 144 trains per day per direction.[12] From 2006 to the end of 2010, all long-distance trains ran from Berlin to Dresden without stopping. From 2010 onwards, some Eurocity (EC) stops were introduced again in Elsterwerda, but these were not worth the time due to poor connection times for travellers to intermediate stations.

In 2012, the Regionalbahn service from Elsterwerda to Dresden Hbf took 61 minutes, no Regional Express ran and the Eurocity took 37 minutes. Towards the north, the RE from Elsterwerda to Berlin Hbf took 127 minutes and the Eurocity took 89 minutes. In 2012, there were political demands that, in addition to stopping some ECs in Elsterwerda, a few trains should also stop in Doberlug-Kirchhain, especially because of the slow development of the line. Some REs could have run via the Doberlug-Kirchhain Nord connecting curve to Finsterwalde instead of via Elsterwerda.[13]

In 2013, according to Deutsche Bahn, a market volume of around 6,700 trips per day was estimated across all modes of transport between the metropolitan areas of Dresden and Berlin.[14]

In August 2016, the line between Wünsdorf-Waldstadt and Elsterwerda was completely closed in order to upgrade the line to a speed of 200 km/h by removing level crossings and building new tracks.

Since 2019, in addition to the Czech Railways' Eurocitys, an Intercity service has been running every two hours from Rostock via Berlin to Dresden. With scheduled stops in Doberlug-Kirchhain and Elsterwerda, this connects the Elbe-Elster-Land and parts of Lower Lusatia to the two major cities with short travel times. The double-decker multiple unit used for this runs at 160 km/h and also stops at Berlin Brandenburg Airport. In the future, it is planned to accelerate this connection to 200 km/h using new safety technology.

Development of travel time edit

 
A Stralsund–Elsterwerda RE service in Doberlug-Kirchhain station

The travel time of the Henschel-Wegmann train from 1936 to 1939 (100 minutes in the shortest case) has not yet been reached again, but the Anhalter Bahnhof in Berlin was around 2 km south of today's Hauptbahnhof and therefore a little closer to Dresden. Until 2019, there were scheduled travel times of just under 100 minutes for the section from Berlin-Südkreuz to Dresden-Neustadt.[15]

While the condition of the line enabled travel times of under two hours from 1992 onwards, a journey from Dresden to Berlin took longer until the mid-2010s. There were numerous slow speed zones. In May 2008, only around 45 percent of the Blankenfelde–Neucoswig section used by long-distance traffic was still passable at 160 km/h.[16] At the end of 2011, around a quarter of the Brandenburg section, between Blankenfelde and Elsterwerda, could not even be operated at the speed of 120 km/h intended for regional traffic.[17]

The following table provides an overview of the development of the scheduled travel time in long-distance transport (fastest connection in each case):[18][16][19][20]

Year Berlin–Dresden Hbf
(in min)
Dresden Hbf–Berlin
(in min)
Berlin
statiom
1905 170 165 Anhalter Bahnhof
1937/1938 101 100 Anhalter Bahnhof
1939 116 109 Anhalter Bahnhof
1960 152 168 Ostbahnhof
1976 114 115 Ostbahnhof
1988 161 145 Lichtenberg
1994 108 110 Ostbahnhof
2005 131 135 Ostbahnhof
2009 138 136 Hauptbahnhof
2011 118 130 Hauptbahnhof
2012 127 129 Hauptbahnhof
2013 126 130 Hauptbahnhof
2014 124 131 Hauptbahnhof
2015 123 128 Hauptbahnhof
2016 118 124 Hauptbahnhof
2017 112 122 Hauptbahnhof
2018 108 106 Hauptbahnhof
2019 128 115 Hauptbahnhof
2020 110 107 Hauptbahnhof
2021 110 107 Hauptbahnhof
2022 111 107 Hauptbahnhof
2023 126 124 Hauptbahnhof
2024 110 109 Hauptbahnhof

Depending on the annual timetable, up to 20 minutes of timetable reserve is included. With the completion of further development stages, the shortest travel time should fall to 102 minutes in December 2020.[21] Further expansion stages are being planned (see below). In the long term, the aim is for a journey time of 90 minutes.[22] Currently (2024 timetable year) there are direct connections between the two major cities every hour during the day with a travel time of around two hours.

For journeys between Berlin and Prague, the use of multi-system locomotives has eliminated the need to change locomotives in Dresden since mid-2018 and the time spent at Dresden Hauptbahnhof has been shortened by 10 minutes.[22]

Planning and financing after 1990 edit

The Institute for Railway Construction at TU Dresden developed for the State of Saxony, concepts for various new lines in the new federal states in the second half of 1990. A new line was largely planned between Berlin and Dresden. This would have largely followed the existing line to the north of Großenhain and run in a southwesterly direction to the west of Cossebaude in order to be integrated into a planned high-speed line from Leipzig to Dresden. From Dresden a continuation towards Prague was planned.[23]

In 1991, the considerations were further developed. While planning to upgrade the existing line to 200 km/h (120 mph) was already underway, the university continued to recommend a new line.[23]

The upgrade of the line for higher speeds (than the 160 km/h already largely achieved) was listed in the 1992 Federal Transport Infrastructure Plan (Bundesverkehrswegeplan) as a new project with planned total costs of DM 395 million (1 January 1991 prices).[24]

Subsequently, preliminary plans were developed by 1996 to upgrade the line to a length of 148 km (92 mi) for a speed of 200 km/h. Uckro, Elsterwerda and Böhla were to be bypassed and Doberlug-Kirchhain station was to be rebuilt. The costs for this were estimated at DM 2.295 billion (1 January 1993 prices).[25]

Towards the end of these plans, an intergovernmental agreement was concluded on 7 June 1995 to further develop the Berlin–Prague–Vienna railway route. This was already based on a general development of the line for 200 km/h. In the long term, the travel time on the Berlin–Prague section should be reduced to three hours, which would also require the completion of a high-speed line from Dresden to Prague. However, a completion date was not agreed upon.[12]

On 5 June 1997, the transport ministers of Germany, the Czech Republic and Austria reached an agreement to upgrade the Berlin–Prague–Vienna axis.[26]

In October 1997, the Bahnbau Deutsche Einheit planning company was commissioned to plan and implement the development project. For DM 1.6 billion German, 125 km (78 mi) of railway line should be upgraded to a maximum speed of 200 km/h by 2008. The plan included the construction of 45 railway and 15 road bridges, 99 culverts, 435 km (270 mi) of overhead lines and twelve electronic signal boxes. The travel time between the main stations[27] of Berlin and Dresden was supposed to decrease from 111 minutes (1997) to 59 minutes.[28]

In 1998, it was decided to begin development work immediately, which had the character of maintenance and was to be completed in sections without any change in travel time by 2002. An upgrade to 200 km/h would only take place after 2003.[27]

The European Commission awarded a grant of €10 million in 2007 under the TEN program.[12]

On 11 December 2008, a financing agreement was signed for the continuous upgrading for 160 km/h as a continuation of the first stage of development. This would be completed by 2014 and the travel time would be reduced to around 103 minutes after the work was completed.[29][30]

From the funds of the economic stimulus package I in repsonse to the 2007–2008 financial crisis, the following funds were made available from 2009:[31]

  • Track renewal at Doberlug-Kirchhain: €2 million
  • Track renewal near Brenitz-Sonnewalde: €10 million
  • Complete renovation of the track structure, partial substructure with new construction of all bridges and removal of the level crossing between Weinböhla and Radebeul West (part of VDE 9): €34 million

In 2010, renewed planning became necessary in order to access the available funds and carry out the approved construction work. A cost–benefit analysis in April 2010 determined a benefit-cost ratio of 2.9 for the upgrade project.[32]

In mid-2010, the Federal Ministry of Transport expected that the total investment costs for the line upgrade would be €802 million.[33] The costs are broken down into the different implementation and upgrade stages as follows:

  • 1st upgrade stage, 1st implementation stage: €148 million.[29]
  • 1st upgrade stage, 2nd implementation stage: €224 million.[29][34]
  • 1st upgrade stage, further implementation stage(s): €213 million.[34]
  • 2nd upgrade stage: €217 million.[34]

No financing agreement had still not be achieved in 2010 for the last two points.[34]

In 2014, EU funding of €30 million was won from the European Regional Development Fund (ERDF) for the supra-regional function of the project.[35]

In order to implement the complex tasks required to realise the overall project, DB Netz set up a project that regularly provides information about the activities.[36] For this purpose, the work to be carried out was divided into three main line sections:

  • Berlin urban area to Berlin outer ring,
  • Berlin outer ring to Böhla,
  • Böhla to Dresden city center.

The planned work in the Berlin urban area was legally difficult because the intended use of the former Dresden Railway was locally controversial. The plans were only fully approved in 2019.[37]

The Berlin outer ring section to Böhla runs through predominantly rural areas. The development as a high-speed railway provides little economic benefit in this structurally weak area. After various individual projects on the part of Deutsche Bahn, the state and federal level felt compelled to overcome the deadlock through special funding for municipal contributions.[35] This made the complex and fundamental reconstruction possible between 2016 and 2018. Due to deployment problems with the required European Train Control System, the maximum speed of 200 km/h would only be achieved from the end of 2020.[38] The reason given is a version change to version SRS 3.4.0 of the ETCS specification ordered by the EU Commission in 2015. Now, ESTW and ETCS equipment would not be done in parallel, but one after the other.[38] The section between Berlin Südkreuz and Blankenfelde is to be equipped with ETCS by the end of 2025, and all remaining sections between Blankenfelde and Kottewitz junction are expected to be equipped by 2028. The ETCS equipment between Kottewitz and Dresden Hauptbahnhof is open.[39]

The Böhla–Neucoswig section near Dresden is part of the German Unity Transport Project (Verkehrsprojekte Deutsche Einheit, VDE) No. 9 to upgrade the Leipzig – Dresden line and is also included in the balance sheet in terms of costs. The Weißig–Böhla connecting curve links the Leipzig–Dresden railway in Böhla with the Berlin–Dresden railway. This means that this section can also be used by fast long-distance and freight traffic from and towards Leipzig. The former regional traffic between Großenhain and Radebeul via Weinböhla has been routed via Priestewitz and Coswig since 2002 and is thus separated from fast long-distance traffic.[40] The Dresden-Friedrichstadt-Radebeul-Naundorf section of the line, which historically belonged to the Berlin-Dresden Railway, is not part of the current upgrade projects as it is predominantly used for freight traffic. For this purpose, together with the VDE 9 project in connection with the upgrade of the Dresden railway junction, the Radebeul – Dresden-Neustadt line was restored to the four-tracks that existed before 1945 with a maximum speed of 160 km/h for the long-distance tracks.[41]

The measures were defined individually for each of these route and project sections, which will create a maximum line speed of 160 km/h as part of upgrade stage 1 and 200 km/h as part of upgrade stage 2.

After completion of all construction measures in upgrade stage 1, including the reactivation of the section in Berlin, the travel time between Berlin Südkreuz and Dresden-Neustadt would be 74 minutes. After completion of the Böhla–Radebeul section as part of VDE 9, the travel time is expected to be shortened by a further five minutes,[34] but this was not foreseeable in 2017 due to the lack of a tunnel south of Böhla.

The extensive expansion of the line to 200 km/h is referred to as upgrade stage 2. According to the new planning from 2010, the first sections of the line with this track quality were completed in 2012, without any impact on driving technology.

As part of the i2030 program, the states of Berlin and Brandenburg, among others, are investigating: an extension of the S-Bahn by around five kilometres to Rangsdorf with stations in Dahlewitz, Dahlewitz-Rolls-Royce and Rangsdorf. In April 2020, the financing agreement amounting to around €16 million in state funds for preliminary, draft and approval planning was signed.[42]

Development edit

Restoration of the Dresden Railway in Berlin edit

Overview edit

 
The now abandoned level crossing at Berlin-Lichtenrade station, 2011

Since the end of May 2006, most long-distance and regional trains to the Dresden Railway have been running from Berlin Hauptbahnhof through the Tiergarten Tunnel of the Berlin North–South mainline and meet the old line of the Dresden railway and the Berlin–Halle railway near Gleisdreieck. Until the inner-city line between Berlin Südkreuz station and the southern Berlin outer ring is restored, trains will run via a detour via the Berlin–Halle railway, a newly built connecting curve at Genshagener Heide and the Berlin outer ring to Glasower Damm junction. There the trains rejoin the Dresden Railway at line kilometre 19.0.

Once the upgrade has been completed, the trains will switch from the North-South long-distance railway to the Berlin-Dresden railway line (line kilometre 5.0) near Priesterweg station without level crossings.[43] The state of Berlin is planning to establish a stop for regional transport at Buckower Chaussee station. However, no specific decision to proceed was initially made in order not to further delay the planning approval process.[44] ​​A total of 14 railway bridges are being built, among other things.

The design speed in Berlin's urban area is (as of 2001) at 160 km/h.[45] The upgrade of the 14.2 km (8.8 mi)[45] long direct section between Südkreuz station and the southern outer ring (Blankenfelde) is intended to reduce travel time for long-distance passenger trains by around ten minutes.[12] In the final state, a travel time between Berlin and Dresden of 75 minutes would be possible (as of May 2014).[46] The upgrade is also important for connecting Berlin Brandenburg Airport with Airport Express trains.[47] After the Dresden Railway goes into operation in December 2025, the "Airport Express" will reach BER Airport from the Hauptbahnhof via a new connecting curve to the Berlin outer ring in 20 minutes.[48]

The reconstruction of the section is expected to cost around €558 million;[49] construction officially began in 2019 and commissioning is planned for the end of 2025.[50]

Planning approval procedure edit

The first planning approval procedure was initiated in 1998;[51] the last planning approval procedure (PFA 3) was completed in August 2019.[37] The middle section 2 (Berlin-Lichtenrade) was to be approved first, but this was delayed due to legal proceedings (see below).[34] In 2008, the DB accused the Berlin Senate of having delayed the process for implementing structural changes, which began in 1997, for several years.[43][52] At the end of July 2000, Deutsche Bahn announced that it would postpone the development of the access route in Berlin until further notice in order to save costs.[53]

The planned construction period after completion of the planning approval process was given as "four years" in 2009.[54]

In the meantime, the construction of a second entrance to Marienfelde station was proposed, which DB rejected due to high costs.[47] Another point of contention was a second entrance to Buckower Chaussee station requested by the Senate.[55]

The planned investment cost was stated as €470 million in 2009.[54] In the investment framework plan for federal transport infrastructure from 2006 to 2010, investments amounting to €430 million were planned for the restoration of the Südkreuz–Blankenfelde section.[56] The investment framework plan 2011–2015 gave the cost as €417.2 million.[57]

The reconstruction was divided into four planning approval phases (PFA):[37]

  • The PFA 4 (Schöneberg) begins at the exit from the Anhalter Bahn and extends to the Attilastraße station.[37] The exit structure and the subgrade in this section were built at the same time as the reconstruction of the Anhalter Bahn (Berlin–Halle railway).
  • The PFA 1 (Marienfelde[51]) extends from Südkreuz station to the Schichauweg stop.[49] The report of the hearing process was available at the end of 2012.[51] According to DB information, the submitted plans had to be corrected and then the public authorities would probably have to be heard again.[49] The planning approval decision for the 6.3 km (3.9 mi) long section was issued in May 2017.[58]
  • The 2.5 km (1.6 mi)[59] long PFA 2 (Lichtenrade[51]) leads from Schichauweg via Lichtenrade to the state border.[49] At the end of 2012, the Federal Railway Authority began developing the planning approval decision, which was available in November 2015.[60] In this section, the construction of a tunnel instead of an above-ground route was controversial. In its ruling of 29 June 2017, the Federal Administrative Court, as the first and last instance, dismissed all related lawsuits and, in particular, found that the Federal Railway Authority had rightly rejected the idea of ​​relocating the line into a tunnel. This solution, according to the court, is not preferable.[61]
  • In May 2013, Deutsche Bahn presented new plans for PFA 3 (Blankenfelde–Mahlow), which extends from the Berlin city limits to Blankenburg. After corrections in 2017, the planning approval decision was issued on 30 August 2019.[37] Two electrified long-distance railway tracks that can be used at speeds of 200 km/h and a connecting curve to BER Airport will be built. The parallel, largely single-track S-Bahn line is being modernised. At Blankenfelde station, the S-Bahn platform will be moved to the south and designed as a combined platform for S-Bahn and regional trains. Five level crossings will be replaced by bridges and noise barriers will be built.[62]

Dispute over a tunnel in Lichtenrade edit

While Deutsche Bahn sought planning approval for a surface route in Lichtenrade, residents and the Senate demanded that a tunnel be built.[47] Around 4,000 objections were raised in the proceedings against the surface route.[63] From 1998 onwards, the Berlin Senate also supported Lichtenrad's residents, who at the time included the later Governing Mayor Klaus Wowereit, and interrupted the planning approval process that had just begun for two years.[50] In 2008, several corresponding lawsuits from residents were pending before the Federal Administrative Court. The Berlin-Lichtenrade Dresdner Bahn citizens' initiative was founded in Lichtenrade and was committed to a tunnel solution.[43] The initiative called for a tunnel between Buckower Chaussee and the outskirts of the city; other initiatives wanted a tunnel that was around 1.2 km (0.75 mi) shorter and began at Schichauweg station.[64]

A feasibility study of various tunnel solutions carried out by Deutsche Bahn[51] in 2001 revealed additional costs of at least DM 254 million (equivalent to around €197 million in 2024). These would be even higher now due to increased safety requirements.[57] According to Deutsche Bahn, the federal government would not finance a tunnel solution.[65] The Berlin Senate Administration offered to contribute €30 million towards a tunnel solution. Various tunnel variants developed by Deutsche Bahn were examined by the Federal Railway Authority around 2012.[51] In May 2014, Deutsche Bahn announced that it would wait for a decision from the Federal Railway Authority as to whether an above-ground solution could be approved.[49] In 2015, State Secretary for Transport Christian Gaebler estimated the costs of a ground-level route at €128 million, that of a cut-and-cover tunnel at €223 million, and that of a tunnel with shield driving (as requested by the citizens' initiative) at €360 million. Commissioning would be delayed by eight years, to 2031.[59] While the citizens' initiative wanted to leave the S-Bahn on the surface, the DB expects that it would also have to run in the tunnel.[49]

In August 2015, the Federal Railway Authority decided in favour of the above-ground development sought by Deutsche Bahn.[66] A planning approval decision was issued on 13 November 2015.[61] Lawsuits against the decision were filed by a recognised environmental association and three owners at the Federal Administrative Court (BVerwG) as the first and last instance, as well as an application for interim legal protection. Deutsche Bahn sought immediate completion and announced that it would begin construction work in 2017 if possible.[67] The main hearing took place on 14 and 15 June 2017 in Leipzig,[68] the judgment of the Federal Administrative Court was issued on 29 June 2017 and dismissed the lawsuits. In particular, the Federal Railway Authority rejected the idea of ​​relocating the line into a tunnel without making any errors in consideration; it did not clearly a preferable solution.[61]

Construction edit

 
Construction at Blankenfelde station in June 2023

On 20 September 2017, an interactive information point was opened in the former train dispatcher's house at Lichtenrade station, providing information about the construction project. The construction work itself began in October 2017 with preparatory measures, including felling trees between Lichtenrade and the city limits. From November 2017, a temporary pedestrian bridge was built at the Säntisstraße railway crossing.[69] The level crossing was closed on 29 March 2018.[70]

The Marienfelde computer-based interlocking went into operation on 3 April 2018. It controls the track systems, which initially continue to be operated jointly by the S-Bahn and long-distance railways (freight transport). In addition to the new train control system (Zugbeeinflussungssystem S-Bahn Berlin, ZBS), the old Punktförmige Zugbeeinflussung (PZB) train control system is still used. The transition zone extends from Attilastrasse station to Lichtenrade station. In this context, the former Attilastraße halt was converted into a full station and Mariendorf (BMD) junction was closed.[70] On 2 December 2018, the transition zone (including ZBS) was extended to Blankenfelde, while maintaining the PZB on the shared line to Mahlow station.[71]

With the installation of the last element of a noise barrier at the Wolziger Zeile railway crossing in Berlin-Lichtenrade in the presence of the DB Infrastructure Board member, Ronald Pofalla, and the coordinator of TEN projects at the European Union, Mathieu Grosch, on 5 February 2019, construction of the Dresden Railway in the south of Berlin began. The planned total cost at the start of construction were estimated at around €560 million.[72]

The Berlin Hbf to Blankenfelde section is scheduled to go into operation in December 2025.[73][74] The remainder of the second phase of construction is scheduled to be commissioned in December 2028.[75]

Berlin outer ring to Böhla edit

The upgrade of the line between Blankenfelde (bei Berlin) to Böhla (near Dresden) is to be carried out in two construction stages over the entire section. The first development stage includes measures that enable a speed of 160 km/h (99 mph) with an option of 200 km/h (120 mph). The tracks, points and engineering structures are to be renewed and the control and safety technology is to be modernised.[12] After completion of the second development stage, in which all 35 level crossings will be eliminated, and with the commissioning of ETCS, operations at 200 km/h will be authorised.[76][77]

 
Upgrade of the line to Brenitz, May 2010

Preliminary planning for the upgrade began in 2002.[67] Following a decision by the Mediation Committee of the federal parliament to reduce subsidies in December 2003, numerous new construction and upgrade measures in the transport infrastructure, including those on the Berlin–Dresden railway line, were delayed. The first construction stage was therefore divided into several implementation stages. As part of the first implementation stage, the upgrade would only took place from Doberlug-Kirchhain to around Hohenleipisch and between Wünsdorf and Neuhof with a total length of 21 km (13 mi) by the end of 2006.[12] In 2005, the federal government stopped the work.[67] In April 2007, Deutsche Bahn also listed the further upgrade of the line among the "projects postponed in the medium term".[78] Planning was resumed in 2009.[67] The upgrade of the following section from Doberlug-Kirchhain to Brenitz and Sonnewalde, including signalling and safety technology, took place from the end of 2010 to 2011.

The second implementation stage includes the following project sections:

From the end of 2011 to the end of 2012, as the third part of the first stage, the section between Neuhof and Baruth was to be upgraded to 200 km/h.[79] According to media reports from 2010, it was not yet possible to predict when the first construction stage would be completed. There was still no concrete schedule for the second construction phase (as of 2010).[80] Construction of the second construction phase would not begin before 2015 (as of February 2009).[81] During the renovation work in the first construction stage, all measures are being carried out for a line speed of 200 km/h.[82]

On 28 July 2010, Deutsche Bahn announced that it would reorganize the upgrade of the line. As far as building permits were available, the approximately 80 km (50 mi) long Wünsdorf – Hohenleipisch section was to be upgraded between 2012 and December 2014—with complete closures in sections—for a maximum speed of 200 km/h. To do this, 21 level crossings would have to be removed and this section would have to be equipped with ETCS. The travel time between Berlin and Dresden would be reduced to a maximum of one and a half hours.[83][76]

 
Doberlug-Kirchhain tower station in the direction of Berlin

As of 2012, the Wünsdorf–Neuhof, Uccro–Walddrehna and Brenitz–Hohenleipisch sections were upgraded to 160 km/h with the possibility of operations at 200 km/h.

According to plans from October 2011, the approximately 80 km long Wünsdorf – Elsterwerda section was to be completely closed in 2014 in order to convert all level crossings to make them grade-separated.[84]

In June 2012 it became known that, according to the Federal Ministry of Transport, completion, which was unofficially planned for 2016 at the time, was at risk. Deutsche Bahn did not give a date for completion of the upgrade, but announced that it would submit the planning approval documents for the sections that have not yet been approved by the end of 2012.[85] Deutsche Bahn saw financing problems on the part of the road construction authorities for the removal of around 20 level crossings in Brandenburg.[86] At the end of 2012, agreements under the Railway Crossing Act had been concluded for two level crossings, corresponding agreements were in preparation for 14 others, and 11 further agreements were to be approved by the end of 2013. A crossing agreement was still pending for four other crossings due to a lack of funds. The state of Brandenburg promised to promote the municipal share with unbundling funds.[51] The state of Brandenburg announced in September 2013 that it would assume large parts of the municipalities' own contributions required under the Railway Crossing Act. In Brandenburg, 75 percent of the municipal share of the removal of the 21 level crossings in the 16 affected municipalities is to be paid for from state funds; financially distressed municipalities could receive up to 90 percent. The state of Saxony promised general support, but made no specific commitment.Cite error: A <ref> tag is missing the closing </ref> (see the help page).

Because there was no building permit, this section was not scheduled to go into operation for 200 km/h before 2016, as of the end of 2012.[51] Deutsche Bahn announced another delay in June 2013, according to which the full closure of the Wünsdorf–Elsterwerda section, originally planned for the 2016 annual timetable, was postponed to 2017.[87] The reason for this was that there were still outstanding crossing agreements to eliminate a total of 21 level crossings in the Brandenburg section.[88] In mid-2013, the upgraded line was scheduled to be put into operation at the end of 2017. At the beginning of September 2013, Deutsche Bahn wanted to discuss with the Federal Railway Authority and the transport ministries of Berlin and Brandenburg how the upgrade could be accelerated.[89] According to DB information from the end of 2013, the expansion measures for 160 km/h should be completed in 2017 and the travel time should then be shortened by 25 minutes compared to 2013. The majority of the work should take place in Brandenburg; in Saxony, only a line improvement at Großenhain is necessary.[90] At the 2018 timetable change, the travel time between Berlin and Dresden was planned to be reduced by 20 minutes, to one hour and 45 minutes (as of 2015).[91] The further upgrade to 200 km/h, which was to be completed in 2018, would bring savings of another five minutes.[90]

 
Construction work near ​​the Elsterwerda-Biehla crossing (2014)

According to information from the beginning of 2014, 80 km (50 mi) of 125 km (78 mi)of the upgraded route should be passable at 200 km/h by the end of 2018. This would reduce the scheduled travel time between Berlin and Dresden by 20 to 106 minutes.[35] According to DB information from May 2014, the 125 km long section between the Berlin outer ring and Kottewitz would be completely closed from August 2016. Among other things, nine stations are to be rebuilt, 20 level crossings removed and a European Train Control System installed. The contract award should begin in May 2015.[46] At the end of November 2014, Deutsche Bau advertised the construction work for the reconstruction of the section between Neuhof and Hohenleipisch in the Official Journal of the European Union.[92] The upgraded section between Hohenleipisch and Elsterwerda was scheduled to be put into operation at the end of 2015 for a permissible speed of 160 km/h.[93]

 
Demolition work in Elsterwerda (2016)

Construction of the upgrade to 200 km/h since 2014 edit

From 2013 to 2016, Rangsdorf station was completely rebuilt for €40 million,[46] and Elsterwerda station was rebuilt from mid-2014 to July 2015.[94][95] Between June 2014 and June 2016, an electronic signal box was built for the Elsterwerda and Hohenleipisch area[96] and the six km (3.7 mi) long section was also rebuilt by the end of 2016.[97].

On 30 May 2016, the formal start of construction (1st construction stage) on the Baruth (Mark) – Hohenleipisch section of the line was celebrated in Baruth in the presence of DB boss Rüdiger Grube, Parliamentary State Secretary Norbert Barthle and Brandenburg's Transport Minister Kathrin Schneider.[98] The 73 km (45 mi) long section between Wünsdorf-Waldstadt and Elsterwerda was upgraded during a full closure of the line that lasted from 5 August 2016 to 9 December 2017. In addition to the renewal of tracks, platforms and railway technology, 18 level crossings were replaced with bridges. After the upgrade is complete, a travel time of 107 minutes should be achieved.

In order to be able to fully close the route for construction projects, long-distance trains in particular were rerouted via the partly single-track Jüterbog–Röderau railway line and the Berlin–Halle railway line. Despite the longer route, the journey time did not increase due to use of the high-speed sections between Jüterbog and Berlin Südkreuz. In addition, trains were occasionally rerouted via Leipzig (without stopping).

In front of the upgraded route at Zossen[99] and at Doberlug-Kirchhain[100] there are still speed limits of 50 km/h.

With the commissioning of ETCS, travel time should be further reduced.[101] Since 4 December 2020 [102] the section Neuhof (b Zossen) to Rückersdorf (Niederl) has been operable at 200 km/h. However, as there are not yet enough vehicles with ETCS equipment available, a further reduction in travel time has not yet been achieved.

Once all construction work has been completed, the travel time from Berlin to Dresden should be reduced to 69 minutes (as of 2009)[103] and the line between Blankenfelde[104] and a few kilometres from Dresden[104] should be operable at 200 km/h.

From 2020 to 2022, the Wünsdorf-Waldstadt station was rebuilt.[105] Zossen station has been being rebuilt since January 2023. The work is scheduled to be completed in 2025.[106] The 2nd construction stage, with the sections Blankenfelde (exclusively) – Wünsdorf-Waldstadt (exclusively), the Doberlug-Kirchhain station and Elsterwerda – Großenhain Berliner Bahnhof, is planned to be completed by 2028.[39]

From the mid-2020s, a travel time of 80 minutes was planned (as of 2016).[67] With the construction of the Kockelsberg Tunnel, a travel time of 78 minutes would be possible (as of 2020).[39] For cost reasons, the Gehren bend (160 km/h) and the Hohenleipisch–Elsterwerda section (160 km/h) have been excluded. The line is not included in the Federal Railway Authority's ETCS national implementation plan, so there has been no prioritised increase in the maximum speed as a result of implementing ETCS Level 2 even after 2023.[107] The Doberlug-Kirchhain area (140 km/h (87 mph)) should also be accessible at 200 km/h at a later date, after a bridge has been replaced.

The state of Saxony submitted the Berlin-Dresden upgrade and a connecting new line towards Prague for the 2030 Federal Transport Infrastructure Plan.[108]

Böhla to Dresden edit

As part of the sections assigned to the Leipzig–Dresden upgraded line, initial construction work began in 2008 on the Weißig–Böhla connecting curve. The connecting line is connects with the Berlin – Dresden line at a grade-separated and went into operation in December 2010.[109] volume The further expansion sections Böhla–Weinböhla and Weinböhla station[110] were originally supposed to be completed by 2016, but have not yet started (as of 2022).[111] One component of this is the Kockelsberg Tunnel, which has been under consideration since the 1990s and has been part of the planning since 2020. At the timetable change on 15 December 2002, Weinböhla station on the line to Berlin was closed and a stop of the same name was opened on the line to Leipzig.[112]

As part of the economic stimulus package I, the Weinböhla – Neucoswig and Neucoswig – Radebeul West sections were modernised in 2010. As a result, the line between Neucoswig and Großenhain was closed for a year after the timetable change in December 2009.[109] The six kilometre long section between Neucoswig and Weinböhla was completely rebuilt.[109] In the area of ​​the crossing structure of the former Az signal box up to the area of ​​Radebeul-Zitzschewig station, bridges were replaced between the beginning of 2018 and mid-2020 and curve radii were increased.[113][114]

Route description edit

 
Elsterwerda station
 
Niederwartha railway bridge over the Elbe

The comparatively flat topography meant that only a few engineering structures were necessary, and the line has a slight incline. It runs from Berlin Südkreuz station in a southerly direction through the urban area of ​​Berlin, leaving it after Lichtenrade. After Mahlow S-Bahn station, the line crosses Berlin outer ring and it continues south. The Berlin S-Bahn ends in Blankenfelde. From here on, the long-distance tracks to the south are used. After Dahlewitz, A 10 (the Berliner Ring), is crossed and the outskirts of Berlin are left at Rangsdorf. After Zossen, where a now closed line branches off towards Jüterbog, the railway crosses the Notte canal. The line runs through the Wünsdorf lakes area and through extensive forest landscapes. Baruth station is located at the transition from the Fläming Heath to the Glogau-Baruth glacial valley. Lower Lusatia is reached near Golßen. At Uckro, the line crosses the closed Falkenberg–Beeskow railway and runs through two curves through the Gehren hills before continuing through the forests of Lower Lusatia to the Doberlug-Kirchhain two-level station. The Halle–Cottbus railway is crossed here. From there it runs past the Bad Erna recreational lakes and from Rückersdorf through a wooded area towards Hohenleipisch station, located on a curve, and on to Elsterwerda.

The industrial town of Elsterwerda, which is also a medium-sized railway junction, lies in a valley of the Black Elster. Several line branch off from the station, which is rather small despite its importance (towards Hoyerswerda, Riesa and Falkenberg). Shortly after the station, two rivers, the Black Elster and the Pulsnitz, are crossed. This is also the transition into the landscape of Großenhain care . In the urban area of ​​Großenhain the railway to Priestewitz and Cottbus crosses. The Weißig–Böhla connecting curve north of Böhla integrates fast long-distance traffic from the Leipzig–Dresden railway line . After Böhla, the route reaches the northern edge of the Elbe basin and descends relatively winding to the former Weinböhla train station. From Böhla, the two railway lines Leipzig-Dresden and Berlin-Dresden run almost parallel and partly within sight of Dresden, with both lines crossing each other west of Radebeul. Double-track connecting curves link the routes together and enable the transition from Berlin towards Dresden-Neustadt and from Leipzig towards Dresden-Friedrichstadt and in the opposite direction.

The Elbe is crossed over a long steel bridge at Niederwartha before continuing along the left bank of the Elbe past the pumped storage plant to Dresden-Friedrichstadt train station . The Berlin–Dresden route has its nominal end point at Dresden-Friedrichstadt train station. Two connecting curves create a connection to the Děčín–Dresden-Neustadt line and enable train journeys towards Dresden-Neustadt on the one hand and towards Dresden Hbf and Dresden-Plauen on the other.

Train operations edit

 
Regionalbahn train in the Dresden city area on the Berlin-Dresden railway line on the left bank of the Elbe, with the Briesnitz church in the background

Since the long-distance railway tracks of the Berlin–Dresden railway in the city of Berlin have not yet been rebuilt, train traffic has to take the detour described above via the Anhalter Bahn and the Berlin outer ring and only reaches the actual Berlin–Dresden railway before Blankenfelde . Between Großenhain Berliner Bahnhof and Radebeul-Naundorf, regional traffic does not run on the Berlin–Dresden railway line, but rather on the Großenhain–Priestewitz railway line, which runs almost parallel , and the route from Leipzig ( Leipzig–Dresden railway line ).

The following table shows the long-distance and regional transport lines that run on the Berlin–Dresden route (as of 2023):

Linie Zuglauf Streckenabschnitt Takt (min)
IC 17 (Warnemünde –) Rostock – Waren – Neustrelitz – Oranienburg – Berlin-Gesundbrunnen – Berlin-Hauptbahnhof – Berlin-Südkreuz – Flughafen Berlin Brandenburg – Doberlug-Kirchhain – Elsterwerda – Dresden-Neustadt – Dresden Hbf (– Freiberg – Chemnitz (2 Zugpaare)) Blankenfelde – Dresden 120
EC 27 (Hamburg-Altona / WesterlandHamburg Hbf –) Berlin Hbf (tief)Dresden Hbf – (Praha hl.n. (– BratislavaBudapest)) BlankenfeldeNeucoswig 120
RJ 258/259 Berlin Hbf (tief)Dresden HbfDecin hl.n. – Praha hl.n.Brno hl.n.Wien HbfGraz Hbf 1× /Tag
RE 8 Berlin Hbf (tief) – Berlin Südkreuz – Wünsdorf-Waldstadt – Elsterwerda/Finsterwalde Blankenfelde – Elsterwerda 120 (60)
RB 24 (Berlin Hbf (tief) – Berlin Ostkreuz –) Flughafen Berlin-BrandenburgWünsdorf-Waldstadt Blankenfelde – Wünsdorf-Waldstadt 60
RB 31 Elsterwerda-BiehlaElsterwerda – Großenhain Cottb Bf – Dresden Hbf Elsterwerda – Großenhain / Radebeul-Naundorf – Dresden 120
S 2 BernauBerlin FriedrichstraßeBlankenfelde Berlin-Südkreuz – Blankenfelde 20 (10)

In addition, several other trains use the route. These are e.g. T. Special trains .

Like the RE trains, the IC/EC trains travel to Berlin-Südkreuz and thus the Tiergarten Tunnel to Berlin Hbf.

Furthermore, as part of the renovation of the Berlin–Cottbus route between Königs-Wusterhausen and Lübbenau/Spreewald, the RegionalExpress trains on the RE 2 line, the IC train pair Norddeich Mole/Emden Outer Harbor–Hannover–Berlin–Cottbus and the EC train pair Hamburg- Altona–Berlin–Cottbus–Kraków Glówny the route between Blankenfelde and the Doberlug-Kirchhain Nord junction. The RE-2 trains ran between Berlin-Südkreuz and Calau (Niederlausitz) and did not stop at any stations on the Dresden railway.

A new IC line Dresden–Berlin–Rostock has been offered on the route since December 2019. Initially, ten trains will run per day, which will also serve Schönefeld Airport from May 2020. Since November 2020, the BER Airport train station has been directly connected with regular stops. The offer is to be expanded to 16 trains per day.[115]

Operation under ETCS edit

In December 2020, a first section of the route with ETCS was put into operation between Neuhof (b Zossen) and Rückersdorf (Niederl) . This equipment remains unused for the time being on long-distance transport services (Railjet, Intercity and Eurocity). Vehicles without ETCS equipment (according to Baseline 3 ) continue to operate under PZB  90 protection at a maximum speed of 160 km/h.

From 2021, test drives with the Intercity 2 trains ( Stadler KISS ), which have been in use since 2019, are planned and will be used commercially with ETCS on the route from 2022.[116] From summer 2022, KISS multiple units in the Hohenleipisch–Baruth section will run with ETCS and up to 200 km/h over the route.[117] From 2024, international trains with ETCS will also run on the route.[116]

In 2025, when operations begin on the newly built Berlin-Südkreuz – Blankenfelde long-distance railway line, ETCS Level 2 will also go into operation in addition to PZB and conventional signals. In the long term, the entire route is to be equipped with ETCS.

References edit

  1. ^ Eisenbahnatlas Deutschland (German railway atlas). Schweers + Wall. 2009. pp. 36, 47, 59, 72–3, 127–8. ISBN 978-3-89494-139-0.
  2. ^ Kaiß & Hengst 1994, p. 169.
  3. ^ Bley 1993, p. 26.
  4. ^ "Mahlow und die S-Bahn, Biografie anlässlich der Wiederinbetriebnahme der S-Bahn-Strecke Lichtenrade–Mahlow–Blankenfelde" (PDF) (in German). 31 August 1992. Archived from the original (PDF) on 21 October 2007. Retrieved 2 May 2024.
  5. ^ Kaiß & Hengst 1994, p. 172f.
  6. ^ Bley 1993, pp. 53 ff.
  7. ^ a b Thomas, Horst (1992). "Ab Fahrplanwechsel Berlin–Dresden mit 160 km/h". Die Deutsche Bahn (in German). 5: 529–531.
  8. ^ a b "Mit Tempo 160 von Berlin nach Dresden". Signal + Draht (in German). 84 (9): 283. 1992. ISSN 0037-4997.
  9. ^ "Jahresrückblick 1992: Personenverkehr". Die Deutsche Bahn (in German) (1): 32–40. 1993.
  10. ^ "Dresden an ICE-Strecke nach Berlin angeschlossen". Süddeutsche Zeitung (in German). No. 222. 1994. p. 6. ISSN 0174-4917.
  11. ^ "Fünf Strecken fallen ganz weg". n-tv.de (in German). 19 April 2001. Retrieved 3 May 2024.
  12. ^ a b c d e f "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Jan Mücke, Horst Friedrich (Bayreuth), Patrick Döring, weiterer Abgeordneter und der Fraktion der FDP" (PDF). Parliamentary Record (in German) (16/5024). Deutscher Bundestag. 16 May 2007. Retrieved 3 May 2024.
  13. ^ Babbe, Dieter (27 June 2012). "Kein ICE-Halt in Doberlug-Kirchhain". Lausitzer Rundschau (in German). Archived from the original on 6 October 2013. Retrieved 3 May 2024.
  14. ^ Rehkopf, Manuel (26 August 2013). Vollständige Inbetriebnahme der Neu-/Ausbaustrecke VDE 8, Angebotskonzept DB Fernverkehr AG (presentation) (in German). DB Fernverkehr. p. 10.
  15. ^ Based on a ticket for 5 January 2019 from Berlin-Südkreuz 7:23 AM (platform 3) to Dresden-Neustadt 9:00 AM (platform 7)
  16. ^ a b "Eisenbahnverbindung Berlin – Elsterwerda – Dresden (1): Antwort des sächsischen Staatsministeriums für Wirtschaft und Arbeit auf die kleine Anfrage des Abgeordneten Johannes Lichdi, Fraktion Bündnis 90/Die Grünen" (PDF). Parliamentary Record (in German) (4/13878). Landtag of Saxony. Archived from the original (PDF) on 30 December 2015. Retrieved 4 May 2024.
  17. ^ "Qualitätsanalyse Netzzustand 2011" (PDF) (in German). Verkehrsverbund Berlin Brandenburg. June 2019. p. 3.{{cite web}}: CS1 maint: url-status (link)
  18. ^ Kaiß & Hengst 1994, p. 171.
  19. ^ Deutsche Bahn timetable accessed 28 August 2018
  20. ^ "Deutsches Kursbuch Sommer 1939, 133a Berlin – Elsterwerda – Dresden" (in German). 1939. Retrieved 4 May 2024.
  21. ^ Rothe, Michael (26 May 2016). "Schnelle Bahnverbindung: Dresden–Berlin kommt noch später". Sächsische Zeitung (in German). Retrieved 4 May 2024.
  22. ^ a b "Änderungen im Fernverkehrsfahrplan 2018". deutschebahn.com. Deutsche Bahn. 16 October 2017. Archived from the original on 22 October 2017. Retrieved 22 October 2017.
  23. ^ a b Zschweigert, Manfred (April 1992). "Hochgeschwindigkeitsstrecken in den neuen Bundesländern". Der Eisenbahningenieur (in German). 43 (4): 234–238. ISSN 0013-2810.
  24. ^ Bundesverkehrswegeplan 1992 (in German). Bundesministerium für Verkehr. p. 21.
  25. ^ "Unterrichtung der Bundesregierung. Bericht zum Ausbau der Schienenwege 1996" (PDF). Parliamentary Record (in German) (13/6929). Deutscher Bundestag. 4 February 1997. Retrieved 5 May 2024.
  26. ^ Bahnstadt Berlin: Ausbau der Infrastruktur von 1990 bis 2015 (in German). Berlin: Deutsche Bahn. 2006. p. 55.
  27. ^ a b "Ausbau der Schienenwege nach Dresden". Eisenbahn-Revue International (in German) (12): 507. 1998. ISSN 1421-2811.
  28. ^ Wirtschaftlich bauen. Schneller fahren (brochure) (in German). Berlin: Planungsgesellschaft Bahnbau Deutsche Einheit. 30 November 1997. p. 28.
  29. ^ a b c "Bahn baut Strecke Berlin–Dresden für Tempo 160 aus". Die Welt (in German). 27 November 2008. Retrieved 5 May 2024.
  30. ^ "ABS Berlin – Dresden, 1. und 2. Baustufe" (PDF) (in German). SPD, Landtagsfraktion Sachsen. 9 November 2009. Archived from the original (PDF) on 28 November 2018. Retrieved 5 May 2024.
  31. ^ "Mittel für Schienenstrecken und Terminals aus den Konjunkturprogrammen 1 und 2" (PDF) (in German). Bundesministerium für Verkehr, Bau und Stadtentwicklung. 29 July 2009.{{cite web}}: CS1 maint: url-status (link)
  32. ^ "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Dr. Anton Hofreiter, Winfried Hermann, Dr. Valerie Wilms, weiterer Abgeordneter und der Fraktion Bündnis 90/Die Grünen – Drucksache 17/4035 – Überprüfung des Bedarfsplans Schiene" (PDF). Parliamentary Record (in German) (17/4270). Deutscher Bundestag. 16 December 2010. Retrieved 5 May 2024.
  33. ^ "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Stephan Kühn, Bettina Herlitzius, Winfried Hermann, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN: "Stand der Umsetzung bei den Bedarfsplanprojekten Schiene im Freistaat Sachsen: ABS Berlin–Dresden, ABS Karlsruhe–Stuttgart–Nürnberg–Leipzig/Dresden und ABS Hoyerswerda–Horka–Grenze D/PL"" (PDF). Parliamentary Record (in German) (17/2094). Deutscher Bundestag. 14 June 2010. Retrieved 5 May 2024.
  34. ^ a b c d e f "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Stephan Kühn, Bettina Herlitzius, Winfried Hermann, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN – Drucksache 17/1842" (PDF). Parliamentary Record (in German) (17/2094). Deutscher Bundestag. 14 June 2010. Retrieved 5 May 2024.
  35. ^ a b c "Reiche: Die EU gibt 30 Millionen Euro für den Ausbau der Strecke Berlin–Dresden aus dem EFRE-Fonds" (in German). Bundesministerium für Verkehr und digitale Infrastruktur. Archived from the original on 5 March 2016. Retrieved 5 May 2024.
  36. ^ "Bauprojekt Berlin – Dresden" (in German). DB Netz AG. 2017. Retrieved 5 May 2024.
  37. ^ a b c d e "Berlin Südkreuz – Blankenfelde (Dresdner Bahn)" (in German). Deutsche Bahn. September 2019. Archived from the original on 13 September 2019. Retrieved 7 May 2024.
  38. ^ a b Bung, Michael (31 May 2016). "Keine leichte Übung" (in German). DB Netz AG. Retrieved 5 May 2024.
  39. ^ a b c "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Stephan Kühn (Dresden), Matthias Gastel, Stefan Gelbhaar, Daniela Wagner und der Fraktion BÜNDNIS 90/DIE GRÜNEN – Drucksache 19/17666 – Umsetzung des Bedarfsplans Schiene und Finanzierung der Schienenprojekte im Freistaat Sachsen" (PDF). Parliamentary Record (in German). 19 (18476). Berlin: Deutscher Bundestag: 3–6. 2 April 2020. ISSN 0722-8333. Retrieved 10 May 2024.
  40. ^ "Grundsteinlegung für die Ausbaustrecke Leipzig–Dresden". Die Deutsche Bahn (in German) (9/10): 729. 1993.
  41. ^ "Bauprojekt Knoten Dresden". bauprojekte.deutschebahn.com (in German). DB Netz AG. 2017. Archived from the original on 11 July 2017. Retrieved 5 May 2024.
  42. ^ "Verlängerung der S2 von Blankenfelde nach Rangsdorf: Planungen erreichen nächste Stufe" (Press release) (in German). Verkehrsverbund Berlin-Brandenburg. 14 April 2020. Archived from the original on 30 June 2020. Retrieved 5 May 2024.
  43. ^ a b c "Regionalbahn soll Airport-Shuttle ersetzen". Welt online (in German). 10 January 2008. Retrieved 6 May 2024.
  44. ^ "Drucksache 17/15264" (PDF) (in German). Abgeordnetenhaus Berlin. 27 January 2015. Retrieved 6 May 2024.
  45. ^ a b Drehscheibe Berlin. Pilzkonzept (24-page brochure) (in German). DB Projekt Verkehrsbau. November 2001. p. 16.
  46. ^ a b c Rothe, Michael (15 May 2014). "Brahms und die Zukunftsmusik Dresden–Berlin". Sächsische Zeitung. p. 19.
  47. ^ a b c Kurpjuweit, Klaus (23 February 2012). "Planungsprobleme bremsen Airport-Express". Potsdamer Neueste Nachrichten (in German). p. 16. Archived from the original on 13 February 2015.
  48. ^ "S2 nach Blankenfelde sechs Wochen gesperrt" (in German). Retrieved 6 May 2024.
  49. ^ a b c d e f Kurpjuweit, Klaus (12 May 2014). "Die Bahn will nicht unter die Erde". Der Tagesspiegel (in German). No. 22042. p. 11. Retrieved 7 May 2024.
  50. ^ a b Neumann, Peter (7 March 2013). "Bahnverkehr: Erst 2022 schnell zum Flughafen". Berliner Zeitung (in German). Archived from the original on 21 November 2015. Retrieved 7 May 2024.
  51. ^ a b c d e f g h "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Stephan Kühn, Renate Künast, Dr. Valerie Wilms, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN" (PDF). Parliamentary Record (in German) (17/11584). Deutscher Bundestag. 11 December 2012. Retrieved 6 May 2024.
  52. ^ "Wowereit-Kritik an Mehdorns Tempelhof-Engagement symptomatisch für Umgang mit Wirtschaftsstandort Berlin" (Press release) (in German). Deutsche Bahn. 10 April 2008.
  53. ^ Tietze, Christian (2000). ""Schrumpfkonzept" für Berliner Fernbahnkreuz?". Eisenbahn-Revue International (in German) (11): 524–527. ISSN 1421-2811.
  54. ^ a b "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten (…): Lärmschutz beim Ausbau der Dresdner Bahn" (PDF). Parliamentary Record (in German) (17/11991). Deutscher Bundestag. 16 February 2009. Retrieved 6 May 2024.
  55. ^ Kurpjuweit, Klaus (15 July 2012). "Dresdner Bahn wird dauerhaft ausgebremst". Der Tagesspiegel (in German). No. 21392. p. 13.
  56. ^ Investitionsrahmenplan bis 2010 für die Verkehrsinfrastruktur des Bundes (in German). Bundesministerium für Verkehr, Bau und Stadtentwicklung. April 2007.
  57. ^ a b "Drucksache 17/10914" (PDF) (in German). Abgeordnetenhaus Berlin. 17 September 2012. Retrieved 7 May 2024.
  58. ^ "Baugenehmigung für weiteren Abschnitt der "Dresdner Bahn" in Berlin erteilt" (Press release) (in German). Deutsche Bahn. 30 May 2017. Archived from the original on 9 July 2017. Retrieved 6 May 2024.
  59. ^ a b Anker, J.; Fülling, T. (14 November 2015). "Dresdner Bahn kommt oberirdisch". Berliner Zeitung (in German). No. 311. p. 15. ISSN 0947-174X.
  60. ^ Planfeststellungsbeschluss – Ausbau Knoten Berlin – Berlin Südkreuz – Blankenfelde ("Wiederaufbau der Dresdner Bahn") – Planfeststellungsabschnitt 2 – Bahn-km 12,300 bis 14,762 der Strecken 6135 Berlin Südkreuz – Elsterwerda und 6035 Berlin – Blankenfelde. Eisenbahn-Bundesamt. 13 November 2015.
  61. ^ a b c "Klagen gegen den Ausbau der Dresdner Bahn in Berlin-Lichtenrade erfolglos" (BVerwG 3 A 1.16) (in German). Bundesverwaltungsgericht. 29 June 2017. Retrieved 7 May 2024.
  62. ^ "Kurzmeldungen – Eisenbahn". Berliner Verkehrsblätter. No. 10. 2019. p. 202.
  63. ^ "Der Airport-Express steht im Stau". Tagesspiegel (in German). 4 January 2008. Retrieved 7 May 2024.
  64. ^ Kurpjuweit, Klaus (5 September 2013). "Lichtenrader demonstrieren für ihren Bahntunnel". Der Tagesspiegel (in German). No. 21800. p. 14. Retrieved 7 May 2024.
  65. ^ "Bahn-Chef Grube will Airport-Shuttles realisieren". Berliner Morgenpost (in German). 20 April 2012. Retrieved 7 May 2024.
  66. ^ Kurpjuweit, Klaus (15 August 2015). "Kein Licht am Ende". Der Tagesspiegel (in German). No. 22491. p. 13. Retrieved 7 May 2024.
  67. ^ a b c d e Neumann, Peter (29 October 2016). "Mit Tempo 200 von Berlin nach Dresden". Berliner Zeitung (in German). ISSN 0947-174X.
  68. ^ Keitel, Horst-Dieter (28 April 2017). "Die Entscheidung naht: Gerichtsurteil zum Dresdner Bahn-Ausbau erwartet". Berliner Woche (in German). Retrieved 7 May 2024.
  69. ^ "So hört sich die Dresdner Bahn an". punkt 3 (in German). No. 19. 2017. p. 12. Archived from the original on 28 November 2018. Retrieved 7 May 2024.
  70. ^ a b "Kurzmeldungen – Eisenbahn". Berliner Verkehrsblätter (in German) (5): 100. 2018.
  71. ^ "Kurzmeldungen – S-Bahn". Berliner Verkehrsblätter (in German) (2): 30. 2019.
  72. ^ "Baubeginn für Dresdner Bahn im Süden Berlins" (Press release) (in German). Deutsche Bahn AG. 5 February 2019. Archived from the original on 6 February 2019. Retrieved 8 May 2024.
  73. ^ Naumann, Peter (21 September 2017). "Bauarbeiten für die neue Dresdener Bahn beginnen". Berliner Zeitung (in German). Archived from the original on 22 September 2017. Retrieved 8 May 2024.
  74. ^ "Grünes Licht für Dresdner Bahn in Brandenburg" (Press release) (in German). Deutsche Bahn. 13 September 2019. Archived from the original on 17 October 2019. Retrieved 8 May 2024.
  75. ^ "Etappierung Deutschlandtakt" (in German). Federal Ministry for Digital and Transport. August 2022. p. 13. Archived from the original (PDF) on 17 October 2019. Retrieved 8 May 2024.
  76. ^ a b "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Stephan Kühn, Cornelia Behm, Hans-Josef Fell, weiterer Abgeordneter und der Fraktion Bündnis 90/Die Grünen" (PDF). Parliamentary Record (in German) (17/2782). Deutscher Bundestag. 20 August 2010. Retrieved 8 May 2024.
  77. ^ "Schriftliche Fragen mit den in der Woche vom 20. November 2006 eingegangenen Antworten der Bundesregierung" (PDF). Parliamentary Record (in German) (16/3570). Deutscher Bundestag. 24 November 2006. Retrieved 8 May 2024.
  78. ^ "Bahn investiert kräftig in das Berliner Netz". Berliner Morgenpost (in German). 18 April 2007.
  79. ^ "D-Berlin: Bauarbeiten für Eisenbahnlinien". Tenders Electronic Daily (2011/S 87-141810). 5 May 2011.
  80. ^ "Schnelle Bahn nach Berlin kommt viel später". Sächsische Zeitung (in German). 18 June 2010.
  81. ^ "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Dr. Lothar Bisky, Dr. Dagmar Enkelmann, Diana Golze, weiterer Abgeordneter und der Fraktion Die Linke: "Bau einer Eisenbahnunterführung in Rangsdorf"" (PDF). Parliamentary Record (in German) (16/11846). Deutscher Bundestag. 6 February 2009. Retrieved 6 May 2024.
  82. ^ "Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Jan Mücke, Horst Friedrich (Bayreuth), Patrick Döring, weiterer Abgeordneter und der Fraktion der FDP: "Entwicklung ost- und mitteldeutscher Eisenbahnverbindungen"" (PDF). Parliamentary Record (in German) (16/10763). Deutscher Bundestag. 3 November 2008. Retrieved 8 May 2024.
  83. ^ "Bahngipfel Sachsen: DB sagt schnellere Verbindung von Dresden nach Berlin verbindlich zu" (Press release) (in German). Deutsche Bahn. 28 July 2010.
  84. ^ Claus, Frank (22 December 2011). "Bahn bremst Tunnel in Elsterwerda aus". Lausitzer Rundschau (in German).
  85. ^ Alexe, Thilo (4 June 2012). "Bahnreisende brauchen weiter Geduld". Sächsische Zeitung (in German). p. 6.
  86. ^ "Die Strecke muss schneller werden". Dresdner Neueste Nachrichten (in German). No. 146. 25 June 2012. p. 6.
  87. ^ Rothe, Michael (12 September 2013). "Brandenburger Millionen für Bahnlinie Dresden–Berlin". Sächsische Zeitung (in German). p. 25.
  88. ^ "Bahnübergänge verzögern Bahnausbau Berlin–Dresden" (Press release) (in German). DB Mobility Logistics AG. 10 June 2013. Archived from the original on 2 October 2013. Retrieved 9 May 2024.
  89. ^ Rothe, Michael; Winzer, Tobias (11 June 2013). "Die Bahn feilt an einem Masterplan für Sachsen". Sächsische Zeitung (in German). p. 1.
  90. ^ a b Franke, Jan-Dirk (18 February 2013). "Ab 2017 geht es schneller von Dresden nach Berlin". Freie Presse (in German). Retrieved 9 May 2024.
  91. ^ "Mehr Bahn für Metropolen und Regionen" (PDF) (presentation) (in German). Deutsche Bahn. 18 March 2015. p. 7. Archived from the original (PDF) on 4 April 2015. Retrieved 9 May 2024.
  92. ^ "Deutschland-Berlin: Gleisbauarbeiten". Tenders Electronic Daily (in German) (Document 2014/S 230-406604). 28 November 2014. Retrieved 9 May 2024.
  93. ^ "Inbetriebnahmen zum bzw. im Netzfahrplan 2016" (PDF) (in German). DB Netze. Archived from the original (PDF) on 27 May 2015. Retrieved 9 May 2024.
  94. ^ "Deutschland-Frankfurt am Main: Bauarbeiten für Eisenbahnlinien". Tenders Electronic Daily (Document 2014/S 063-108028). 29 March 2014.
  95. ^ "Bahnsteige barrierefrei erreichbar - Katrin Lange bei feierlicher Einweihung in Elsterwerda" (Press release) (in German). 7 July 2015. Archived from the original on 22 December 2015. Retrieved 9 May 2024.
  96. ^ "Deutschland-Frankfurt am Main: Installation von Fernmeldeanlagen". Tenders Electronic Daily (in German) (Document 2014/S 049-082434). 11 March 2014.
  97. ^ "Deutschland-Frankfurt am Main: Bau von Eisenbahnbrücken". Tenders Electronic Daily (in German) (Document 2014/S 053-089163). 15 March 2014.
  98. ^ "Start für Ausbau von 73 Kilometer langem Abschnitt auf der Ausbaustrecke Berlin–Dresden" (Press release) (in German). Deutsche Bahn. 30 May 2016. Archived from the original on 2 June 2016. Retrieved 10 May 2024.
  99. ^ "Strecke 6135" (Glasower Damm Süd [BAG S] → Elsterwerda [BEW] (19,066 → 122,75)) (in German). berlindresden.streckenkunde. Archived from the original on 31 January 2018. Retrieved 10 May 2024.
  100. ^ "Streckenprospekt Ausbaustrecke Wünsdorf – Elsterwerda" (PDF) (in German). DB Netz AG. September 2017. p. 32. Retrieved 10 May 2024.
  101. ^ "Vom 5. August 2016 bis 9. Dezember 2016 fahren zwischen Wünsdorf-Waldstadt und Elsterwerda Busse, Umleitung im Fernverkehr" (Press release) (in German). Deutsche Bahn. 29 July 2016. Archived from the original on 31 July 2016. Retrieved 10 May 2024.
  102. ^ "Inbetriebnahme ABS Berlin-Dresden: Zulassung ETCS-Fahrzeuge" (in German). DB Netz. 19 September 2019. Archived from the original on 6 October 2019. Retrieved 10 May 2024.
  103. ^ "Unterrichtung durch die Bundesregierung: Verkehrsinvestitionsbericht 2009" (PDF). Parliamentary Record (in German). 19 (444). Berlin: Deutscher Bundestag: 41 f. 2 April 2020. ISSN 0722-8333. Retrieved 10 May 2024.
  104. ^ a b "Neue Straßenbrücke für mehr Sicherheit und Bahntempo auf der Ausbaustrecke Berlin–Dresden" (in German). Deutsche Bahn. 28 August 2015. Archived from the original on 28 August 2015. Retrieved 10 May 2024.
  105. ^ "Umbau des Bahnhofs Wünsdorf-Waldstadt" (PDF) (in German). Deutsche Bahn. Retrieved 10 May 2024.
  106. ^ "Bürgerinformationsveranstaltung, Ausbaustrecke Berlin-Dresden, 1. Baustufe, Umbau des Bahnhofs Zossen" (PDF) (in German). Deutsche Bahn. 30 March 2023. Retrieved 10 May 2024.
  107. ^ "Nationaler Umsetzungsplan ETCS" (PDF) (in German). Eisenbahn-Bundesamt. 11 December 2017. Retrieved 10 May 2024.
  108. ^ "Ausbau Bahntrasse Dresden-Berlin geplant". Leipziger Volkszeitung (in German). 9 April 2013. p. 6. ISSN 0232-3222.
  109. ^ a b c "DB investiert 80 Millionen Euro in moderne Fernbahngleise zwischen Radebeul West und Weißig" (Press release) (in German). Deutsche Bahn. 3 December 2010.
  110. ^ "Verkehrsinvestitionsbericht für das Berichtsjahr 2010" (PDF). Parliamentary Record (in German). 17 (8700). Berlin: Deutscher Bundestag: 60. 2 April 2020. ISSN 0722-8333. Retrieved 10 May 2024.
  111. ^ Reinike, Frederike (2012). "Weitblick". Weitblick (in German). Hauptverband der Deutschen Bauindustrie. p. 11–13. ISBN 978-3-00-038025-9.
  112. ^ "Neuer Haltepunkt Weinböhla". Eisenbahn-Revue International (in German). 2003 (4).
  113. ^ "Leipzig – Dresden; Ausbau der Strecke im Rahmen des "Verkehrsprojekts Deutsche Einheit Nummer 9 (VDE 9)"" (in German). Deutsche Bahn. 2018. Archived from the original on 9 December 2018. Retrieved 10 May 2024.
  114. ^ "Ausbaustrecke Leipzig–Dresden: Deutsche Bahn nimmt die Kurve Dresden–Elsterwerda (DEK) in Betrieb". Deutsche Bahn. 27 April 2020.
  115. ^ "Fahrplanwechsel: Mehr Züge, häufigere Verbindungen". deutschebahn.com. Deutsche Bahn. 2019-10-10. Retrieved 2019-10-11.
  116. ^ a b "Stenografischer Bericht, 191. Sitzung" (PDF). dipbt.bundestag.de (Plenarprotokoll 19/191). Deutscher Bundestag. 2020-11-18. pp. 24173 (145 im PDF). Retrieved 2020-12-30.
  117. ^ "Erste Neuigkeiten zum Fernreiseverkehr im DB-Netz ab dem Fahrplanjahr 2022", Eisenbahn-Revue International, no. 8–9, pp. 438 f., 2021-08, ISSN 1421-2811 {{citation}}: Check date values in: |date= (help)

Sources edit

  • Bley, Peter (1993). Berlin S-Bahn (in German). Düsseldorf: publication Alba. p. 26.
  • Bley, Peter (1999). 125 Jahre Berlin–Dresdener Eisenbahn (125 years of the Berlin-Dresden railway) (in German). Düsseldorf: Alba Publikation. ISBN 3-87094-360-2.
  • Kaiß, Kurt; Hengst, Matthias (1994). Dresdens Eisenbahn (Dresden Railway): 1894–1994 (in German). Düsseldorf: Alba Publikation. ISBN 3-87094-350-5.
  • "Dresdener Bahn" (in German). beefland. Retrieved 23 May 2010.