Submission declined on 29 December 2023 by KylieTastic (talk).
Where to get help
How to improve a draft
You can also browse Wikipedia:Featured articles and Wikipedia:Good articles to find examples of Wikipedia's best writing on topics similar to your proposed article. Improving your odds of a speedy review To improve your odds of a faster review, tag your draft with relevant WikiProject tags using the button below. This will let reviewers know a new draft has been submitted in their area of interest. For instance, if you wrote about a female astronomer, you would want to add the Biography, Astronomy, and Women scientists tags. Editor resources
|
Submission declined on 20 December 2023 by Jovanmilic97 (talk). This draft's references do not show that the subject qualifies for a Wikipedia article. In summary, the draft needs multiple published sources that are: Declined by Jovanmilic97 5 months ago.
|
Submission declined on 19 December 2023 by Mach61 (talk). This draft's references do not show that the subject qualifies for a Wikipedia article. In summary, the draft needs multiple published sources that are: Declined by Mach61 5 months ago.
|
Submission declined on 18 December 2023 by NoobThreePointOh (talk). This draft's references do not show that the subject qualifies for a Wikipedia article. In summary, the draft needs multiple published sources that are: Declined by NoobThreePointOh 5 months ago.
|
- Comment: Nothing has changed since the last declined and the concerns haven't been addressed. Please add more references. Jovanmilic97 (talk) 10:50, 20 December 2023 (UTC)
- Comment: Neither source is independent, they are from affiliated construction companies. Mach61 (talk) 17:18, 19 December 2023 (UTC)
Hermosa-San Jose Transmission Line | |
---|---|
Location | |
Founded | May 27, 2023 |
Country | Philippines |
Province | Hermosa, Bataan and San Jose del Monte, Bulacan |
General direction | heading West |
From | Hermosa Substation |
Passes through | Guagua, Candaba Swamp, NLEX Candaba Viaduct, Pampanga and Pulilan |
To | San Jose Substation |
Ownership information | |
Owner | National Grid Corporation of the Philippines (NGCP) |
Operator | National Grid Corporation of the Philippines (NGCP) |
Construction information | |
Cable layer | TASCR/AS |
Contractors | First Balfour, BAUER |
Construction cost | P10.2 billion |
Technical information | |
Total length | 82.41 km (51.21 mi) |
No. of transmission towers | 96 |
AC voltage | 500 kV |
Technical description edit
The line conductor is 4x410mm2 TACSR/AS conductor, quadruple bundle power line, and double circuit line. The line consists of 96 lattice towers.[1]
Notes edit
References edit
- ^ "Hermosa-San Jose Transmission line". First Balfour. May 27, 2023. Archived from the original on September 30, 2023. Retrieved December 19, 2023.
- in-depth (not just passing mentions about the subject)
- reliable
- secondary
- independent of the subject
Make sure you add references that meet these criteria before resubmitting. Learn about mistakes to avoid when addressing this issue. If no additional references exist, the subject is not suitable for Wikipedia.