This is an annotated list of all the nuclear reactors in the world, sorted by country, with operational status. The list includes military, commercial and research reactors, excludes nuclear marine propulsion reactors, except those at land installations.

Contents

AlgeriaEdit

Research reactorsEdit

  • Es Salam (The Peace), 15 MW nuclear reactor for research, located in Aïn Oussera, in service since 1993
  • Nur, research reactor built by Argentine INVAP

AntarcticaEdit

  • McMurdo StationPM-3A NNPU "Nukey Poo" US Navy power reactor (operational 1962, shut down 1972, fully dismantled 1979)[1]

ArgentinaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Atucha[2][3][4] 1 PHWR PHWR KWU   Operational 335 362 1 June 1968 24 June 1974
Atucha[5] 2 PHWR PHWR KWU   Operational 692 745 14 July 1981 (mothballed between 1994 and 2007) 27 June 2014
Atucha[6] 3 PHWR CANDU-6   Planned 800 January 2018 2025
5th Plant[7] 1 PWR Hualong-1   Planned 1000 2020 2026
Embalse [8] 1 PHWR CANDU-6   Operation suspended for maintenance[9] 600 648 1 April 1974 20 January 1984

Research reactors [10]Edit

Name Reactor Status Capacity in kWt Construction start date Operation date Closure Operator and owner
RA-0 Tank type   Operational 0.001 1958 Universidad Nacional de Córdoba
RA-1 Enrico Fermi Tank type   Operational 40 May 1957 17 January 1958 National Atomic Energy Commission
RA-2 Critical assembly type   Shut down 0.03 19 July 1966 September 1983 National Atomic Energy Commission
RA-3 Pool type   Operational 10,000 20 December 1967 National Atomic Energy Commission
RA-4 HOMOG type   Operational 0.001 September 1971 Universidad Nacional de Rosario
RA-6 Pool type   Operational 3,000 1 September 1978 23 September 1982 National Atomic Energy Commission
RA-8 Critical assembly type   Operation suspended 0.01 16 June 1997 2001 National Atomic Energy Commission
RA-10   Under construction 30,000 March 2016 National Atomic Energy Commission
CAREM 25 Small modular reactor   Under construction 25,000 8 February 2014 National Atomic Energy Commission

ArmeniaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Metsamor 1 PWR VVER V-270   Shut down 376 408 1 July 1969 6 October 1977 25 February 1989
Metsamor 2 PWR VVER V-270   Operational 375 408 1 July 1975 3 May 1980

AustraliaEdit

Research reactorsEdit

AustriaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Zwentendorf 1 BWR   Finished; never started 692 April 1972 5 November 1978

Research reactorsEdit

  • Austrian Research Centers at Seibersdorf — 10 MW ASTRA research reactor (in use 1960–1999)
  • Atomic Institute of the Austrian Universities in Vienna — 250 kW TRIGA Mark II research reactor (in use since 1962)
  • Reactor Institute of the Technical University in Graz — 10 kW Siemens Argonaut research reactor (operated from 1965–2004)

BangladeshEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Ruppur 1 PWR VVER-1200/523   Planned 1150 1200 August 2017 2023
Ruppur 2 PWR VVER-1200/523   Planned 1150 1200 2018 2024

Research reactorsEdit

  • SavarTRIGA Mark II, Atomic Energy Research Establishment (installed 1986)

BelarusEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Ostrovets 1 PWR VVER V-491   Under construction 1109 1194 6 November 2013 2019
Ostrovets 2 PWR VVER V-491   Under construction 1109 1194 24 April 2014 2020

Research reactorsEdit

  • Sosny, Minsk
    • IRT research reactor (shut down 1988)
    • "Pamir" - mobile nuclear power reactor test (shut down 1986)

BelgiumEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction
start date
Commercial
operation date
Closure
(planned)
Type Model Net Gross
Doel 1 PWR WE-2 loops   Operational 433 454 1 July 1969 15 February 1975 (2025)
Doel 2 PWR WE-2 loops   Operational 433 454 1 September 1971 1 December 1975 (2025)
Doel 3 PWR Framatome 3-loops   Operational 1006 1056 1 January 1975 1 October 1982 (2022)
Doel 4 PWR WE-3 loops   Operational 1039 1090 1 December 1978 1 July 1985 (2025)
Tihange 1 PWR Framatome 3-loops   Operational 962 1009 1 June 1970 1 October 1975 (2025)
Tihange 2 PWR Framatome 3-loops   Operational 1008 1055 1 April 1976 1 June 1983 (2023)
Tihange 3 PWR WE-3 loops   Operational 1046 1094 1 November 1978 1 September 1985 (2025)

Research reactorsEdit

BrazilEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Angra 1 PWR WE-2 loops   Operational 609 640 1 May 1971 1 January 1985
Angra 2 PWR PRE KONVOI   Operational 1275 1350 1 January 1976 1 February 2001
Angra 3 PWR PRE KONVOI   Under construction 1245 1350 1984 (halted in 1986, restarted on 1 June 2010)

Research reactorsEdit

  • São Paulo – IEA-R1 – Pool-type reactor, 5MW – IPEN-Instituto de Pesquisas Energéticas e Nucleares, São Paulo, SP (criticality 1957-09-16)
  • Belo Horizonte – IPR-R1 – TRIGA Mark I, 250 kW - CDTN-Centro de Desenvolvimento de Tecnologia Nuclear, Belo Horizonte, MG (criticality 1960-11-06)
  • Rio de Janeiro – ARGONAUTA – Argonaut class reactor, 100 kW – IEN-Instituto de Engenharia Nuclear, Rio de Janeiro, RJ (criticality 1965-02-20)
  • São Paulo – IPEN/MB-01 – Critical assembly, 0.1 kW – IPEN-Instituto de Pesquisas Energéticas e Nucleares, São Paulo, SP (criticality 1988-11-09)

BulgariaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Kozloduy 1 PWR VVER-440/V-230   Shut down 408 440 1 April 1970 28 October 1974 31 December 2002
Kozloduy 2 PWR VVER-440/V-230   Shut down 408 440 1 April 1970 10 November 1975 31 December 2002
Kozloduy 3 PWR VVER-440/V-230   Shut down 408 440 1 October 1973 20 January 1981 31 December 2006
Kozloduy 4 PWR VVER-440/V-230   Shut down 408 440 1 October 1973 20 June 1982 31 December 2006
Kozloduy 5 PWR VVER-1000/V-320   Operational 963 1000 9 July 1980 23 December 1988
Kozloduy 6 PWR VVER-1000/V-320   Operational 963 1000 1 April 1982 30 December 1993
Belene 1 PWR VVER-1000/V-320
VVER-1000/V-446B
  Unfinished 1000
Belene 2 PWR VVER-1000/V-320
VVER-1000/V-446B
  Unfinished 1000

Research reactorsEdit

CanadaEdit

Power Station ReactorsEdit

Name Unit
No.
Reactor Status Capacity in MWe Construction Start Date Commercial Operation Date Closure

(Planned)

Type Model Net Gross
Pickering A 1 PHWR CANDU   Operational 515 542 June 1966 29 July 1971 (2022)
Pickering A 2 PHWR CANDU   Shut Down 515 542 September 1966 30 December 1971 1997
Pickering A 3 PHWR CANDU   Shut Down 515 542 December 1967 1 June 1972 1997
Pickering A 4 PHWR CANDU   Operational 515 542 May 1968 17 June 1973 (2022)
Pickering B 5 PHWR CANDU   Operational 516 540 November 1974 10 May 1983 (2024)
Pickering B 6 PHWR CANDU   Operational 516 540 October 1975 1 February 1984 (2024)
Pickering B 7 PHWR CANDU   Operational 516 540 March 1976 1 January 1985 (2024)
Pickering B 8 PHWR CANDU   Operational 516 540 September 1976 28 February 1986 (2024)
Darlington 1 PHWR CANDU   Operational 878 934 April 1982 14 November 1992 (2052)
Darlington 2 PHWR CANDU   Operational 878 934 September 1981 9 October 1990 (2050)
Darlington 3 PHWR CANDU   Operational 878 934 September 1984 14 February 1993 (2053)
Darlington 4 PHWR CANDU   Operational 878 934 July 1985 14 June 1993 (2053)
Bruce A 1 PHWR CANDU   Operational 750 805 June 1971 1 September 1977 (2042)
Bruce A 2 PHWR CANDU   Operational 750 805 December 1970 1 September 1977 (2043)
Bruce A 3 PHWR CANDU   Operational 750 805 July 1972 1 February 1978 (2053)
Bruce A 4 PHWR CANDU   Operational 750 805 September 1972 18 January 1979 (2054)
Bruce B 5 PHWR CANDU   Operational 795 845 June 1978 1 March 1985 (2052)
Bruce B 6 PHWR CANDU   Operational 822 872 January 1978 15 September 1984 (2052)
Bruce B 7 PHWR CANDU   Operational 822 872 May 1979 10 April 1986 (2052)
Bruce B 8 PHWR CANDU   Operational 795 845 August 1979 22 May 1987 (2052)
NPD 1 PHWR CANDU   Shut Down 19.5 22 January 1958 4 June 1962 1987
Douglas Point 1 PHWR CANDU-6   Shut Down 200 220 February 1960 26 September 1968 1984
Gentilly 1 BWR CANDU   Shut Down 250 266 September 1966 1 May 1972 1977
Gentilly 2 PHWR CANDU-6   Shut Down 635 675 April 1974 1 October 1983 2012
Point Lepreau 1 PHWR CANDU   Operational 635 660 May 1975 1 February 1983 (2041)

Research ReactorsEdit

Chalk River Laboratories - Chalk River, Ontario

  •   MAPLE 1 (NEVER USED) - Medical isotope production reactor. Built, incomplete commissioning, no operating license
  •   MAPLE 2 (NEVER USED) - Medical isotope production reactor. Built, incomplete commissioning, no operating license
  •   NRU (OPERATING) - 135 MW reactor used for research and medical isotope production
  •   NRX (NOT OPERATING) - One of the highest flux reactors in the world until shut down
  •   SLOWPOKE-1 prototype (NOT OPERATING) - Moved to University of Toronto, later upgraded to SLOWPOKE-2 - decommissioned
  •   PTR (NOT OPERATING) - Pool test reactor shut down in 1990
  •   ZED-2 (OPERATING) - 1960 - Zero-energy reactor, still operational
  •   ZEEP (NOT OPERATING) - The first nuclear reactor in Canada in 1945, and first outside the United States

Whiteshell Laboratories - Pinawa, Manitoba

  •   WR-1 (NOT OPERATING) - Organically cooled CANDU class reactor 1965-1985. Plant had coolant leak of 2,739 litres in November 1978.[20]
  •   SLOWPOKE-3 demonstration reactor (NOT OPERATING) - Shut down in 1989

Saskatchewan Research Council - Saskatoon, Saskatchewan

Nordion - Kanata, Ontario

Tunney's Pasture - Ottawa, Ontario

  •   SLOWPOKE-2 prototype (NOT OPERATING) - Shut down in 1984

Dalhousie University - Halifax, Nova Scotia

  •   SLOWPOKE-2 reactor (NOT OPERATING) - Decommissioned (2009); dismantled (2011)

École Polytechnique de Montréal - Montreal, Quebec

McMaster University- Hamilton, Ontario

Royal Military College - Kingston, Ontario

University of Alberta - Edmonton, Alberta

  •   SLOWPOKE-2 reactor (OPERATING) - Planned Decommissioning 2017

University of Toronto - Toronto, Ontario

ChileEdit

Research reactorsEdit

  • RECH 1 – Pool-type reactor, 5 MWt MTR – Comisión Chilena de Energía Nuclear, Santiago (criticality 1974)
  • RECH 2 – Pool-type reactor, 10 MWt MTR – Comisión Chilena de Energía Nuclear, Santiago (criticality 1977, refurbished 1989)

ChinaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Changjiang I 1 PWR CNP-600   Operational 610 650 25 April 2010 25 December 2015
Changjiang I 2 PWR CNP-600   Operational 610 650 21 November 2010 20 June 2016
Changjiang II 3 PWR CNP-600   Planned 610 650
Changjiang II 4 PWR CNP-600   Planned 610 650
Daya Bay (Guangdong) 1 PWR M-310   Operational 944 984 7 August 1987 1 February 1994
Daya Bay (Guangdong) 2 PWR M-310   Operational 944 984 7 April 1988 6 May 1994
Fangchenggang 1 PWR CPR-1000   Operational 1000 1080 30 July 2010 25 October 2015
Fangchenggang 2 PWR CPR-1000   Operational 1000 1080 23 December 2010 15 July 2016
Fangchenggang 3 PWR Hualong-1   Under construction 1080 1150 24 December 2015
Fangchenggang 4 PWR Hualong-1   Under Construction 1080 1150 23 December 2016
Fangchenggang 5 PWR AP-1000   Planned 1117 1250
Fangchenggang 6 PWR AP-1000   Planned 1117 1250
Fangjiashan 1 PWR CPR-1000   Operational 1000 1080 26 December 2008 15 December 2014
Fangjiashan 2 PWR CPR-1000   Operational 1000 1080 17 July 2009 12 February 2015
Fuqing I 1 PWR CPR-1000   Operational 1000 1080 21 November 2008 19 November 2014
Fuqing I 2 PWR CPR-1000   Operational 1000 1080 17 June 2009 15 October 2015
Fuqing II 3 PWR CPR-1000   Operational 1000 1080 31 December 2010 7 September 2016
Fuqing II 4 PWR CPR-1000   Operational 1000 1080 17 November 2012 31 July 2017
Fuqing II 5 PWR Hualong-1   Under construction 1080 1150 15 April 2015
Fuqing II 6 PWR Hualong-1   Under construction 1080 1150 22 December 2015
Haiyang I 1 PWR AP-1000   Under construction 1100 1250 24 September 2009
Haiyang I 2 PWR AP-1000   Under construction 1100 1250 20 June 2010 2017
Haiyang II 3 PWR AP-1000   Planned 1100 1250
Haiyang II 4 PWR AP-1000   Planned 1100 1250
Haiyang III 5 PWR AP-1000   Planned 1100 1250
Haiyang III 6 PWR AP-1000   Planned 1100 1250
Haiyang III 7 PWR AP-1000   Planned 1100 1250
Haiyang III 8 PWR AP-1000   Planned 1100 1250
Hongyanhe I 1 PWR CPR-1000   Operational 1061 1119 18 August 2007 6 June 2013
Hongyanhe I 2 PWR CPR-1000   Operational 1061 1119 28 March 2008 13 May 2014
Hongyanhe I 3 PWR CPR-1000   Operational 1000 1080 7 March 2009 23 March 2015
Hongyanhe I 4 PWR CPR-1000   Operational 1000 1080 15 August 2009 1 April 2016
Hongyanhe II 5 PWR Hualong-1   Under construction 1080 1150 29 March 2015 Nov 2019
Hongyanhe II 6 PWR Hualong-1   Under Construction 1080 1150 24 July 2015 August 2020
Ling Ao I 1 PWR M-310   Operational 950 990 15 May 1997 28 May 2002
Ling Ao I 2 PWR M-310   Operational 950 990 28 November 1997 8 January 2003
Ling Ao II 3 PWR CPR-1000   Operational 1007 1080 15 December 2005 15 September 2010
Ling Ao II 4 PWR CPR-1000   Operational 1007 1080 15 June 2006 7 August 2011
Ningde I 1 PWR CPR-1000   Operational 1018 1087 18 February 2008 15 April 2013
Ningde I 2 PWR CPR-1000   Operational 1018 1080 12 November 2008 4 May 2014
Ningde I 3 PWR CPR-1000   Operational 1018 1080 8 January 2010 10 June 2015
Ningde I 4 PWR CPR-1000   Operational 1018 1080 29 September 2010 29 March 2016
Ningde II 5 PWR Hualong-1   Planned 1080 1150
Ningde II 6 PWR Hualong-1   Planned 1080 1150
Pengze 1 PWR AP-1000   Planned 1100 1250 2016-2017
Pengze 2 PWR AP-1000   Planned 1100 1250 2016-2017
Qinshan I 1 PWR CNP-300   Operational 298 310 20 March 1985 1 April 1994
Qinshan II 1 (2) PWR CNP-600   Operational 610 650 2 June 1996 15 April 2002
Qinshan II 2 (3) PWR CNP-600   Operational 610 650 1 April 1997 3 May 2004
Qinshan II 3 (4) PWR CNP-600   Operational 610 650 28 April 2006 5 October 2010
Qinshan II 4 (5) PWR CNP-600   Operational 610 650 28 January 2007 30 December 2011
Qinshan III 1 (6) PHWR CANDU-6   Operational 650 728 8 June 1998 31 December 2002
Qinshan III 2 (7) PHWR CANDU-6   Operational 650 728 25 September 1998 24 July 2003
Sanmen 1 PWR AP-1000   Under construction 1000 1250 19 April 2009 2017
Sanmen 2 PWR AP-1000   Under construction 1000 1250 15 December 2009
Shidaowan 1 PWR CAP-1400   Under construction 1500 1550 25 April 2015
Shidaowan 2 PWR CAP-1400   Planned 1500 1550
Taohuajiang 1 PWR AP-1000   Planned 1100 1250 2016-2017
Taohuajiang 2 PWR AP-1000   Planned 1100 1250 2016-2017
Taishan 1 PWR EPR   Under construction 1660 1750 18 November 2009 2017
Taishan 2 PWR EPR   Under construction 1660 1750 15 April 2010
Tianwan 1 PWR VVER V-428   Operational 990 1060 20 October 1999 17 May 2007
Tianwan 2 PWR VVER V-428   Operational 990 1060 20 September 2000 16 August 2007
Tianwan 3 PWR VVER V-428M   Under construction 990 1060 27 December 2012 2016
Tianwan 4 PWR VVER V-428M   Under construction 990 1060 27 September 2013 2017
Tianwan 5 PWR ACPR-1000   Under construction 1000 1080 27 December 2015 Dec 2020
Tianwan 6 PWR ACPR-1000   Under construction 1000 1080 7 September 2016 Oct 2021
Tianwan 7 PWR VVER-1200   Planned 1150 1200
Tianwan 8 PWR VVER-1200   Planned 1150 1200
Xianning 1 PWR AP-1000   Planned 1100 1250 2016-2017
Xianning 2 PWR AP-1000   Planned 1100 1250 2016-2017
Xiapu[21] 1 Fast Reactor   Planned 600 2017
Yangjiang I 1 PWR CPR-1000   Operational 1021 1086 16 December 2008 25 March 2014
Yangjiang I 2 PWR CPR-1000   Operational 1021 1080 4 June 2009 8 June 2015
Yangjiang I 3 PWR CPR-1000+   Operational 1080 1089 15 November 2010 1 January 2016
Yangjiang I 4 PWR CPR-1000+   Operational 1080 1089 17 November 2012 8 January 2017
Yangjiang II 5 PWR ACPR-1000   Under construction 1000 1087 18 September 2013
Yangjiang II 6 PWR ACPR-1000   Under construction 1000 1087 23 December 2013
Zhangzhou 1 PWR Hualong-1   Planned 1080 1150
Zhangzhou 2 PWR Hualong-1   Planned 1080 1150

Research reactorsEdit

  • CEFR Chinese Experimental Fast Reactor (65 MWt, 20 MWe, sodium cooled fast-spectrum neutron reactor). Located at CIAE Beijing, construction started May 2000, first criticality July 2010.

ColombiaEdit

Research reactorsEdit

  • Bogotá – IAN-R1, 100 kW – TRIGA, Institute of Nuclear Science (installed in 1997)

Democratic Republic of the CongoEdit

Research reactorsEdit

  • TRICO I – TRIGA reactor, CREN-K (University of Kinshasa), 50 kW (initial criticality 1959, shut down 1970)
  • TRICO II – TRIGA reactor, CREN-K (University of Kinshasa), 1 MW (initial criticality 1972, extended shut down since 2004)[22]

CubaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Juragua 1 PWR VVER-440 V-318   Unfinished 440 1983 5 September 1992
Juragua 2 PWR VVER-440 V-318   Unfinished 440 1985 5 September 1992

Czech RepublicEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Dukovany 1 PWR VVER V-213   Operational 468 500 1 January 1979 3 May 1985
Dukovany 2 PWR VVER V-213   Operational 471 500 1 January 1979 21 March 1986
Dukovany 3 PWR VVER V-213   Operational 468 500 1 March 1979 20 December 1986
Dukovany 4 PWR VVER V-213   Operational 471 500 1 March 1979 19 July 1987
Temelín 1 PWR VVER V-320   Operational 1003 1056 1 February 1987 10 June 2002
Temelín 2 PWR VVER V-320   Operational 1003 1056 1 February 1987 18 April 2003

Research reactorsEdit

DenmarkEdit

Research reactorsEdit

  • Risø – DR-3 DIDO class experimental reactor (shut down permanently in 2000)
  • Risø – DR-2 experimental reactor (shut down in 1975)
  • Risø – DR-1 experimental reactor (shut down permanently in 2001)

EgyptEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction
start date
Commercial
operation date
Closure
(planned)
Type Model Net Gross
El Dabaa 1 PWR VVER-1200   Planned 1200 2024
El Dabaa 2 PWR VVER-1200   Planned 1200
El Dabaa 3 PWR VVER-1200   Planned 1200
El Dabaa 4 PWR VVER-1200   Planned 1200

Research reactorsEdit

EstoniaEdit

Research reactorsEdit

  • Paldiski – 2 PWR naval training reactors (dismantled)

FinlandEdit

Nuclear power plants in Finland (view)
  Active plants
  Planned plants

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Loviisa 1 PWR VVER-440/V-213   Operational 496 520 1 May 1971 9 May 1977
Loviisa 2 PWR VVER-440/V-213   Operational 496 520 1 August 1972 5 January 1981
Olkiluoto 1 BWR ABB-III, BWR-2500   Operational 880 910 1 February 1974 10 October 1979
Olkiluoto 2 BWR ABB-III, BWR-2500   Operational 880 910 1 November 1975 10 July 1982
Olkiluoto 3 PWR EPR   Under construction 1600 1720 12 August 2005 2019
Hanhikivi 1 PWR VVER-1200/V-491   Planned 1200 2019

Research reactorsEdit

  • EspooTRIGA Mark II, State Institute for Technical Research (installed 1962, decommissioned 2015)

FranceEdit

Fission-electric stations in France (view)
  Active plants
  Closed plants

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Belleville 1 PWR P4 REP 1300   Operational 1310 1363 1 May 1980 1 June 1988
Belleville 2 PWR P4 REP 1300   Operational 1310 1363 1 August 1980 1 January 1989
Blayais 1 PWR CP1   Operational 910 951 1 January 1977 1 December 1981
Blayais 2 PWR CP1   Operational 910 951 1 January 1977 1 February 1983
Blayais 3 PWR CP1   Operational 910 951 1 April 1978 14 November 1983
Blayais 4 PWR CP1   Operational 910 951 1 April 1978 1 October 1983
Brennilis 1 HWGCR MONTS-D'ARREE   Shut down 70 75 1 July 1962 1 June 1968 31 July 1985
Bugey 1 GCR UNGG   Shut down 540 555 1 December 1965 1 July 1972 27 May 1994
Bugey 2 PWR CP0   Operational 910 945 1 November 1972 1 March 1979
Bugey 3 PWR CP0   Operational 910 945 1 September 1973 1 March 1979
Bugey 4 PWR CP0   Operational 880 917 1 June 1974 1 July 1979
Bugey 5 PWR CP0   Operational 880 917 1 July 1974 3 January 1980
Cattenom 1 PWR P4 REP 1300   Operational 1300 1362 29 October 1979 1 April 1987
Cattenom 2 PWR P4 REP 1300   Operational 1300 1362 28 July 1980 1 February 1988
Cattenom 3 PWR P4 REP 1300   Operational 1300 1362 15 June 1982 1 February 1991
Cattenom 4 PWR P4 REP 1300   Operational 1300 1362 28 September 1983 1 January 1992
Chinon A 1 GCR UNGG   Shut down 70 80 1 February 1957 1 February 1964 16 April 1973
Chinon A 2 GCR UNGG   Shut down 180 230 1 August 1959 24 February 1965 14 June 1985
Chinon A 3 GCR UNGG   Shut down 360 480 1 March 1961 4 August 1966 15 June 1990
Chinon B 1 PWR CP2   Operational 905 954 1 March 1977 1 February 1984
Chinon B 2 PWR CP2   Operational 905 954 1 March 1977 1 August 1984
Chinon B 3 PWR CP2   Operational 905 954 1 October 1980 4 March 1987
Chinon B 4 PWR CP2   Operational 905 954 1 February 1981 1 April 1988
Chooz A 1 PWR CHOOZ-A   Shut down 305 320 1 January 1962 15 April 1967 30 October 1991
Chooz B 1 PWR N4 REP 1450   Operational 1500 1560 1 January 1984 15 May 2000
Chooz B 2 PWR N4 REP 1450   Operational 1500 1560 1 January 1984 15 May 2000
Civaux 1 PWR N4 REP 1450   Operational 1495 1561 15 October 1988 29 January 2002
Civaux 2 PWR N4 REP 1450   Operational 1495 1561 1 April 1991 23 April 2002
Cruas 1 PWR CP2   Operational 915 956 1 August 1978 2 April 1984
Cruas 2 PWR CP2   Operational 915 956 15 November 1978 1 April 1985
Cruas 3 PWR CP2   Operational 915 956 15 April 1979 10 September 1984
Cruas 4 PWR CP2   Operational 915 956 1 October 1979 11 February 1985
Dampierre 1 PWR CP1   Operational 890 937 1 February 1975 10 September 1980
Dampierre 2 PWR CP1   Operational 890 937 1 April 1975 16 February 1981
Dampierre 3 PWR CP1   Operational 890 937 1 September 1975 27 May 1981
Dampierre 4 PWR CP1   Operational 890 937 1 December 1975 20 November 1981
Fessenheim 1 PWR CP0   Operational 880 920 1 September 1971 1 January 1978
Fessenheim 2 PWR CP0   Operational 880 920 1 February 1972 1 April 1978
Flamanville 1 PWR P4 REP 1300   Operational 1330 1382 1 December 1979 1 December 1986
Flamanville 2 PWR P4 REP 1300   Operational 1330 1382 1 May 1980 9 March 1987
Flamanville 3 PWR EPR   Under construction 1600 1650 3 December 2007
Golfech 1 PWR P4 REP 1300   Operational 1310 1363 17 November 1982 1 February 1991
Golfech 2 PWR P4 REP 1300   Operational 1310 1363 1 October 1984 4 March 1994
Gravelines 1 PWR CP1   Operational 910 951 1 February 1975 25 November 1980
Gravelines 2 PWR CP1   Operational 910 951 1 March 1975 1 December 1980
Gravelines 3 PWR CP1   Operational 910 951 1 December 1975 1 June 1981
Gravelines 4 PWR CP1   Operational 910 951 1 April 1976 1 October 1981
Gravelines 5 PWR CP1   Operational 910 951 1 October 1979 15 January 1985
Gravelines 6 PWR CP1   Operational 910 951 1 October 1979 25 October 1985
Marcoule G1 GCR UNGG   Shut down 2 1955 7 January 1956 15 October 1968
Marcoule G2 GCR UNGG   Shut down 39 43 1 March 1955 22 April 1959 2 February 1980
Marcoule G3 GCR UNGG   Shut down 40 43 1 March 1956 4 April 1960 20 June 1984
Marcoule Phénix FBR PH-250   Shut down 130 142 1 November 1968 14 July 1974 1 February 2010
Nogent 1 PWR P4 REP 1300   Operational 1310 1363 26 May 1981 24 February 1988
Nogent 2 PWR P4 REP 1300   Operational 1310 1363 1 January 1982 1 May 1989
Paluel 1 PWR P4 REP 1300   Operational 1330 1382 15 August 1977 1 December 1985
Paluel 2 PWR P4 REP 1300   Operational 1330 1382 1 January 1978 1 December 1985
Paluel 3 PWR P4 REP 1300   Operational 1330 1382 1 February 1979 1 February 1986
Paluel 4 PWR P4 REP 1300   Operational 1330 1382 1 February 1980 1 June 1986
Penly 1 PWR P4 REP 1300   Operational 1330 1382 1 September 1982 1 December 1990
Penly 2 PWR P4 REP 1300   Operational 1330 1382 1 August 1984 1 November 1992
Penly 3 PWR EPR   Planned 1600 1650
Saint-Alban 1 PWR P4 REP 1300   Operational 1335 1381 29 January 1979 1 May 1986
Saint-Alban 2 PWR P4 REP 1300   Operational 1335 1381 31 July 1979 1 March 1987
Saint-Laurent A 1 GCR UNGG   Shut down 390 500 1 October 1963 1 June 1969 18 April 1990
Saint-Laurent A 2 GCR UNGG   Shut down 465 530 1 January 1966 1 November 1971 27 May 1992
Saint-Laurent B 1 PWR CP1   Operational 915 956 1 May 1976 1 August 1983
Saint-Laurent B 2 PWR CP1   Operational 915 956 1 July 1976 1 August 1983
Superphénix 1 FBR Na-1200   Shut down 1200 1242 13 December 1976 1 December 1986 31 December 1998
Tricastin 1 PWR CP1   Operational 915 955 1 November 1974 1 December 1980
Tricastin 2 PWR CP1   Operational 915 955 1 December 1974 1 December 1980
Tricastin 3 PWR CP1   Operational 915 955 1 April 1975 11 May 1981
Tricastin 4 PWR CP1   Operational 915 955 1 May 1975 1 November 1981

CancelledEdit

Research reactorsEdit

Shut down :

  • Zoé, the first French nuclear reactor (1948)
  • Eau lourde n°2 (EL2)
  • Aquilon
  • Eau lourde n°3 (EL3)
  • Rubéole
  • Mélusine
  • Proserpine
  • PEG
  • Alizé
  • Minerve
  • Triton
  • Néréide
  • Marius
  • Ulysse
  • Peggy
  • Rachel
  • Siloé
  • Pégase
  • Siloette
  • Prototype à terre (PAT)
  • Cesar
  • Marius
  • Harmonie
  • Osiris
  • Réacteur universitaire de Strasbourg (RUS)
  • Rhapsodie
  • Eau lourde n°4 (EL4)
  • Celestin I
  • Celestin II
  • Prospero
  • Caliban
  • Phénix
  • Silène
  • Chaufferie avancée prototype (Cap)
  • Phébus
  • Réacteur nouvelle génération (RNG)

Working :

GermanyEdit

Power station reactorsEdit

Nuclear power plants in Germany (view)
  Active plants
  Closed plants
  Unfinished plants
Name Reactor Status Capacity in MW Construction
Start Date
Commercial
Operation Date
Closure
Type Model Net Gross
AVR 1 HTGR Pebble bed reactor prototype   Shut down 13 15 1 August 1961 19 May 1969 31 December 1988
Biblis 1a PWR PWR   Shut down 1167 1225 1 January 1970 26 February 1975 6 August 2011
Biblis 2a PWR PWR   Shut down 1240 1300 1 February 1972 31 January 1977 6 August 2011
Brokdorf 1 PWR PWR   Operational 1410 1480 1 January 1976 22 December 1986 31 Dec 2021
Brunsbüttel 1a BWR BWR-69   Shut down 771 806 15 April 1970 9 February 1977 6 August 2011
Emsland 1 PWR Konvoi   Operational 1329 1400 10 August 1982 20 June 1988 31 Dec 2022
Grafenrheinfeld 1 PWR PWR   Shut down 1275 1375 1 January 1975 17 June 1982 27 June 2015
Greifswald 1 PWR VVER V-230   Shut down 408 440 1 March 1970 12 July 1974 14 February 1990
Greifswald 2 PWR VVER V-230   Shut down 408 440 1 March 1970 16 April 1975 14 February 1990
Greifswald 3 PWR VVER V-230   Shut down 408 440 1 April 1972 1 May 1978 28 February 1990
Greifswald 4 PWR VVER V-230   Shut down 408 440 1 April 1972 1 November 1979 22 July 1990
Greifswald 5 PWR VVER V-213   Shut down 408 440 1 December 1976 1 November 1989 24 November 1989
Greifswald 6 PWR VVER V-213   Finished;
never started
408 440
Grohnde 1 PWR PWR   Operational 1360 1430 1 June 1976 1 February 1985 31 Dec 2021
Großwelzheim 1 BWR Superheated steam reactor   Shut down 25 27 1 January 1965 2 August 1970 20 April 1971
Gundremmingen 1 BWR   Shut down 237 250 12 December 1962 12 April 1967 13 January 1977
Gundremmingen 2 BWR BWR-72   Operational 1284 1225 20 July 1976 19 July 1984 31 Dec 2017
Gundremmingen 3 BWR BWR-72   Operational 1288 1344 20 July 1976 18 January 1985 31 Dec 2021
Isar 1a BWR BWR-69   Shut down 878 912 1 May 1972 21 March 1979 6 August 2011
Isar 2 PWR Konvoi   Operational 1410 1485 15 September 1982 9 April 1988 31 Dec 2022
Kahl 1 BWR BWR   Shut down 15 16 1 July 1958 1 February 1962 25 November 1985
SNR-300 1 FBR   Finished;
never started
327 1972 1985
KNK II 1 FBR   Shut down 17 21 1 September 1974 3 March 1979 23 August 1991
Krümmel 1a BWR BWR-69   Shut down 1346 1402 5 April 1974 28 March 1984 6 August 2011
Lingen 1 BWR BWR with fossil fuel-fired superheater   Shut down 183 268 1 October 1964 1 October 1968 5 January 1977
Mülheim-Kärlich 1 PWR PWR   Shut down 1219 1302 15 January 1975 8 August 1987 9 September 1988
MZFR 1 PHWR Heavy water-cooled pressure vessel reactor   Shut down 52 57 1 December 1961 19 December 1966 3 May 1984
Neckarwestheim 1a PWR PWR   Shut down 785 840 1 February 1972 1 December 1976 6 August 2011
Neckarwestheim 2 PWR PWR   Operational 1310 1400 9 November 1982 15 April 1989 31 Dec 2022
Niederaichbach 1 HWGCR Pressure tube reactor   Shut down 100 106 1 June 1966 1 January 1973 31 July 1974
Obrigheim 1 PWR   Shut down 340 357 15 March 1965 31 March 1969 11 May 2005
Philippsburg 1a BWR BWR-69   Shut down 890 926 1 October 1970 26 March 1980 6 August 2011
Philippsburg 2 PWR PWR   Operational 1402 1468 7 July 1977 18 April 1985 31 Dec 2019
Rheinsberg 1 PWR VVER-70   Shut down 62 70 1 January 1960 11 October 1966 1 June 1990
Stade 1 PWR VVER-1000/320   Shut down 640 672 1 December 1967 19 May 1972 4 November 2003
Stendal 1 PWR VVER-1000/320   Unfinished 1000 1983 1990
Stendal 2 PWR VVER-1000/320   Unfinished 1000 1983 1990
Stendal 3 PWR VVER-1000/320   Never built 1000
Stendal 4 PWR VVER-1000/320   Never built 1000
THTR-300 1 HTGR Pebble bed reactor   Shut down 296 308 3 May 1971 1 June 1987 29 September 1988
Unterweser 1a PWR PWR   Shut down 1345 1410 1 July 1972 6 September 1979 6 August 2011
Würgassen 1 BWR   Shut down 640 670 26 January 1968 11 November 1975 26 August 1994
Notes:
^a Post-Fukushima shutdown of eight reactors. On 15 March 2011, the German Government decided to close seven nuclear power plants built before 1980 along with the Krümmel nuclear power plant for a duration of three months.[23] The temporary shutdown was changed into permanent shutdown by the German parliament on 30 June 2012. The remaining nine plants that stayed operational were given new decommissioning dates.[24]

Research reactorsEdit

  • AKR II – Ausbildungskernreaktor II, Technische Universität Dresden; rating: 2 W, commissioned 2005
  • BER II – Berliner-Experimentier-Reaktor II, Helmholtz-Zentrum Berlin für Materialien und Energie; rating: 10 MW, commissioned 1990
  • FRG-1 (see GKSS Research Center) – Geesthacht; rating: 5 MW, commissioned 1958
  • FRM IITechnische Universität München; rating: 20 MW, commissioned 2004
  • FRMZ – TRIGA of the University of Mainz, institute of nuclear chemistry; continuous rating: 0.10 MW, pulse rating for 30ms: 250 MW; commissioned 1965
  • FR2 - Forschungsreaktor 2; rating: 44 MW; commissioned 1957; closed: 1981

PlannedEdit

  • Wyhl, planned nuclear plant that was never built because of long-time resistance by the local population and environmentalists.

GreeceEdit

Research reactorsEdit

  • GRR-1 – 5 MW research reactor at Demokritos National Centre for Scientific Research, Athens.bn

HungaryEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Paks 1 PWR VVER V-213   Operational 470 500 1 August 1974 10 August 1983
Paks 2 PWR VVER V-213   Operational 473 500 1 August 1974 14 November 1984
Paks 3 PWR VVER V-213   Operational 473 500 1 October 1979 1 December 1986
Paks 4 PWR VVER V-213   Operational 471 500 1 October 1979 1 November 1987
Paks 5 PWR VVER-1200   Planned 1114 1200 2023
Paks 6 PWR VVER-1200   Planned 1114 1200 2025

The modernization of the four reactors was finally ended at 2009, so the plant's total power generation reached 2000 MWe.

Research reactorsEdit

IndiaEdit

Atomic Power Stations in India (view)
  Active plants
  Planned plants

Power station reactorsEdit

For more information: Electricity in India[25]

Breakdown by Reactor
Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Kaiga 1 PHWR Horizontal Pressure Tube   Operational 202 220 1 September 1989 16 November 2000
Kaiga 2 PHWR Horizontal Pressure Tube   Operational 202 220 1 December 1989 16 March 2000
Kaiga 3 PHWR Horizontal Pressure Tube   Operational 202 220 30 March 2002 6 May 2007
Kaiga 4 PHWR Horizontal Pressure Tube   Operational 202 220 10 May 2002 20 January 2011
Kakrapar 1 PHWR Horizontal Pressure Tube   Operational 202 220 1 December 1984 6 May 1993
Kakrapar 2 PHWR Horizontal Pressure Tube   Operational 202 220 1 April 1985 1 September 1995
Kakrapar 3 PWR PHWR-700   Under construction 630 700 22 November 2010
Kakrapar 4 PWR PHWR-700   Under construction 630 700 22 November 2010
Kudankulam 1 PWR VVER V-412   Operational 917 1000 31 March 2002 30 June 2014
Kudankulam 2 PWR VVER V-412   Operational 917 1000 4 July 2002 29 August 2016
Kudankulam 3 PWR VVER V-412   Under construction 917 1000 30 June 2017
Kudankulam 4 PWR VVER V-412   Under construction 917 1000 30 June 2017
Madras 1 PHWR Horizontal Pressure Tube   Operational 205 220 1 January 1971 27 January 1984
Madras 2 PHWR Horizontal Pressure Tube   Operational 205 220 1 October 1972 21 March 1986
Narora 1 PHWR Horizontal Pressure Tube   Operational 202 220 1 December 1976 1 January 1991
Narora 2 PHWR Horizontal Pressure Tube   Operational 202 220 1 November 1977 1 July 1992
PFBR 1 FBR Prototype   Under construction 470 500 23 October 2004
Rajasthan 1 PHWR CANDU/Horiz. Pressure Tube   Shut Down 90 100 1 August 1965 16 December 1973 Oct 2014
Rajasthan 2 PHWR Horizontal Pressure Tube   Operational 187 200 1 April 1968 1 April 1981
Rajasthan 3 PHWR Horizontal Pressure Tube   Operational 202 220 1 February 1990 1 June 2000
Rajasthan 4 PHWR Horizontal Pressure Tube   Operational 202 220 1 October 1990 23 December 2000
Rajasthan 5 PHWR Horizontal Pressure Tube   Operational 202 220 18 September 2002 4 February 2010
Rajasthan 6 PHWR Horizontal Pressure Tube   Operational 202 220 20 January 2003 31 March 2010
Rajasthan 7 PHWR Horizontal Pressure Tube   Under construction 630 700 18 July 2011
Rajasthan 8 PHWR Horizontal Pressure Tube   Under construction 630 700 30 September 2011
Tarapur 1 BWR BWR-1, Mark 2   Operational 150 160 1 October 1964 28 October 1969
Tarapur 2 BWR BWR-1, Mark 2   Operational 150 160 1 October 1964 28 October 1969
Tarapur 3 PHWR Horizontal Pressure Tube   Operational 490 540 12 May 2000 18 August 2006
Tarapur 4 PHWR Horizontal Pressure Tube   Operational 490 540 8 March 2000 12 September 2005

Research and production reactorsEdit

  • Bhabha Atomic Research Center (BARC) – Trombay
    • Apsara reactor – Asia's first nuclear reactor. 1 MWT, pool type, light water moderated, enriched uranium fuel supplied by France
    • CIRUS reactor – 40 MWT, supplied by Canada, heavy water moderated, uses natural uranium fuel
    • Dhruva reactor – 100 MWT, heavy water moderated, uses natural uranium fuel
    • Purnima series
  • Indira Gandhi Center for Atomic Research (IGCAR) – Kalpakkam

IndonesiaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction start date Commercial operation date Closure
Type Model Net Gross
Muria 1 PWR VVER-1200   Planned 1150 1200 2022
Muria 2 PWR VVER-1200   Planned 1150 1200 2022
Muria 3 PWR VVER-1200   Planned 1150 1200 2022
Muria 4 PWR VVER-1200   Planned 1150 1200 2022
Bangka Belitung 1 PWR VVER-1200   Planned 1150 1000 2030
Bangka Belitung 2 PWR VVER-1200   Planned 1150 1000 2030

Research reactorsEdit

IranEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Bushehr 1 PWR VVER V-446   Operational 915 1000 1 May 1975 23 September 2013
Bushehr 2 PWR VVER V-446   Unfinished; restart planned 915 1000 March 2016
Bushehr 3 PWR VVER V-446   Planned 915 1000
Bushehr 4 PWR VVER V-446   Cancelled 915 1000
Darkhovin 1 PWR   Under construction 280 300 2008

Research reactorsEdit

  • Tehran – AMF reactor at Tehran Nuclear Research Center (supplied by USA, 1967)
  • Isfahan, Nuclear Technology Center (mainly supplied by China,[26])
    • MNSR – 27 kWt Miniature Neutron Source Reactor
    • Light Water Subcritical Reactor (LWSCR)
    • Heavy Water Zero Power Reactor (HWZPR)
    • Graphite Subcritical Reactor (GSCR)
  • ArakIR-40 Heavy water-moderated Reactor (under construction, planned commissioning 2014)

IraqEdit

Research reactorsEdit

IsraelEdit

Research and production reactorsEdit

ItalyEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Caorso 1 BWR BWR-4 Mark2   Shut down 860 882 1 January 1970 1 December 1981 1 July 1990
Enrico Fermi 1 PWR WE 4-loops   Shut down 260 270 1 July 1961 1 January 1965 1 July 1990
Garigliano 1 BWR BWR-1   Shut down 150 160 1 November 1959 1 June 1964 1 March 1982
Latina 1 GCR MAGNOX   Shut down 153 160 1 November 1958 1 January 1964 1 December 1987
Alto Lazio 1 BWR   Unfinished, never started 982 1009 1 July 1982 1 January 1988
Alto Lazio 2 BWR   Unfinished, never started 982 1009 1 July 1982 1 July 1988

Research reactorsEdit

JamaicaEdit

JapanEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Fukushima Daiichi 1 BWR BWR-3   Inoperable 439 460 25 July 1967 26 March 1971 19 May 2011
Fukushima Daiichi 2 BWR BWR-4   Inoperable 760 784 9 June 1969 18 July 1974 19 May 2011
Fukushima Daiichi 3 BWR BWR-4   Inoperable 760 784 28 December 1970 27 March 1976 19 May 2011
Fukushima Daiichi 4 BWR BWR-4   Shut down/ Inoperable 760 784 12 February 1973 12 October 1978 19 May 2011
Fukushima Daiichi 5 BWR BWR-4   Shut down 760 784 22 May 1972 18 April 1978 17 December 2013
Fukushima Daiichi 6 BWR BWR-5   Shut down 1067 1100 26 October 1973 24 October 1979 17 December 2013
Fukushima Daini 1 BWR BWR-5   Operation suspended 1067 1100 16 March 1976 20 April 1982
Fukushima Daini 2 BWR BWR-5   Operation suspended 1067 1100 25 May 1979 3 February 1984
Fukushima Daini 3 BWR BWR-5   Operation suspended 1067 1100 23 March 1981 21 June 1985
Fukushima Daini 4 BWR BWR-5   Operation suspended 1067 1100 28 May 1981 25 August 1987
Genkai 1 PWR M (2-loop)   Shut down 529 559 15 September 1971 15 October 1975 March 2015
Genkai 2 PWR M (2-loop)   Operation suspended 529 559 1 February 1977 30 March 1981
Genkai 3 PWR M (4-loop)   Operation suspended 1127 1180 1 June 1988 18 March 1994
Genkai 4 PWR M (4-loop)   Operation suspended 1127 1180 15 July 1992 25 July 1997
Hamaoka 1 BWR BWR-4   Shut down 515 540 10 June 1971 17 March 1976 30 January 2009
Hamaoka 2 BWR BWR-4   Shut down 806 840 14 June 1974 29 November 1978 30 January 2009
Hamaoka 3 BWR BWR-5   Operation suspended 1056 1100 18 April 1983 28 August 1987
Hamaoka 4 BWR BWR-5   Operation suspended 1092 1137 13 October 1989 3 September 1993
Hamaoka 5 BWR ABWR   Operation suspended 1325 1380 12 July 2000 18 January 2005
Higashidōri 1 BWR BWR-5   Operation suspended 1067 1100 7 November 2000 8 December 2005
Higashidōri 2   Planned
Higashidōri 3   Planned
Higashidōri 4   Planned
Ikata 1 PWR M (2-loop)   Operation suspended 538 566 1 September 1973 30 September 1977
Ikata 2 PWR M (2-loop)   Operation suspended 538 566 1 August 1978 19 March 1982
Ikata 3 PWR M (3-loop)   Operational 846 890 1 October 1990 15 December 1994
Kashiwazaki-Kariwa 1 BWR BWR-5   Operation suspended 1067 1100 5 June 1980 18 September 1985
Kashiwazaki-Kariwa 2 BWR BWR-5   Operation suspended 1067 1100 18 November 1985 28 September 1990
Kashiwazaki-Kariwa 3 BWR BWR-5   Operation suspended 1067 1100 7 March 1989 11 August 1993
Kashiwazaki-Kariwa 4 BWR BWR-5   Operation suspended 1067 1100 5 March 1990 11 August 1994
Kashiwazaki-Kariwa 5 BWR BWR-5   Operation suspended 1067 1100 20 June 1985 10 April 1990
Kashiwazaki-Kariwa 6 BWR ABWR   Operation suspended 1315 1356 3 November 1992 7 November 1996
Kashiwazaki-Kariwa 7 BWR ABWR   Operation suspended 1315 1356 1 July 1993 2 July 1997
Mihama 1 PWR M (2-loop)   Shut down 320 340 1 February 1967 28 November 1970 March 2015
Mihama 2 PWR M (2-loop)   Shut down 470 500 29 May 1968 25 July 1972 March 2015
Mihama 3 PWR M (3-loop)   Operation suspended 780 826 7 August 1972 1 December 1976
Monju 1 FBR -   Shut down 246 280 10 May 1986 29 August 1995 8 December 1995
Ōi 1 PWR W (4-loop)   Operation suspended 1120 1175 26 October 1972 27 March 1979
Ōi 2 PWR W (4-loop)   Operation suspended 1120 1175 8 December 1972 5 December 1979
Ōi 3 PWR M (4-loop)   Operation suspended 1127 1180 3 October 1987 18 December 1991
Ōi 4 PWR M (4-loop)   Operation suspended 1127 1180 13 June 1988 2 February 1993
Ōma 1 BWR ABWR   Under construction 1325 1383 7 May 2010
Onagawa 1 BWR BWR-4   Operation suspended 498 524 8 July 1980 1 June 1984
Onagawa 2 BWR BWR-5   Operation suspended 796 825 12 April 1991 28 July 1995
Onagawa 3 BWR BWR-5   Operation suspended 796 825 23 January 1998 30 January 2002
Sendai 1 PWR M (3-loop)   Operational 846 890 15 December 1979 4 July 1984
Sendai 2 PWR M (3-loop)   Operational 846 890 12 October 1981 28 November 1985
Shika 1 BWR BWR-5   Operation suspended 505 530 1 July 1989 30 July 1993
Shika 2 BWR ABWR   Operation suspended 1108 1150 20 August 2001 15 March 2006
Shimane 1 BWR BWR-3   Shut down 439 460 2 July 1970 29 March 1974 March 2015
Shimane 2 BWR BWR-5   Operation suspended 789 820 2 February 1985 10 February 1989
Shimane 3 BWR ABWR   Under construction 1325 1373 12 October 2007
Takahama 1 PWR M (3-loop)   Operation suspended 780 826 25 April 1970 14 November 1974
Takahama 2 PWR M (3-loop)   Operation suspended 780 826 9 March 1971 14 November 1975
Takahama 3 PWR M (3-loop)   Operational 830 870 12 December 1980 17 January 1985
Takahama 4 PWR M (3-loop)   Operational 830 870 19 March 1981 5 June 1985
Tōkai 1 GCR MAGNOX   Shut down 137 166 1 March 1961 25 July 1966 31 March 1998
Tōkai 2 BWR BWR-5   Operation suspended 1060 1100 3 October 1973 28 November 1978
Tomari 1 PWR M (2-loop)   Operation suspended 550 579 18 April 1985 22 June 1989
Tomari 2 PWR M (2-loop)   Operation suspended 550 579 13 June 1985 12 April 1991
Tomari 3 PWR M (3-loop)   Operation suspended 866 912 18 November 2004 22 December 2009
Tsuruga 1 BWR BWR-2   Shut down 340 357 24 November 1966 14 March 1970 March 2015
Tsuruga 2 PWR M (4-loop)   Operation suspended 1108 1160 6 November 1982 17 February 1987

Research reactorsEdit

JordanEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Jordan Reactor 1 PWR VVER-1000   Planned 950 1000
Jordan Reactor 2 PWR VVER-1000   Planned 950 1000

Research reactorEdit

KazakhstanEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
BN-350 1   Shut down 135 1964 1973 1999

Research reactorsEdit

  • Alatau, Institute of Nuclear Physics of the National Nuclear Center
    • VVR-K – 10 MWe reactor
  • Kurchatov, National Nuclear Center, Semipalatinsk Test Site
    • IVG-1M – 60 MW reactor
    • RA – zirconium hydride moderated reactor (dismantled)
    • IGR (Impulse Graphite Reactor) – 50 MW reactor

LatviaEdit

Research reactorsEdit

  • Salaspils, Nuclear Research Center
    • 5 MWe research reactor (shut down)

LibyaEdit

Research reactorsEdit

  • Tajura Nuclear Research Center, REWDRC (see [2]) – 10 MW research reactor (supplied by the USSR)

LithuaniaEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Ignalina 1 LWGR RBMK-1500   Shut down 1185 1300 1 May 1977 1 May 1985 31 December 2004
Ignalina 2 LWGR RBMK-1500   Shut down 1185 1300 1 January 1978 1 December 1987 31 December 2009
Ignalina 3 LWGR RBMK-1500   Unfinished 1185 1300
Ignalina 4 LWGR RBMK-1500   Never built 1185 1300
Visaginas 1   Planned

MalaysiaEdit

Research reactorsEdit

MexicoEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Laguna Verde 1 BWR BWR-5   Operational 665 700 1 October 1976 29 July 1990
Laguna Verde 2 BWR BWR-5   Operational 665 700 1 June 1977 10 April 1995

Research reactorsEdit

MoroccoEdit

Research reactorsEdit

NetherlandsEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Borssele 1 PWR LWR - PWR   Operational 482 515 1 July 1969 26 October 1973 26 Oct 2033
Dodewaard 2 BWR BWR-5   Shut down 55 60 1 May 1965 26 March 1969 26 March 1997

Research reactorsEdit

North KoreaEdit

Power station reactorsEdit

  • Yongbyon
    • Yongbyon 2 - 50 MWe Magnox reactor (construction suspended 1994)
    • Yongbyon 2 - 30 MWe light water reactor (completion scheduled for 2013)
  • Taechon (20 km from Yongbyon)
    • Taechon 1 - 200 MWe reactor (construction suspended 1994)
  • Kumho (30 km north of Sinpo), see KEDO
    • Kumho 1 - PWR 1000 MWe (construction suspended 2003)
    • Kumho 2 - PWR 1000 MWe (construction suspended 2003)

Research and production reactorsEdit

  • Yongbyon
    • IRT-2000 - 8 MWt (2MWt 1965-1974, 4MWt 1974-1986) heavy-water moderated research reactor (supplied by USSR, 1965)
    • Yongbyon 1 - 5 MWe Magnox reactor, provides power and district heating (active 1987-1994, reactivated 2003, and shut-down in July 2007)

NorwayEdit

Research reactorsEdit

  • Kjeller reactors
    • NORA (activated 1961, shut down 1967)
    • JEEP I (activated 1951, shut down 1967)
    • JEEP II (activated 1966, scheduled to temporarily shut down in December 2016, without saying what year it will reopen)[30]
  • Halden Reactor
    • HBWR - Halden boiling water reactor (activated 1959)

PakistanEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Chashma 1 PWR CNP-300   Operational 300 325 1 August 1993 15 September 2000
Chashma 2 PWR CNP-300   Operational 300 325 28 December 2005 18 May 2011
Chashma 3 PWR CNP-300   Operational 315 340 28 May 2011 15 October 2016
Chashma 4 PWR CNP-300   Operational 315 340 18 December 2011 1 July 2017
Chashma 5 PWR CNP-300   Planned 300
Karachi 1 PHWR CANDU-137 MW   Operational 90 100 1 August 1966 7 December 1972
Karachi 2 PWR Hualong-1   Under construction 1080 1150 23 May 2013 2021
Karachi 3 PWR Hualong-1   Under construction 1080 1150 21 August 2015 2022
Karachi 4 PWR Hualong-1   Planned 1080 1150

Research and production reactorsEdit

Under IAEA safeguards

Reactor Type MWT Location Status
PARR I Pool-type reactor 10 Islamabad Operational since 1965
PARR II Pool-type reactor 30 kWT Islamabad Operational since 1974

Not under IAEA safeguards

Reactor Type MWT Location Status
Khushab-I HWR Classified. Estimated: 50-70 Khushab Operational since 1998
Khushab-II HWR Classified Khushab Operational since 2010
Khushab-III HWR Classified Khushab Under construction
Khushab-IV HWR Classified Khushab Under construction[31]

PanamaEdit

Research reactorsEdit

PeruEdit

Research reactorsEdit

PhilippinesEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Bataan 1 PWR Westinghouse   Finished; never started 621 1976 N/A (Never went operational) 1986

Research reactorsEdit

  • PRR-1 - 3 MW TRIGA-converted reactor, Quezon City. Managed by the Philippine Nuclear Research Institute (formerly Philippine Atomic Energy Commission). 1st criticality in August 1963, reactor conversion in March 1984, criticality after conversion in April 1988, shut down since 1988 for pool repairs, on extended shutdown at present.

PolandEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Żarnowiec 1 PWR VVER-440   Unfinished 440 31 March 1982 4 September 1990
Żarnowiec 2 PWR VVER-440   Unfinished 440 31 March 1982 4 September 1990
Żarnowiec 3 PWR VVER-440   Never built 440 4 September 1990
Żarnowiec 4 PWR VVER-440   Never built 440 4 September 1990

Research reactorsEdit

  • Ewa reactor - 10 MW VVR-SM research reactor (dismantled in 1995)
  • Maria reactor - 30 MW research reactor
  • Anna reactor - 10 kW research reactor (dismantled)
  • Agata reactor - 10 W zero-power research reactor (dismantled)
  • Maryla reactor - 100 W zero-power research reactor (dismantled)
  • UR-100 reactor - 100 kW training reactor (dismantled)

PortugalEdit

Research reactorsEdit

  • Sacavem - RPI, Portuguese Research Reactor - 1 MWt pool type, Instituto Tecnológico e Nuclear

Puerto RicoEdit

Research reactorsEdit

RomaniaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Cernavodă 1 PHWR CANDU-6   Operational 650 706 1 July 1982 2 December 1996
Cernavodă 2 PHWR CANDU-6   Operational 650 705 1 July 1983 31 October 2007
Cernavodă 3 PHWR CANDU-6   Unfinished 650 705
Cernavodă 4 PHWR CANDU-6   Unfinished 650 705
Cernavodă 5 PHWR CANDU-6   Unfinished 650 705

Fuel FactoryEdit

    • Mioveni Fuel Factory, CANDU fuel
    • Turnu Severin-Halînga Heavy Water Factory

ResearchEdit

RussiaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Balakovo 1 PWR VVER V-320   Operational 950 1000 1 December 1980 23 May 1986
Balakovo 2 PWR VVER V-320   Operational 950 1000 1 August 1981 18 January 1988
Balakovo 3 PWR VVER V-320   Operational 950 1000 1 November 1982 8 April 1989
Balakovo 4 PWR VVER V-320   Operational 950 1000 1 April 1984 22 December 1993
Balakovo 5 PWR VVER V-320   Unfinished 950 1000 28 December 1992
Balakovo 6 PWR VVER V-320   Unfinished 950 1000 28 December 1992
Beloyarsk 1 LWGR AMB-100   Shut down 102 108 1 June 1958 26 April 1964 1 January 1983
Beloyarsk 2 LWGR AMB-200   Shut down 146 160 1 January 1962 1 December 1969 1 January 1990
Beloyarsk 3 FBR BN-600   Operational 560 600 1 January 1969 1 November 1981
Beloyarsk 4 FBR BN-800   Operational 789 864 18 July 2006 10 December 2015
Bilibino 1 LWGR EGP-6   Operational 11 12 1 January 1970 1 April 1974
Bilibino 2 LWGR EGP-6   Operational 11 12 1 January 1970 1 February 1975
Bilibino 3 LWGR EGP-6   Operational 11 12 1 January 1970 1 February 1976
Bilibino 4 LWGR EGP-6   Operational 11 12 1 January 1970 1 January 1977
Kalinin 1 PWR VVER V-338   Operational 950 1000 1 February 1977 12 June 1985
Kalinin 2 PWR VVER V-338   Operational 950 1000 1 February 1982 3 March 1987
Kalinin 3 PWR VVER V-320   Operational 950 1000 1 October 1985 8 November 2005
Kalinin 4 PWR VVER V-320   Operational 950 1000 1 August 1986 25 December 2012
Kaliningrad 1 PWR VVER V-491   Under construction 1109 1194 22 February 2012 2017
Kaliningrad 2 PWR VVER V-491   Under construction 1109 1194 22 February 2012 2018
Kola 1 PWR VVER V-230   Operational 441 440 1 May 1970 28 December 1973
Kola 2 PWR VVER V-230   Operational 441 440 1 May 1970 21 February 1975
Kola 3 PWR VVER V-213   Operational 441 440 1 April 1977 3 December 1982
Kola 4 PWR VVER V-213   Operational 441 440 1 August 1976 6 December 1984
Kursk 1 LWGR RBMK-1000   Operational 925 1000 1 June 1972 12 October 1977
Kursk 2 LWGR RBMK-1000   Operational 925 1000 1 January 1973 17 August 1979
Kursk 3 LWGR RBMK-1000   Operational 925 1000 1 April 1978 30 March 1984
Kursk 4 LWGR RBMK-1000   Operational 925 1000 1 May 1981 5 February 1986
Kursk 5 LWGR RBMK-1000   Unfinished 925 1000 1 December 1985
Kursk 6 LWGR RBMK-1000   Unfinished 925 1000 1 August 1986
Kursk II 1 PWR AES 2006   Under Construction 1300 1350 2016
Leningrad 1 LWGR RBMK-1000   Operational 925 1000 1 March 1970 1 November 1974
Leningrad 2 LWGR RBMK-1000   Operational 925 1000 1 June 1970 11 February 1976
Leningrad 3 LWGR RBMK-1000   Operational 925 1000 1 December 1973 29 June 1980
Leningrad 4 LWGR RBMK-1000   Operational 925 1000 1 February 1975 29 August 1981
Leningrad II 1 PWR VVER V-491   Under construction 1085 1170 25 October 2008 2018
Leningrad II 2 PWR VVER V-491   Under construction 1085 1170 15 April 2010 2019
Leningrad II 3 PWR VVER V-491   Planned 1085 1170
Leningrad II 4 PWR VVER V-491   Planned 1085 1170
Novovoronezh 1 PWR VVER V-120   Shut down 197 210 1 July 1957 31 December 1964 16 February 1988
Novovoronezh 2 PWR VVER V-120   Shut down 336 365 1 June 1964 14 April 1970 29 August 1990
Novovoronezh 3 PWR VVER V-179   Shut down 385 417 1 July 1967 29 June 1972 25 December 2016
Novovoronezh 4 PWR VVER V-179   Operational 385 417 1 July 1967 24 March 1973
Novovoronezh 5 PWR VVER V-187   Operational 950 1000 1 March 1974 20 February 1981
Novovoronezh II 1 VVER VVER-1200   Operational 1114 1199 24 June 2008 4 August 2016
Novovoronezh II 2 PWR VVER V-392M   Under construction 1114 1199 12 July 2009 2019
Novovoronezh II 3 PWR VVER V-510   Planned 1175 1255
Novovoronezh II 4 PWR VVER V-510   Planned 1175 1255
Obninsk 1 LWGR AM-1   Shut down 5 6 1 January 1951 1 December 1954 29 April 2002
Rostov 1 PWR VVER V-320I   Operational 950 1000 1 September 1981 25 December 2001
Rostov 2 PWR VVER V-320I   Operational 950 1000 1 May 1983 10 December 2010
Rostov 3 PWR VVER V-320   Operational 1011 1100 15 September 2009 27 December 2014
Rostov 4 PWR VVER V-320   Under construction 1011 1100 16 June 2010
Smolensk 1 LWGR RBMK-1000   Operational 925 1000 1 October 1975 30 September 1983
Smolensk 2 LWGR RBMK-1000   Operational 925 1000 1 June 1976 2 July 1985
Smolensk 3 LWGR RBMK-1000   Operational 925 1000 1 May 1984 12 October 1990
Smolensk 4 LWGR RBMK-1000   Unfinished 925 1000

Research reactorsEdit

A total of 98 nuclear research facilities, including:[32]

Saudi ArabiaEdit

Saudi Arabia has proposals to build nuclear power plants in anticipation of growth in domestic energy consumption.[33]

SerbiaEdit

Research reactorsEdit

  • Vinca Nuclear Institute, Vinča
    • RA - Reaktor A (1956–2002) - 6.5 MW heavy water moderated and cooled research reactor
    • RB - Reaktor B (1958-...) - At the very beginning the RB reactor was designed and constructed as an unreflected zero power heavy water - natural uranium critical assembly. First criticality was reached in April 1958. Later, the 2% enriched metal uranium fuel and 80% enriched UO2 fuel were obtained and used in the reactor core. Modifications of the reactor control, safety and dosimetry systems (1960, 1976, 1988) converted the RB critical assembly to a flexible heavy water reflected experimental reactor with 1 W nominal power, operable up to 50 W. Several coupled fast-thermal systems were designed and constructed at RB reactor in the early 1990s, for the research in fast reactors physics.

(For more information on the subject, please visit[34])

SlovakiaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Bohunice [35] A-1 HWGCR KS 150   Shut down 93 143 1 August 1958 25 December 1972 22 February 1977
Bohunice V1 [36] 1 PWR VVER V-230   Shut down 408 440 24 April 1972 1 April 1980 31 December 2006
Bohunice V1 2 PWR VVER V-230   Shut down 408 440 24 April 1972 1 January 1981 31 December 2008
Bohunice V2 3 PWR VVER V-213   Operational 472 505 1 December 1976 14 February 1985
Bohunice V2 4 PWR VVER V-213   Operational 471 505 1 December 1976 18 December 1985
Mochovce 1 PWR VVER V-213   Operational 436 470 13 October 1983 29 October 1998
Mochovce 2 PWR VVER V-213   Operational 436 470 13 October 1983 11 April 2000
Mochovce 3 PWR VVER V-213   Under construction 440 471 27 January 1987 (restarted in 2009)
Mochovce 4 PWR VVER V-213   Under construction 440 471 27 January 1987 (restarted in 2009)

SloveniaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Krško 1 PWR Westinghouse 212   Operational 688 727 30 March 1975 1 January 1983

Research reactorsEdit

South AfricaEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Koeberg 1 PWR CP-1   Operational 930 970 1 July 1976 21 July 1984
Koeberg 2 PWR CP-1   Operational 930 970 1 July 1976 9 November 1985

Research reactorsEdit

South KoreaEdit

 
 
 
 
 
Yeongdeok
Nuclear plants in South Korea (view)
  •   Active plants
  •   Plants under construction
  •   Planned plants

Power station reactorsEdit

Breakdown by site
Plant Town Province Primary Technology Current Capacity Planned Capacity
Hanbit Yeonggwang Jeonnam PWR 5900 5900
Hanul Uljin Gyeongbuk PWR 5900 11500
Kori Gijang Busan PWR 4137 10737
Wolsong Gyeongju Gyeongbuk PHWR 4635 4779
Breakdown by Reactor
Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Hanbit 1 PWR WH F   Operational 960 996 4 June 1981 25 August 1986
Hanbit 2 PWR WH F   Operational 958 993 10 December 1981 10 June 1987
Hanbit 3 PWR OPR-1000   Operational 997 1050 23 December 1989 31 March 1995
Hanbit 4 PWR OPR-1000   Operational 997 1049 26 May 1990 1 January 1996
Hanbit 5 PWR OPR-1000   Operational 997 1053 29 June 1997 21 May 2002
Hanbit 6 PWR OPR-1000   Operational 995 1052 20 November 1997 24 December 2002
Hanul 1 PWR France CPI   Operational 960 1003 26 January 1983 10 September 1988
Hanul 2 PWR France CPI   Operational 962 1008 5 July 1983 30 September 1989
Hanul 3 PWR OPR-1000   Operational 994 1050 21 July 1993 11 August 1998
Hanul 4 PWR OPR-1000   Operational 998 1053 1 November 1993 31 December 1999
Hanul 5 PWR OPR-1000   Operational 996 1051 1 October 1999 29 July 2004
Hanul 6 PWR OPR-1000   Operational 996 1051 29 September 2000 22 April 2005
Shin-Hanul 1 PWR APR-1400   Under construction 1340 1400 10 July 2012 2017
Shin-Hanul 2 PWR APR-1400   Under construction 1340 1400 19 July 2012 2018
Shin-Hanul 3 PWR APR-1400   Planned 1400
Shin-Hanul 4 PWR APR-1400   Planned 1400
Kori 1 PWR WH 60   Operational 576 608 27 April 1972 29 April 1978
Kori 2 PWR WH F   Operational 639 676 4 December 1977 25 July 1983
Kori 3 PWR WH F   Operational 1011 1042 1 October 1979 30 September 1985
Kori 4 PWR WH F   Operational 1010 1041 1 April 1980 29 April 1986
Shin-Kori 1 PWR OPR-1000   Operational 1000 1048 16 June 2006 28 February 2011
Shin-Kori 2 PWR OPR-1000   Operational 1000 1045 5 June 2007 20 July 2012
Shin-Kori 3 PWR APR-1400   Operational 1340 1400 16 October 2008 January 15, 2016
Shin-Kori 4 PWR APR-1400   Under construction 1340 1400 19 August 2009 2017
Shin-Kori 5 PWR APR-1400   Planned 1400
Shin-Kori 6 PWR APR-1400   Planned 1400
Wolsong 1 PHWR CANDU-6   Operational 657 687 30 October 1977 22 April 1983
Wolsong 2 PHWR CANDU-6   Operational 655 678 22 June 1992 1 July 1997
Wolsong 3 PHWR CANDU-6   Operational 684 698 17 March 1994 1 July 1998
Wolsong 4 PHWR CANDU-6   Operational 688 703 22 July 1994 1 October 1999
Shin-Wolsong 1 PWR OPR-1000   Operational 991 1043 20 November 2007 31 July 2012
Shin-Wolsong 2 PWR OPR-1000   Operational 960 1000 23 September 2008 26 February 2015

Research reactorsEdit

  • Aerojet General Nucleonics Model 201 Research Reactor
  • High-Flux Advanced Neutron Application Reactor, MAPLE class reactor
  • TRIGA General Atomics Mark II (TRIGA-Mark II) Research Reactor (decommissioned)
  • TRIGA General Atomics Mark III (TRIGA-Mark III) Research Reactor (decommissioned)

SpainEdit

Nuclear power plants in Spain (view)
  Active plants
  Closed plants
  Unfinished plants

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Almaraz 1 PWR WE-3 loops   Operational 1011 1049 3 July 1973 1 September 1983
Almaraz 2 PWR WE-3 loops   Operational 1006 1044 3 July 1973 1 July 1984
Ascó 1 PWR WE 3-loops   Operational 995 1033 16 May 1974 10 December 1984
Ascó 2 PWR WE-3 loops   Operational 997 1035 7 March 1975 31 March 1986
Cofrentes 1 BWR BWR-6   Operational 1064 1102 9 September 1975 11 March 1985
José Cabrera 1 PWR WE-1 loop   Shut down 141 150 24 June 1964 13 August 1969 30 April 2006
Lemoniz 1 PWR   Unfinished 1000 1972 1984
Lemoniz 2 PWR   Unfinished 1000 1972 1984
Santa María de Garoña 1 BWR BWR-3   Shut down 446 466 11 May 1971 15 February 1975 6 July 2013
Trillo 1 PWR KWU-3 loops   Operational 1003 1066 17 August 1979 6 August 1988
Valdecaballeros 1 BWR   Unfinished 975 1975 1984
Valdecaballeros 2 BWR   Unfinished 975 1975 1984
Vandellòs 1 GCR   Shut down 480 500 6 May 1972 2 August 1972 31 July 1990
Vandellòs 2 PWR WE-3 loops   Operational 1045 1087 29 December 1980 8 March 1988

Research reactorsEdit

SwedenEdit

Nuclear power plants in Sweden (view)
  Active plants
  Closed plants
  Unfinished plants

Power Station ReactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Ågesta 1 PHWR   Shut down 10 12 1 December 1957 1 May 1964 2 June 1974
Barsebäck 1 BWR ABB-II   Shut down 600 615 1 February 1971 1 July 1975 30 November 1999
Barsebäck 2 BWR ABB-II   Shut down 600 615 1 January 1973 1 July 1977 31 May 2005
Forsmark 1 BWR ABB-III, BWR-3000   Operational 984 1022 1 June 1973 10 December 1980
Forsmark 2 BWR ABB-III, BWR-3000   Operational 1122 1158 1 January 1975 7 July 1981
Forsmark 3 BWR ABB-III, BWR-3000   Operational 1187 1212 1 January 1979 18 August 1985
Oskarshamn 1 BWR ABB-I   Shut down 473 492 1 August 1966 6 February 1972 19 June 2017
Oskarshamn 2 BWR ABB-II   Shut down 638 661 1 September 1969 1 January 1975 14 October 2015
Oskarshamn 3 BWR ABB-III, BWR-3000   Operational 1400 1450 1 May 1980 15 August 1985
R4 1   Unfinished 130
Ringhals 1 BWR ABB-I   Operational 878 910 1 February 1969 1 January 1976 2020
Ringhals 2 PWR WE 3-loops   Operational 807 847 1 October 1970 1 May 1975 2019
Ringhals 3 PWR WE 3-loops   Operational 1064 1117 1 September 1972 9 September 1981
Ringhals 4 PWR WE 3-loops   Operational 1080 1140 1 November 1973 21 November 1983

Research reactorsEdit

Name Location Description Power Operational Current status
R1 KTH, Stockholm Research 1 MW 1954–1970 dismantled
R2 Studsvik Research, production of isotopes for industry 50 MW 1960–2005 shut down
R2-0 Studsvik Research, production of isotopes for industry 1 MW 1960–2005 shut down
Ågestaverket (R3) Farsta, Stockholm District heating 80 MW 1963–1973 shut down
R4 Marviken, Norrköping Research, plutonium production never completed abandoned in 1970
FR-0 Studsvik Research, zero-power fast reactor low 1964–1971 dismantled

SwitzerlandEdit

Switzerland Nuclear power plants (view)
  Active plants
  Closed plants

As of 8 December 2014, the Swiss parliament has voted to limit the operational life-time of Beznau I & II to no more than 60 years, and to enshrine a ban of constructing new reactors in the Constitution. However, this decision still has to pass the Council of States and it is likely that a referendum will be taken against such amendment. In addition, an Initiative of limiting the life-span of all nuclear reactors to 45 years will have to be voted upon the Swiss, irrespective of whether the legislature will actually enforce the constitutional amendment or not.[38]

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction
Start Date
Commercial
Operation Date
Decommissioning[39]
Type Model Net Gross
Beznau 1 PWR WH 2-loops   Operational 365 380 1 September 1965 1 September 1969 2029
Beznau 2 PWR WH 2-loops   Operational 365 380 1 January 1968 1 December 1971 2031
Gösgen 1 PWR PWR 3-loops   Operational 985 1035 1 December 1973 1 November 1979 not defined
Leibstadt 1 BWR BWR-6   Operational 1220 1275 1 January 1974 15 December 1984 not defined
Mühleberg 1 BWR BWR-4   Operational 373 390 1 March 1967 6 November 1972 2019[40]

Research reactorsEdit

SyriaEdit

TaiwanEdit

Nuclear power plants in Taiwan (view)
  Active plants
  Halted

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Jinshan 1 BWR BWR-4   Operational 604 636 2 June 1972 10 December 1978
Jinshan 2 BWR BWR-4   Operational 604 636 7 December 1973 15 July 1979
Kuosheng 1 BWR BWR-6   Operational 985 1,020 19 November 1975 28 December 1981
Kuosheng 2 BWR BWR-6   Operational 985 1,020 15 March 1976 16 March 1983
Lungmen 1 BWR ABWR   Unfinished[41] 1,300 1,350 31 March 1999
Lungmen 2 BWR ABWR   Unfinished 1,300 1,350 30 August 1999
Maanshan 1 PWR WE 312 3-loops   Operational 926 951 21 August 1978 27 July 1984
Maanshan 2 PWR WE 312 3-loops   Operational 928 951 21 February 1979 18 May 1985

Research reactorsEdit

ThailandEdit

Research reactorsEdit

TurkeyEdit

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Akkuyu NPP 1 VVER AES-2006   Under construction 1150 1197 14 April 2015
Akkuyu NPP 2 VVER AES-2006   Planned 1150 1197 2015
Akkuyu NPP 3 VVER AES-2006   Planned 1150 1197 2016
Akkuyu NPP 4 VVER AES-2006   Planned 1150 1197 2016
Sinop NPP 1 PWR ATMEA-1   Planned 1100 1150 2017
Sinop NPP 2 PWR ATMEA-1   Planned 1100 1150 2017
Sinop NPP 3 PWR ATMEA-1   Planned 1100 1150 2018
Sinop NPP 4 PWR ATMEA-1   Planned 1100 1150 2018

Research reactorsEdit

Fuel pilot plantsEdit

  • TRD Fuel Pilot Plant (Turkish Atomic Energy Authority)

UkraineEdit

Nuclear power plants in Ukraine (view)
  Active plants
  Closed plants
  Unfinished plants

Power station reactorsEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Chernobyl 1 LWGR RBMK   Shut down 740 636 1 March 1970 27 May 1978 30 November 1996
Chernobyl 2 LWGR RBMK   Shut down 925 1000 1 February 1973 28 May 1979 11 October 1991
Chernobyl 3 LWGR RBMK   Shut down 925 1000 1 March 1976 8 June 1982 15 December 2000
Chernobyl 4 LWGR RBMK   Inoperable 925 1000 1 April 1979 26 March 1984 26 April 1986
Chernobyl 5 LWGR RBMK   Unfinished 925 1000
Chernobyl 6 LWGR RBMK   Unfinished 925 1000
Khmelnytskyi 1 PWR VVER V-320   Operational 950 1000 1 November 1981 13 August 1988
Khmelnytskyi 2 PWR VVER V-320   Operational 950 1000 1 February 1985 15 December 2005
Khmelnytskyi 3 PWR VVER V-392B   Under construction 950 1000 1 March 1986 2018
Khmelnytskyi 4 PWR VVER V-392B   Under construction 950 1000 1 February 1987 2020
Rivne 1 PWR VVER V-213   Operational 381 420 1 August 1973 22 September 1981
Rivne 2 PWR VVER V-213   Operational 376 415 1 October 1973 29 July 1982
Rivne 3 PWR VVER V-320   Operational 950 1000 1 February 1980 16 May 1987
Rivne 4 PWR VVER V-320   Operational 950 1000 1 August 1986 6 April 2006
South Ukraine 1 PWR VVER V-302   Operational 950 1000 1 August 1976 2 December 1983
South Ukraine 2 PWR VVER V-338   Operational 950 1000 1 July 1981 6 April 1985
South Ukraine 3 PWR VVER V-320   Operational 950 1000 1 November 1984 29 December 1989
South Ukraine 4 PWR VVER V-320   Unfinished 950 1000
Zaporizhia 1 PWR VVER V-320   Operational 950 1000 1 April 1980 25 December 1985
Zaporizhia 2 PWR VVER V-320   Operational 950 1000 1 January 1981 15 February 1986
Zaporizhia 3 PWR VVER V-320   Operational 950 1000 1 April 1982 5 March 1987
Zaporizhia 4 PWR VVER V-320   Operational 950 1000 1 April 1983 14 April 1988
Zaporizhia 5 PWR VVER V-320   Operational 950 1000 1 November 1985 27 October 1989
Zaporizhia 6 PWR VVER V-320   Operational 950 1000 1 June 1986 17 September 1996

Research reactorsEdit

  • Kiev Institute for Nuclear Research
  • Sevastopol Institute of Nuclear Energy and Industry

United Arab EmiratesEdit

Name Unit
No.
Reactor Status Capacity in MW Construction Start Date Commercial Operation Date Closure
Type Model Net Gross
Barakah 1 PWR APR-1400   Under construction 13